Deliverable 11.1 Harmonization catalogue
Riechert, Uwe; Belda, Nadew Adisu; Smeets, Rene; Plet, Cornelis; Sørensen, Poul Ejnar; Göksu, Ömer;
Sharifabadi, Kamran; Chiesa, Nicola; Jahn, Ilka; Chaffey, Geraint
Total number of authors:
16
Publication date:
2019
Document Version
Publisher's PDF, also known as Version of record
Link back to DTU Orbit
Citation (APA):
Riechert, U., Belda, N. A., Smeets, R., Plet, C., Sørensen, P. E., Göksu, Ö., Sharifabadi, K., Chiesa, N., Jahn, I.,
Chaffey, G., Leterme, W., Kahlen, C., Despouys, O., Brantl, C., Bertinato, A., & Blasco-Gimenez, R. (2019).
Deliverable 11.1 Harmonization catalogue. European Commission. https://www.promotionoffshore.net/results/deliverables/
General rights
Copyright and moral rights for the publications made accessible in the public portal are retained by the authors and/or other copyright
owners and it is a condition of accessing publications that users recognise and abide by the legal requirements associated with these rights.
Users may download and print one copy of any publication from the public portal for the purpose of private study or research.
You may not further distribute the material or use it for any profit-making activity or commercial gain
You may freely distribute the URL identifying the publication in the public portal
If you believe that this document breaches copyright please contact us providing details, and we will remove access to the work immediately
and investigate your claim.
Deliverable 11.1
Harmonization catalogue
PROMOTioN – Progress on Meshed HVDC Offshore Transmission Networks
Mail info@promotion-offshore.net
Web www.promotion-offshore.net
This result is part of a project that has received funding form the European Union’s
Horizon 2020 research and innovation programme under grant agreement No 691714.
Publicity reflects the author’s view and the EU is not liable of any use made of the
information in this report.
PROJECT REPORT
DOCUMENT INFO SHEET
Document Name:
Harmonization catalogue
Responsible partner:
DTU
Work Package:
WP 11
Work Package leader:
Poul Sørensen, DTU
Task:
11.1
Task lead:
Poul Sørensen, DTU
DISTRIBUTION LIST
APPROVALS
Name
Company
Validated by:
Frank Wester
TenneT
Task leader:
Poul Sørensen
DTU
WP Leader:
Poul Sørensen
DTU
WP
Number
WP 11
Deliverable
Number
D11.1
WP Title
Person
months
Harmonization towards standardization
100
Deliverable Title
Type
Harmonization catalogue
Report
Start month
End month
25
48
Dissemination
level
Due month
38
ii
PROJECT REPORT
DOCUMENT HISTORY
Version
Date
Main modification
Author
5.4
2019-04-15
Edited introduction and GIS content from D15.2
Poul Sørensen
5.3
2019-04-07
Added TC95 and approved
Geraint Chaffey
5.2
2019-03-29
Comments on missing inputs incl revision of
Poul Sørensen
offshore consumption section based on Nicola’s
input
5.1
2019-02-27
Review version: Included Ömers updates to 3.4
Poul Sørensen
5.0
2019-02-24
V4.4 all accepted
Poul Sørensen
4.4
2019-02-24
Editing and adding IEC TC8
Poul Sørensen
4.3
2019-02-20
Update and review
Geraint Chaffey
4.2
2019-02-19
Update and review
Christina Brantl
4.1
2019-02-19
Update and review
Geraint Chaffey
4.0
2019-02-18
Version 3.15 with all changes accepted
Poul Sørensen
3.15
2019-02-17
Moved CIGRE SCA3 from 3.3.3 to 2.1.1 and
Poul Sørensen
updated IEC TC17A AHGs from 3.3.3 to 2.2.4
3.14
2019-02-14
Drafted 3.3 switchgear except for 3.3.4 GIS
Cornelis Plet
3.13
2019-02-13
Moved up general intro from 3.2 to Chapter 3
Geraint Chaffey
3.12
2019-02-11
Added switchgear WGs CIGRE SCA3 and
Rene Smeets
updated IEC TC17A AHGs to 3.3.3
3.10
2019-02-10
Update chapter 3.1, plus subchapters 3.2.1 and
Christina Brantl
3.2.2
3.9
2019-02-09
Update 3.4 including drafts for harmonics, grid
Poul Sørensen
forming and EMT modllling.
Draft conclusions regarding HVDC connected
WPPs
3.8
2019-02-04
Review 3.2.3 and 3.2.5
Ilka Jahn
3.7
2019-01-31
Drafts 3.4.3 grid forming and 3.4.5 FRT AC
Christoph Kahlen
3.6
2019-01-30
Updates 3.2 protection analysis
Geraint Chaffey
3.5
2019-01-24
Updates 3.2 protection analysis
Geraint Chaffey
3.3
2019-01-24
Updates 3.4 WPP ToC
Poul Sørensen
3.2
2019-01-23
Updates 3.2 protection analysis
Willem Leterme
3.1
2019-01-21
Updates 3.2 protection analysis
Geraint Chaffey
3.0
2019-01-21
Same as version 2.4, but in Feedback folder
Poul Sørensen
2.4
2019-01-14
Updates 3.2
Geraint Chaffey
2.2
2019-01-09
Section 3.2 first draft
Geraint Chaffey
2.0
2018-12-12
Taking back version 1.7 to WP11 directory
Poul Sørensen
1.7
2018-10-15
Editorial
Poul Søresnsen
iii
PROJECT REPORT
1.6
2018-09-06
Editorial + IEEE to Fig1 + bullets for 3.3
Poul Sørensen
1.5
2018-08-28
Added CIGRE SC C.1
Cornelis Plet
1.4
2018-08-19
Updated Fig 1, document history and contributers
Poul Sørensen
1.3
2018-08-07
Comments + added CIGRE B4-68 and C2/B4 38
Olivier Despouys
1.2
2018-08-07
Added China NB/T 42107
Rene Smeets
1.1
2018-07-19
Added scopes to CIGRE WGs
Geraint Chaffey
1.0
2018-07-15
None, just to move in Projectplace
Poul Sørensen
0.13
2018-07-13
Introduction + chapter 3-4 template
Poul Sørensen
0.12
2018-07-13
Grid codes
Christoph Kahlen
0.11
2018-07-10
IEEE
Ramon Blasco-Gimenez
0.10
2018-07-10
CIGRE SC-D1 AND SC-B3
Uwe Riechert
0.6
2018-07-09
CIGRE SC-B4+JWG
Geraint Chaffey
0.3
2018-06-04
CENELEC
Christina Brantl
0.2
2018-05-07
IEC TC115 & TC17, China GB/T
Nadew Adisu Belda
0.1
2018-05-07
Template and IEC TC88
Poul Sørensen
iv
PROJECT REPORT
LIST OF CONTRIBUTORS
Work Package 1 and deliverables 1.1, 1.5 & 1.7 involve a large number of partners and contributors. The names
of the partners, who contributed to the present deliverable or to one of its predecessors, are presented in the
following table.
PARTNER
NAME
ABB AB
Uwe Riechert
DNV GL
Nadew Adisu Belda, Rene Smeets, Cornelis Plet
DTU
Poul Sørensen, Ömer Göksu
EQUINOR
Kamran Sharifabadi, Nicola Chiesa
KTH
Ilka Jahn
KU Leuven
Geraint Chaffey, Willem Leterme
FGH
Christoph Kahlen
RTE
Olivier Despouys
RWTH Aachen
Christina Brantl
SGI
Alberto Bertinato
UPV
Ramon Blasco-Gimenez
v
PROJECT REPORT
CONTENT
Document info sheet ............................................................................................................................................................. ii
Distribution list ...................................................................................................................................................................... ii
Approvals ............................................................................................................................................................................. ii
Document history ................................................................................................................................................................ iii
List of Contributors ............................................................................................................................................................... v
1
2
Introduction.................................................................................................................................................................... 1
1.1
WP11 – Harmonization towards standardization ..................................................................................................... 1
1.2
D11.1 – Harmonization catalogue ........................................................................................................................... 2
Harmonization Groups and Documents ...................................................................................................................... 4
2.1
CIGRE ..................................................................................................................................................................... 4
2.1.1
SC A3. High Voltage Equipment...................................................................................................................... 4
2.1.2
SC B4. HVDC and Power Electronics ............................................................................................................. 6
2.1.3
SC C1. Power System Development and Economics ................................................................................... 14
2.1.4
SC C2. Power System Operation and Control............................................................................................... 14
2.1.5
SC C4. Power System Technical Performance ............................................................................................. 15
2.1.6
SC D1. Materials and Emerging Test Techniques......................................................................................... 15
2.2
IEC ......................................................................................................................................................................... 17
2.2.1
TC8. System aspects of electrical energy supply .......................................................................................... 17
2.2.2
TC17. High-voltage switchgear and controlgear ............................................................................................ 17
2.2.3
TC88. Wind energy generation systems........................................................................................................ 19
2.2.4
TC95. Measuring relays and protection equipment ....................................................................................... 27
2.2.5
TC115. High Voltage Direct Current (HVDC) transmission for DC voltages above 100 kV .......................... 28
2.3
CENELEC .............................................................................................................................................................. 29
2.3.1
2.4
IEEE-SA ................................................................................................................................................................ 31
2.5
Grid codes ............................................................................................................................................................. 32
2.5.1
Commission regulations (EU) ........................................................................................................................ 32
2.5.2
ENTSO-E ....................................................................................................................................................... 33
2.6
3
TC 8X System aspects of electrical energy supply........................................................................................ 29
Chinese standards ................................................................................................................................................. 34
Potential new contributions ....................................................................................................................................... 36
3.1
Specification and Control of HVDC systems ......................................................................................................... 36
3.1.1
Nomenclature ................................................................................................................................................ 36
3.1.2
Functional HVDC System Specification......................................................................................................... 37
vi
PROJECT REPORT
3.1.3
HVDC Converter Controls ............................................................................................................................. 38
3.1.4
Harmonic Models for MMCs .......................................................................................................................... 38
3.2
3.2.1
Design of protection systems......................................................................................................................... 39
3.2.2
Classification of protection systems: Fault separation concepts And Protection Philosophies ..................... 40
3.2.3
Performance evaluation of Protection System ............................................................................................... 40
3.2.4
Cable overvoltages ........................................................................................................................................ 41
3.2.5
Communication protocols .............................................................................................................................. 42
3.2.6
Communcation interfaces .............................................................................................................................. 43
3.2.7
Testing of protection devices ......................................................................................................................... 44
3.3
HVDC Switchgear .................................................................................................................................................. 44
3.3.1
Approach to Modelling of HVDC circuit breakers .......................................................................................... 45
3.3.2
Application and specification of HVDC circuit breakers ................................................................................. 46
3.3.3
Testing of HVDC circuit breakers .................................................................................................................. 47
3.3.4
GIS................................................................................................................................................................. 48
3.4
HVDC connected wind power plants ..................................................................................................................... 48
3.4.1
Harmonic emission and stability .................................................................................................................... 48
3.4.2
Grid forming control ....................................................................................................................................... 49
3.4.3
Black start capability ...................................................................................................................................... 50
3.4.4
Onshore frequency control from offshore wind .............................................................................................. 51
3.4.5
Fault-ride-through .......................................................................................................................................... 51
3.4.6
EMT modelling ............................................................................................................................................... 53
3.5
4
Protection of HVDC systems ................................................................................................................................. 39
Offshore consumption ........................................................................................................................................... 53
Initial workshops and Conclusions ........................................................................................................................... 55
4.1
Workshop on HVDC Control and Protection ......................................................................................................... 55
4.2
Workshop on HVDC connected wind power plants ............................................................................................... 55
4.3
Outlook .................................................................................................................................................................. 56
vii
PROJECT REPORT
1 INTRODUCTION
1.1
WP11 – HARMONIZATION TOWARDS STANDARDIZATION
In order to fully exploit the technical work within the PROMOTioN project, contribution to harmonisation is
strongly encouraged. The purpose of this Harmonization Catalogue is to provide a state-of-the-art regarding
harmonization of HVDC systems, identify gaps in this harmonization, and analyse how findings in the
PROMOTioN project can contribute. An overall conclusion is that PROMOTioN should contribute to ongoing
work in existing best practice and standard working groups rather than establish new working groups.
The Harmonization Catalogue is the first deliverable from PROMOTioN WP11 on Harmonization Towards
Standardization. It is intended to found a common basis for the work in WP11.
The overall objective of WP11 is to support and establish harmonization of the industry’s best practices,
standards and requirements for HVDC grid systems and DC connected offshore wind power plants. WP11 aims
to ensure that the experience collected through the project – including research and engineering in WP1-6, and
demonstrations in WP9, 10, 15 & 16 – is utilised in ongoing and future harmonization work. Those inputs to
WP11 are illustrated in the PROMOTioN work package structure shown in Figure 1.
Figure 1. PROMOTioN work package structure illustrating how WP11 aims to ensure that the experience collected through the
project – including research and engineering in WP1-6, and demonstrations in WP9, 10, 15 & 16 – is utilised in ongoing and
future harmonization work.
WP11 also aims to contribute to the harmonization of the work in existing and future working groups in IEC,
CENELEC, CIGRE, and in national as well as the European grid codes. Several of those working groups are
covering overlapping topics, and there is a need to ensure that this work is aligned.
1
PROJECT REPORT
WP11 includes the main HVDC system manufacturers and thereby ensure that the different manufacturer
concepts are considered in the relevant working groups.
The more specific objectives of WP11 are:
to provide a consistent and harmonised set of functional requirements to HVDC systems, wind power
plants and other AC systems connected to the HVDC systems;
to recommend test procedures for converters, protection systems, switchgear, wind turbines and plants
in HVDC systems;
to recommend requirements to models of HVDC systems and HVDC connected wind power plants;
to recommend best practice for compliance validation of wind power plants connected to HVDC
systems.
1.2
D11.1 – HARMONIZATION CATALOGUE
The purpose of the Harmonization Catalogue is to identify and analyse potential contributions from
PROMOTioN’s technical work packages to ongoing and possible new harmonization activities on offshore
HVDC transmission networks.
Figure 2 illustrates how the research, development and demonstration in PROMOTioN has a potential to
contribute to harmonization at different levels, in terms of “best practices”, “standards” and “requirements”.
IEA
CIGRE
IEEE
IEC
CENELEC
Grid codes
RD&D
Best
practice
Standard
Requirement
Figure 2. Research, development and demonstration (R&D&D) has a potential to contribute to harmonization in terms of “best
practices”, “standards” and “requirements”. The figure shows where different harmonization bodies are in this harmonization
scale.
Chapter 2 provides an overview of different harmonization groups and documents which have been identified as
relevant for the technical work in PROMOTioN.
Chapter 3 provides an analysis of the potential new contributions which PROMOTioN could have to
harmonisation.
2
PROJECT REPORT
Chapter 4 is the conclusions including recommendations to new harmonization initiatives which will be proposed
in workshops with harmonization groups.
3
PROJECT REPORT
2 HARMONIZATION GROUPS AND DOCUMENTS
2.1
2.1.1
CIGRE
SC A3. HIGH VOLTAGE EQUIPMENT
Working group
Number
Title
CIGRE JWG A3B434
Technical Requirements and Specifications of State-of-the-Art
HVDC Switching Equipment
Timeline
Past / Ongoing / Planned
Begin year
Past
2014
Promotion
partner
involvement
Scope
Person name(s)
Partner(s)
End year
2017
Role(s)
R.P.P. Smeets, N.A. Belda
DNVGL, Mitsubishi Electric
Secretary, members
(MEU), ABB
CIGRÉ Technical Brochure 683 extensively discusses the state-of-the-art, technical and
applicational background of HVDC switchgear. It overviews and categorizes the existing
HVDC switchgear in point-to-point connections in many projects. Transfer switches,
earthing switches, disconnection and paralleling switches are presented.
HVDC circuit breakers are discussed in greater depth, but from a conceptional point of
view, because no project information was available at the time of writing. First, the nature
of HVDC faults in systems have been described. Next. A definition of terminology,
describing the various phases in fault current interruption is proposed. Then, a detailed
overview of available technologies is presented (as present in PROMOTioN): passive
oscillation HVDC circuit breakers, active current injection HVDC circuit breakers, power
electronic HVDC circuit breakers and mechanical and power electronic hybrid HVDC
circuit breakers are defined and discussed. Extra attention is paid to the essential building
blocks: high-speed drives, surge arresters, semi-conductors and residual current
breakers.
A comparison is presented between the different HVDC breaker technologies, as well as
gaps have been identified between requirements (as far as known) and performance
specifications.
The last part discusses the test methods employed so far and proposes test methods, as
introduced in PROMOTioN
Documents
Number
CIGRE TB 683
(2017)
Title
Further
comments
This working group lies at the basis of the test methods, used in WP5, 10.
Working group
Number
Title
CIGRE WG A3-39
Application and field experience with Metal Oxide Surge Arresters
Technical Requirements and Specifications of State-of-the-Art HVDC
Switching Equipment
Timeline
Past / Ongoing / Planned
Begin year
Ongoing
2017
Promotion
partner
involvement
Scope
Person name(s)
Partner(s)
Role(s)
N.A. Belda
DNVGL
Guest
Documents
Number
Further
comments
-
End year
2020
This WG will report on a field survey of application of metal oxide surge arresters
(MOSA), which will include applications in HVDC switchgear.
Experience form WP 10 will be reported and discussed in the WG
Title
4
PROJECT REPORT
Working group
Number
Title
CIGRE WG A3-40
Technical requirements and field experiences with MV DC
switching equipment
Timeline
Past / Ongoing / Planned
Begin year
Ongoing
2018
Promotion
partner
involvement
Scope
Person name(s)
Partner(s)
Role(s)
N.A. Belda
DNVGL, SciBreak
Member
End year
2022
1. Collect the field experiences of MVDC switching equipment to interrupt the DC load
and fault current in MV applications up to 52 kV
2. Review the existing prototypes and state of the art of MV DC switching equipment up to
52 kV.
3. Review experiences of monitoring and diagnosing the interrupting performance with
MV DC switching equipment
4. Investigate the technical requirements for MVDC switching equipment used in different
system configurations such as a point-to-point or multi-terminals MV grids, and
understand the switching phenomena in MVDC grids
5. Summarize the technical requirements for the MVDC circuit breakers (compared with
those for AC circuit breakers and HVDC circuit breakers)
6. Recommend testing requirements for MVDC switching equipment
Documents
Number
Title
Further
comments
-
Working group
Number
CIGRE JWG
B4A3.80
Timeline
Past / Ongoing / Planned
Begin year
Ongoing
2019
Promotion
partner
involvement
Scope
Person name(s)
Partner(s)
Role(s)
R.P.P. Smeets
DNV GL, Mitsubishi Electric
Member
Title
HVDC Circuit Breakers - Technical Requirements, Stresses and
Testing Methods to investigate the interaction with the system
End year
2022
VSC-HVDC transmission is moving fast and is considered as the technology to realize the
development and integration of large-scale renewable energy sources, in order to achieve
high penetration and effective integration of the renewables and to mitigate the impacts of
intermittent renewables on the power system,The relatively independent and adjacent
VSC-HVDC systems can be interconnected together and step by step to form an HVDC
grid, such as the “Super Grid” plan in Europe and the Zhangbei ±500kV HVDC grid
project in China. The key element to establish HVDC grids in terms of efficiency and
reliability as well as controllability, is the realization of viable HVDC circuit breakers.
In 2013, technical brochure 533 “HVDC Grid feasibility study” prepared by WG B4.52 was
published. This TB points out that “technical feasibility of building a large scale HVDC
Grid requires that a fault has to be isolated very fast before it affects the HVDC voltage in
other parts of the grid”. Further, according to technical brochure 678 “Technical
requirements and specifications of HVDC switching equipment” published by JWG
A3/B4.34 in 2017, some HVDC circuit breakers prototypes have been completed and four
categories of topologies were established: adopting a passive oscillating circuit method, a
current oscillation system with active current injection, pure power-electronic devices in
the nominal current path, a hybrid mechanical and power-electronic combination. The DC
fault current can be quickly interrupted by the above stated technical solutions in the order
of milliseconds. However, the interruption time will be a function of the circuit chosen.
The fault current interrupting requirements will be driven by the system requirements and
the functional specifications. However, it is very important to define the corresponding
stresses and test methods for HVDC circuit breakers to ensure that the HVDC circuit
5
PROJECT REPORT
breakers do meet such requirements. It is necessary and important to provide guidelines
on how and the methodology available for testing of the different types of HVDC circuit
breakers will ensure that the stresses are not exceeded and the performance functions
are met.
This WG will work in the close collaboration of SC A3. For this purpose, SC B4 will send a
liaison to participate in WG A3.40. The detailed work will take into account technologies
and results reported in the recent (August, 2018) collaborated CIGRE/IEEE workshop
with the EU PROMOTioN project, as well as the results reported by IEC SC17A/AHG 60
(on HVDC switchgear).
Scope:
The objectives of this Working Group are to perform a technical requirement and stresses
study to investigate the interaction between HVDC circuit breakers and the system from
both simulation and experiment approaches. Based on the results of the study, the
stresses imposed on the circuit breaker will be defined. Based on the above, the detailed
technical requirements and required testing methods of HVDC circuit breakers will be
proposed
Documents
Number
Further
comments
Will have strong input from PROMOTioN WP 5, 10 results
Its tasks are:
1. Describe basic configurations and overview of the HVDC circuit technologies available
in the market and under research / development, including different designs of HVDC
circuit breakers investigated in PROMOTioN project and other research projects in
different countries.
2 Describe possible applications of HVDC circuit breaker and define technical
requirements of HVDC CBs for these different applications;
3 Study specific component stresses (relevant to testing) under continuous operation,
load switching and fault current switching. Specific attention will be given to behaviours
due to operation of mechanical or hybrid switches, current commutation as well as energy
dissipating processes within the equipment.
4 Specify testing methods for component and equipment;
2.1.2
Title
SC B4. HVDC AND POWER ELECTRONICS
Working group
Number
Title
B4
HVDC and power electronics
Timeline
Past / Ongoing / Planned
Begin year
End year
Promotion
partner
involvement
Scope
Person name(s)
Partner(s)
Role(s)
Kamran Sharifabadi
STATOIL
?
Olivier Despouys
RTE
French Regular Member
The work of the Study Committee addresses all the relevant Target Groups in Power
Industry interested in Power Electronics. In addition to technical aspects also economical
and environmental subjects of this technology and asset management are covered.
The Study Committee activities include the following subjects:
HVDC: economics of HVDC, applications, planning aspects, design, performance,
control, protection, control and testing of converter stations, i.e. the converting equipment
itself and also the equipment associated with HVDC links.
Power Electronic for AC systems and Power Quality Improvement: economics, applications, planning, design, performance, control, protection, construction and testing.
Advanced Power Electronics: development of new converter technologies including controls, use of new semiconductor devices, applications of these technologies in HVDC,
Power Electronics for AC systems and Power Quality Improvement. Power Electronics
used in other fields of the Electric Power Industry , interesting for other Study
6
PROJECT REPORT
Committees, will be covered by demand, this Committee being the Sponsoring
Committee
Working group
Number
Title
JWG B4/B5-59
Control and Protection of HVDC Grids
Timeline
Past / Ongoing / Planned
Begin year
Ongoing
2011
Promotion
partner
involvement
Scope
Person name(s)
Partner(s)
Role(s)
Willem Leterme
KUL
Member
Documents
Number
Title
TB 739
Protection and local control of HVDC grids
End year
2018
Functional requirements for protection, short circuit phenomena, short circuit current
limiting techniques, protection system components, protection system overview.
Further
comments
Working group
Number
Title
JWG B4/B1/C1-73
Surge and extended overvoltage testing of HVDC Cable Systems
Timeline
Past / Ongoing / Planned
Begin year
Ongoing
2016
Promotion
partner
involvement
Scope
Person name(s)
Partner(s)
Role(s)
Willem Leterme
KUL
Member
Documents
Number
End year
2018
Cable overvoltage considerations. Including: History and present practice, stresses with
new technology, severity, statistics and testing schemes and equipment.
Title
Further
comments
Working group
Number
Title
CIGRE WG B-74
Guide to Develop Real-Time Simulation Models (RTSM) for HVDC
Operational Studies
Timeline
Past / Ongoing / Planned
Begin year
Ongoing
2016
Promotion
partner
involvement
Scope
Person name(s)
Partner(s)
Role(s)
Firew Dejene
KUL
Member
Documents
Number
End year
2018
Introduction to operational studies, RTSM for HVDC equipment, Slow acting control
system models, RTSM of AC system, Model validation and testing, guidelines for studies.
Title
Further
comments
Working group
Number
Title
CIGRE WG B4-67
Harmonic aspects of VSC HVDC, and appropriate harmonic limits
Timeline
Past / Ongoing / Planned
Begin year
Ongoing
2014
Promotion
partner
involvement
Person name(s)
Partner(s)
Role(s)
Jef Beerten (via Geraint
Chaffey)
KUL
Member
End year
Finalising
7
PROJECT REPORT
Scope
The traditional requirement of harmonic limits is being challenged by the integration of
VSCs. Particularly, the harmonic spectrum significantly varies compared to traditional
loads. Besides steady-state harmonics, instabilities can appear because of the interaction
between converter control dynamics and AC network resonances. The WG determines
the future need to represent better the AC network and converters in order to address
system stability and harmonic studies.
Documents
Number
Title
Further
comments
Working group
Number
Title
CIGRE WG B4-68
DC Harmonics and Filtering
Timeline
Past / Ongoing / Planned
Begin year
Ongoing
2016
Promotion
partner
involvement
Scope
Person name(s)
Partner(s)
End year
2018
Role(s)
CIGRÉ Technical Brochure 92 “DC Side Harmonics and Filtering in HVDC Transmission
Systems” (1994) was prepared by Task Force 2 of WG14.03. It is an extensive treatment
of the subject, has been quoted in numerous Technical Specifications for HVDC Projects,
and is not known to contain any technical errors. However, the typed format of the
Brochure is outdated and makes it a little difficult to read and to access key information.
The Brochure itself, being quite old, has slipped out of people’s knowledge – to the extent
that the appropriate IEC group dealing with this area recently stated that there was no
CIGRÉ publication on DC filters.
There are also aspects of the document which could be improved. It is therefore proposed
that a revision of this Technical Brochure should be undertaken. The revised document
could then be used by IEC in the normal process of adopting the technical work which
flows from CIGRÉ
Documents
Number
Title
Further
comments
Working group
Number
Title
CIGRE WG B4-64
Impact of AC System Characteristics on the Performance of
HVDC schemes
Timeline
Past / Ongoing / Planned
Begin year
Ongoing
2014
Promotion
partner
involvement
Scope
Person name(s)
Partner(s)
Documents
Number
End year
Finalising
Role(s)
Jef Beerten (via Geraint
KUL
Convener
Chaffey)
The WG analyses the limitations of the SCR or short-circuit based calculations in giving
an indicator related to the system strength. The WG has determined that networks with a
large infeed of converters are significantly influenced by the AC voltage control of these
converters and consequently, the system strength is also influenced by their controls.
Short-circuit based calculations neglect up to a large extent the control operating mode.
Therefore, other converter representations need to be used.
Title
Further
comments
8
PROJECT REPORT
Document
Number
Title
TB 269
VSC Transmission
Timeline
Begin year
Scope
This Brochure describes VSC Transmission technology, i.e. HVDC transmission using
Voltage Sourced Converters. A comparison with Line Commutated HVDC technology is
provided. The WG found no technical reason why this technology could not be used at
high voltage and power, and concluded that such development would depend solely on the
perceived commercial return on the R&D investment.
End year
Stage
2005
Published
Further
comments
Document
Timeline
Scope
Number
Title
TB 337
Increased System Efficiency by Use of New Generations of Power
Semiconductors
Begin year
End year
Stage
2007
Published
The TB presents the present developments of power semiconductors, with lower losses,
higher switching frequency, converter modularization…, and their new application areas,
in order to propose and evaluate new or enhance equipment for increased system
efficiency.
Further
comments
Document
Number
Title
TB 364
Systems with multiple DC Infeed
Timeline
Begin year
Scope
The TB provides an analytical framework for the understanding of interactions amongst
multiple HVDC line commutated inverter stations within a common ac system. The
theoretical development is complemented by actual system examples of multi-infeed
HVDC planning
End year
Stage
2008
Published
Further
comments
Document
Number
Title
TB 370
Integration of large Scale Wind Generation using HVDC and Power
Electronics
Timeline
Begin year
Scope
New large wind farms, both onshore and offshore, may face challenges such as, system
stability issues, the need for the wind farm to provide system/ancillary services, and
difficulties to build overhead lines. The TB shows how HVDC and other types of Power
Electronics can help overcome these challenges, thereby helping to integrate large scale
wind farms into power systems.
End year
Stage
2009
Published
Further
comments
Document
Timeline
Scope
Number
Title
TB 388
Impacts of HVDC lines on the economics of HVDC projects
Begin year
End year
Stage
2009
Published
The study considers the overall HVDC system economics, capital (lines and stations),
losses, operation and maintenance. The most economically favorable voltages and
conductor configurations are studied for several HVDC system alternatives. It is shown
how the HVDC line and the converter stations selection impact each combination.
9
PROJECT REPORT
Directives are presented on the 'best-solutions' for different sets of transmission
parameters.
Further
comments
Document
Timeline
Scope
Number
Title
TB 492
Voltage Source Converter (VSC) HVDC for Power Transmission Economic Aspects and Comparison with other AC and DC
Technologies
Begin year
End year
Stage
2012
Published
The objective of the WG was to develop an assessment process to evaluate the
beneficial impact of VSC-HVDC on power systems. The proposed methodology includes
a straightforward analysis of important environmental facts that have to be taken into
account for an appropriate assessment. Case studies have been provided in order to
demonstrate the application of the proposed methodology. This WG gives a snapshot on
the current technology, application areas and economic values. With ongoing
developments it can be expected that VSC-HVDC will become even more attractive for
bulk power transmission and might become an economic feasible alternative to other
technologies.
Further
comments
Document
Timeline
Scope
Number
Title
TB 533
HVDC Grid Feasibility Study
Begin year
End year
Stage
2013
Published
Until now most HVDC schemes have been point to point connections. A few multiterminal schemes have been built with one extra terminal. But there have been many
discussions of using HVDC for more advanced grids. The TB investigates the technical
and economic feasibility to build such HVDC grids. The first question to answer is if
HVDC grids offer any advantage over many point to point HVDC connections inside an
AC grid. Another important question is if it will be possible to build HVDC breakers that
are necessary to make the grid reliable. One more question is if one can make
protections and control to the grid. These and many other challenging questions are
studied in the Brochure.
Further
comments
Document
Timeline
Scope
Number
Title
TB 536
Influence of Embedded HVDC Transmission on System Security and
AC Network Performance
Begin year
End year
Stage
2013
Published
This brochure highlights the gain in flexibility provided by an embedded HVDC link
(defined as a DC link with at least two ends connected to a single synchronous AC
network) for an existing HVAC grid. It also points out the possible technical issues that
may arise, along with the different capabilities and performances depending on the
underlying DC technology. Illustrations through existing or planned projects are proposed,
in addition to open models for a benchmark network and VSC converters.
Further
comments
Number
Title
10
PROJECT REPORT
Document
TB 563
Timeline
Begin year
Scope
Modelling and Simulation Studies to be performed during the lifecycle
of HVDC Systems
End year
Stage
2013
Published
The purpose of this CIGRE TB is to provide an overview of the simulation tools, models
and study procedures typically required at different stages of the lifecycle of an HVDC
system. The document classifies the lifecycle of HVDC into five main phases: studies for
planning and preparation of technical specification of an HVDC project; studies performed
during bid process; post award studies; studies performed for commissioning, studies
over the operational life of the HVDC system. For each stage the brochure presents the
objectives, required input data and results of the main simulation studies as well as
discusses the study related responsibilities between the entities involved to the HVDC
project. The brochure also presents examples how the main simulation tools presented in
the brochure are applied for HVDC lifecycle related studies.
Further
comments
Document
Timeline
Scope
Further
comments
Document
Timeline
Scope
Number
Title
TB 604
Guide for the Development of Models for HVDC Converters in a HVDC
Grid
Begin year
End year
Stage
2014
Published
This TB documents the requirements of simulation models for modular multi-level voltagesourced converters (MMC-VSC) that would form the basis of a DC Grid and provides a
framework for model development that is consistent with known MMC-VSC technologies
presently used. This framework can be adapted to changing power electronic topologies
and control algorithms. In addition, a 9 bus DC Grid test system was developed and
documented. Two and four bus test systems that are subsets of the 9 bus system are
also presented.
Basis for modelling of HVDC converters in WP2
Number
Title
TB 619
HVDC connection of offshore wind power plants.
Begin year
End year
Stage
2015
Published
The first wave of HVDC connected offshore wind power plants (WPPs) has been
commissioned and many more are planned in the North Sea, along with other sites
around the world. VSC-based HVDC has become the preferred solution for large offshore
WPPs, with cable distances typically above 100 km (including both offshore cable and on
shore cable to the converter terminal) to the AC grid connection point. This is largely due
to several technology advantages offered by VSCs, when compared to other HVAC or
HVDC options, resulting in a more economically attractive transmission solution. In
addition, a number of HVDC submarine cable connections for power exchange between
countries are being planned and the possibility of connecting WPPs to these
interconnections, and to future HVDC grids, are being seriously considered. The issues
associated with expanding a WPP and HVDC connections with equipment from multiple
vendors are subjects which need to be developed further, but are outside the scope of
this brochure. Compliance with Grid Codes (GCs), which define the performance during
normal and abnormal operating conditions, is another subject area in need of further
development. Existing GCs are however written for AC connected WPPs, and for an
offshore WPP these conditions typically apply only at the AC grid connection point. This
raises the possibility of optimizing the overall WPP and the HVDC converter, with
potential economic and maintenance benefits. However, if the HVDC connection and the
WPP are provided by different vendors, such optimization cannot be done properly unless
concerns about IP rights and operation benefits are clearly laid out and understood by all
stakeholders involved. Guidelines and recommendation for point to point and multi
terminal HVDC connection of offshore WPPs are therefore highly needed and of mutual
11
PROJECT REPORT
interest for the HVDC and WTG industries in order to be able to provide the best possible
solutions for all stakeholders.
Further
comments
Document
Timeline
Scope
Number
Title
TB 657
Guidelines for the preparation of "connection agreements" or "Grid
Codes" for multi-terminal schemes and DC Grids
Begin year
End year
Stage
2016
Published
In the light of recent advancement of HVDC technology and the prospect of DC grid
projects a need to address the required guide lines to develop the DC grid codes has
arisen. Grid Codes or network codes are a set of rules and guidelines that govern a
power system environment with multiple stakeholders, which describe e.g. the technical
requirements that the equipment must fulfil in order to be integrated in the system and the
rules and guidelines for interactions between the systems and stakeholders under steady
state or abnormal operation conditions. This brochure provides recommendations on the
models of interactions between the stakeholders and activities from planning to operation
including technical aspects of planning, building and operation of a DC grid. Based on
these recommendations a specific (set of) grid code(s) can be developed for the DC grid.
The focus of this document is on the MTDC grids, and not on the HVAC networks which
are connected to these DC grids. The objective of this brochure is to support the
concerned stakeholders i.e. system planners, system operators (SO) and system users,
to develop their own particular DC grid code
Further
comments
Document
Timeline
Scope
Number
Title
TB 671
Connection of wind farms to weak AC networks
Begin year
End year
Stage
2016
Published
Issues with connection of wind power plants (WPP) to weak AC systems and how to
improve the performance of these systems have been addressed. The working group has
also investigated the interactions between wind generator converter systems, power
system, and other power electronic in the vicinity. Guidelines for screening of potential
connection points, selection of WPP models, and possible avenues for mitigating these
issues are provided.
Further
comments
Document
Timeline
Scope
Further
comments
Number
Title
TB 683
Technical requirements and specifications of state-of-the-art HVDC
switching equipment
Begin year
End year
Stage
2017
Published
The new applications projected for future DC grids and multi-terminal DC systems at
different voltages suggest that various DC equipment may be required; in particular all
sorts of switching devices. However, the requirements for DC switching capabilities are
different from those for AC equipment. In the brochure, a review of the technical
requirements of HVDC switching equipment and an overview on the technical capabilities
and limitations of existing switching equipment is given. Included are all sorts of
switchgear such as disconnecting switches, earthing switches, transfer switches, and
especially circuit breakers.
Results to be addressed by IEC TC 17A AHG60
12
PROJECT REPORT
Document
Timeline
Scope
Number
Title
TB 684
Recommended voltages for HVDC grids
Begin year
End year
Stage
2017
Published
This technical brochure provides guidance for system planners and designers to choose
the optimal DC voltage for High Voltage Direct Current (HVDC) grids. This includes a
clear technical definition for the “DC voltage” in line with current practices and standards,
a list of recommended values based on technical considerations and drivers from system
planning, and a flowchart to guide the selection of the optimal voltage for individual
projects.
Further
comments
Document
Timeline
Scope
Number
Title
TB 699
Control methodologies for direct voltage and power flow in a meshed
HVDC grid
Begin year
End year
Stage
2017
Published
This brochure provides the requirements and the classification of different control
methods, including the coordinated system control, in order to ensure system security and
efficient operation of the combined AC and HVDC system in an electricity market
environment. In addition, a range of power flow controlling devices is described for
efficient utilization of overhead lines and cables in the HVDC grid. The main focus for the
technical brochure is on static control characteristics.
Further
comments
Document
Timeline
Scope
Number
Title
TB 713
Designing HVDC grids for optimal reliability and availability
performance
Begin year
End year
Stage
2018
Published
This Technical Brochure addresses the question of how to design a DC grid to achieve
optimal reliability and availability performance. The starting point was to consider a
suitable metric which could be used to assess the reliability and availability performance
of the grid. Anticipating that a DC grid may not have an overall “architect”, the brochure
considers the evolution of the grid from smaller radial and meshed multi-terminal systems
and the factors which need to be considered when incorporating such building blocks to
ensure that the grid can achieve high levels of reliability and availability. The technologies
used at the AC to DC converter stations and at DC switching stations are discussed in the
brochure in terms of their impact on the grid. The interconnecting medium between grid
stations, whether overhead transmissionlines, underground cables or submarine cables,
will also have a major impact on the grid in terms of their susceptibility to internal or
external faults. The design of a DC grid will require analytical techniques to assess
whether the evolving grid is able to achieve the desired levels of reliability and availability
performance. The brochure includes an example of such a study, based on a
deterministic evaluation of a DC grid test model, to illustrate the impacts of specific
outage conditions on the energy not served by the grid. This study is presented as an
illustrative example only and is not proposed as the methodology for future evaluations of
DC grids, as other methods, including probabilistic techniques, may be adopted.
Further
comments
13
PROJECT REPORT
2.1.3
SC C1. POWER SYSTEM DEVELOPMENT AND ECONOMICS
Working group
Number
Title
WG C1.33
Interface & Allocation Issues in multi-party and/or cross-jurisdiction
power infrastructure projects
Timeline
Past / Ongoing / Planned
Begin year
Ongoing
2016
Promotion
partner
involvement
Scope
Person name(s)
Partner(s)
Role(s)
Cornelis Plet
DNV GL
Corresponding member
End year
2019
The increasing need for cross-border links and cross-sector (e.g. transmission-distribution) planning,
as well as the growing diversification of relevant regulatory & market arrangements, call for deeper
consideration of the evaluation principles and allocation criteria for costs, benefits and related risks
on both sides of the link.
The investigated dimensions for a new planned cross-jurisdiction project will be:
- Allocation of cost / benefit / risk between countries and between grid operators
- Allocation of asset ownership & responsibilities
- Authorization / permitting of the same project in several jurisdictions
- Legislation / regulation traps & gaps (for example EU/non-EU links)
- Regulation and tariff applied on assets outside own jurisdiction
- Investment schemes (public, private, mixed) and relevant governance (e.g. delivery company, etc.)
- Business models set-up for economic feasibility and financial viability.
Documents
This will be done in a structured way in order to:
- Identify the challenges (in particular non-technical) for cross-jurisdiction projects;
- Assess the different economic drivers for the different cases;
- Explore advantages and disadvantages of the options for implementation schemes of multi-party
projects;
- Map the different possible business models, also considering asymmetric and unilateral investment
schemes (for public lines), and the conditions imposed on Third Party Access exemptions (for
merchant lines);
- Study the interface issues and applicable business models for coordinated grid planning with
neighbouring networks (distributors, active consumer grids, storage devices);
- Try to extend the analysis from single lines to portion of grids (e.g. off-shore grids).
Number
Title
Further
comments
2.1.4
SC C2. POWER SYSTEM OPERATION AND CONTROL
Working group
Number
Title
JWG C2/B4.38
Capabilities and requirements definition for Power Electronics
based technology for secure and efficient system operation and
control
Timeline
Past / Ongoing / Planned
Begin year
Ongoing
2017
Promotion
partner
involvement
Scope
Person name(s)
Partner(s)
Role(s)
Olivier Despouys
RTE
Member
End year
2019
The main scope of this Joint Working Group will be assessing best practices, technology
capabilities and requirements for the integration of power electronics based technologies
in the electrical power system, with the focus on its usage for system operations and
control, taking advantage of the technical strengths, and mitigate the weaknesses.
The main activities will focus on:
1. Reviewing previous CIGRE (e.g. SC B4, SC C6) and other work in this domain.
14
PROJECT REPORT
2.
3.
4.
5.
Documents
Researching and describing world-wide implemented solutions and best operational
and control practices with Power Electronics based equipment, building an overview
on installed systems and developed solutions.
Identifying Power Electronics technology integration capabilities and control issues
relevant for system operations, including further steps to better define the
requirements and adequately utilise the various Power Electronics based network
components.
Defining best practices for Power Electronics based technology used in system
operation and control, including implementation in connection requirements and
possible description of necessary analysis.
Recommending areas for further research and development, in order to gain new
insights.
Number
Title
Further
comments
2.1.5
SC C4. POWER SYSTEM TECHNICAL PERFORMANCE
Working group
Number
Title
C4.49
Multi-frequency stability of converter-based modern power
systems
Timeline
Past / Ongoing / Planned
Begin year
Ongoing
2018
Promotion
partner
involvement
Scope
Documents
Person name(s)
Partner(s)
Role(s)
Łukasz H. Kocewiak
Ørsted
Convenor
Number
End year
-
Title
Further
comments
2.1.6
SC D1. MATERIALS AND EMERGING TEST TECHNIQUES
Working group
Number
Title
JWG N° D1/B3.57
Dielectric Testing of gas-insulated HVDC Systems
Timeline
Past / Ongoing / Planned
Begin year
Ongoing
2014
Promotion
partner
involvement
Scope
Documents
Person name(s)
Partner(s)
Role(s)
Uwe Riechert
Alain Girodet
ABB
SGI
Member
Member
Number
End year
Finalising
Title
Further
comments
Document
Timeline
Scope
Number
Title
TB 506
Gas Insulated Systems for HVDC: DC Stress at DC and AC Systems
Begin year
End year
Stage
2012
Published
The following items are the main targets for the study in order to realize compact and
highly reliable HVDC equipment:
15
PROJECT REPORT
(1) Insulation characteristics in gas gap and of insulator surface,
(2) Design of insulators for DC applications,
(3) Charge accumulation characteristics on insulator surface and methods for
their measurement,
(4) Particle motions and measures for particle trapping,
(5) Detection and analysis of partial discharges in HVDC applications,
(6) Residual DC voltages and insulation characteristics of equipment with DC
pre-stress at AC system.
This Technical Brochure introduces and discusses the insulation characteristics under DC
stress at DC and AC systems for gas insulated HV equipment such as GIS and GCB,
considering the above issues and referring to the latest research. It summarizes the key
technologies for practical GIS and GCB and will be a useful guidance to realize future
compact and highly reliable high-voltage equipment.
Further
comments
16
PROJECT REPORT
2.2
2.2.1
IEC
TC8. SYSTEM ASPECTS OF ELECTRICAL ENERGY SUPPLY
Working group
Number
Title
IEC TC8 / SC8A /
AHG3
Roadmap of grid integration of renewable energy generation
Timeline
Past / Ongoing / Planned
Begin year
Ongoing
2018
2019
Promotion
partner
involvement
Scope
Person name(s)
Partner(s)
Role(s)
Mr Ramón Blasco Giménez
UPV
Member
Documents
Number
Further
comments
The task (project 2 above) on “Evaluation on the standardization of DC Technology and
AC/DC Hybrid systems for RE integration and other needs” is allocated under
SC8A/AHG3 in collaboration with SC8B/AGH2.
2.2.2
End year
To collect information from regulatory contents including network codes, policies, relevant
issues in different countries, and work out a roadmap for SC 8A, which will mainly
address the technology development tendency, nowadays best practices of RE grid
integration, and the future standardization activities of SC 8A, in cooperation with the
other relevant TCs and liaison organizations.
Presently, there are two projects under AHG 3:
1. Roadmap of Grid Integration of Renewable Energy Generation
2. Evaluation on the standardization of DC Technology and AC/DC Hybrid systems
for RE integration and other needs
Title
TC17. HIGH-VOLTAGE SWITCHGEAR AND CONTROLGEAR
Working group
Number
Title
IEC TC17 AHG4
DC switchgear
Timeline
Past / Ongoing / Planned
Begin year
Past
2016
Promotion
partner
involvement
Scope
Person name(s)
Partner(s)
Documents
Number
IEC 17/1032/INF
(2017)
End year
2017
Role(s)
R.P.P. Smeets
DNVGL, ABB, Mitsubishi
Member
Electric (MEU)
To investigate market relevance of DC switchgear and the need for standardization.
This covers all technical aspects of air and gas-insulated switchgear for indoor and
outdoor applications. Switchgear voltages above 1,5 kV d.c.
The findings of the AHG were presented at the TC 17 meeting in April, 2017.
This WG prepared an inventory on (pre-)standardization documents already available:
1. IEC TC 115 WG9 is drafting a standard on HVDC power system requirements for DC
side equipment (including DC switchgear but excluding DC circuit-breakers).
2 Various Chinese national standards have been issued:
GB/T 25307 (2010) on HVDC bypass switches;
GB/T 25309 (2010) on HVDC transfer switches;
GB/T 25091 (2010) on HVDC disconnecting- and earthing switches;
A GB standard on HVDC circuit-breakers is being drafted.
Title
Final report of Ad Hoc Group 4 Switchgear
17
PROJECT REPORT
Further
comments
Based on the outcome, IEC TC 17 decided to create a follow-up Ad Hoc Group in 2017
Document
Number
Timeline
Scope
Title
IEC TC17
DC switchgear assemblies
SC17C
AHG37
Stage
Begin year
End year
2017
2018
running
Task: Proposal for standardization of DC switchgear assemblies.
This covers all technical aspects of air and gas-insulated switchgear for indoor and
outdoor applications. Switchgear voltages above 1,5 kV d.c.
Further
comments
18
PROJECT REPORT
Working group
Number
Title
IEC TC 17A AHG60
DC switchgear
Timeline
Past / Ongoing / Planned
Begin year
Past
2017
Promotion
partner
involvement
Scope
Person name(s)
Partner(s)
Documents
Number
IEC 17A/1200/INF
(2017)
Further
comments
Based on the outcome, IEC TC 17A decided Nov. 2018 to initiate work on four separate
documents covering requirements and tests on DC switchgear
2.2.3
End year
2018
Role(s)
R.P.P. Smeets
DNVGL, ABB, Mitsubishi
Member
Electric (MEU)
To have a further look at document 17/1032/INF to determine if there is a need for
standardization of DC switchgear. AHG 60 was formed with the task to further analyze
document 17/1032/INF and make recommendations to SC 17A.
Task of this WG is to make an analysis of standardization documents issued already.
On of these is NB/T 42107, 2017: Chinese standard for DC circuit-breakers. This
document has been analyzed, and its test requirements have been compared with HVAC
breaker test-requirements laid down in IEC 62271-100. Ratings, dielectric testing and
basic interruption duties were discussed.
Based on the analysis outlined in this document AHG 60 makes the following
recommendations to TC 17 and SC 17A. The order in which the switchgear appears does
not necessarily reflect the order in which their standards or other deliverables should be
developed.
– To elaborate a document covering common specifications of HVDC switchgear;
– To elaborate documents covering DC circuit-breakers, current transfer switches, DC
disconnectors and earthing switches and DC by-pass switches;
– The status of the documents, i.e. PAS, TS or IS should be decided by the TC or SC
concerned.
Title
Final report of Ad Hoc Group 60 Switchgear
TC88. WIND ENERGY GENERATION SYSTEMS
Working group
Number
Title
TC88 WG21
Wind energy generation systems –
Measurement and assessment of electrical characteristics
Timeline
Past / Ongoing / Planned
Begin year
Ongoing
1997
Promotion
partner
involvement
–
Person name(s)
Partner(s)
Role(s)
End year
Scope
Poul Sørensen
DTU
Member
Lukasz Kocewiak
Ørsted
Member
Ömer Göksu
The scope of this working group is to specify test and measurement procedures for
electrical characteristics of wind turbines and wind power plants. The electrical
characteristics include power quality aspects, control performance such as power control,
reactive power control, voltage control, frequency control, as well as grid protection test.
Documents
Number
Title
IEC 61400-21
IEC 61400-21-1
IEC 61400-21-2
IEC 61400-21-3
Wind turbines
Wind turbines
Wind power plants
Technical Report: Wind turbine harmonic model and its application
Further
comments
19
PROJECT REPORT
Document
Timeline
Scope
Number
Title
IEC 61400-21
Ed2
TC88. Wind turbines –
Part 21. Measurement and assessment of power quality
characteristics of grid connected wind turbines
Begin year
End year
Stage
1997
2008
Published
This part of IEC 61400 includes:
– definition and specification of the quantities to be determined for characterizing
the power
– quality of a grid connected wind turbine;
– measurement procedures for quantifying the characteristics;
– procedures for assessing compliance with power quality requirements, including
estimation
– of the power quality expected from the wind turbine type when deployed at a
specific site,
– possibly in groups.
The measurement procedures are valid for single wind turbines with a three-phase grid
connection, and as long as the wind turbine is not operated to actively control the
frequency or voltage at any location in the network. The measurement procedures are
valid for any size of wind turbine, though this standard only requires wind turbine types
intended for PCC at MV or HV to be tested and characterized as specified in this
standard.
The measured characteristics are valid for the specific configuration of the assessed wind
turbine only. Other configurations, including altered control parameters that cause the
wind
turbine to behave differently with respect to power quality, require separate assessment.
The measurement procedures are designed to be as non-site-specific as possible, so that
power quality characteristics measured at for example a test site can be considered valid
also at other sites.
The procedures for assessing compliance with power quality requirements are valid for
wind turbines with PCC at MV or HV in power systems with fixed frequency within ±1 Hz,
and sufficient active and reactive power regulation capabilities and sufficient load to
absorb the wind power production. In other cases, the principles for assessing
compliance with power quality requirements may still be used as a guide.
Further
comments
20
PROJECT REPORT
Document
Timeline
Scope
Number
Title
IEC 61400-21-1
TC88. Wind energy generation systems.
Part 21-1. Measurement and assessment of electrical characteristics –
Wind turbines.
Begin year
End year
Stage
2012
2018?
CDV
This part of IEC 61400 includes:
– definition and specification of the quantities to be determined for characterizing
the electrical characteristics of a grid connected wind turbine;
– measurement procedures for quantifying the electrical characteristics;
– procedures for assessing compliance with electrical connection requirements,
including estimation of the power quality expected from the wind turbine type
when deployed at a specific site.
The measurement procedures are valid for single wind turbines with a three-phase grid
connection. The measurement procedures are valid for any size of wind turbine, though
this part of IEC 61400 only requires wind turbine types intended for connection to an
electricity supply network to be tested and characterized as specified in this part of IEC
61400.
The measured characteristics are valid for the specific configuration and operational
mode of the assessed wind turbine product family. If a measured property is based on
control parameters and the behavior of the wind turbine can be changed for this property,
it should be stated in the test report. Example: Grid protection, where the disconnect level
is based on a parameter and the test only verifies the proper functioning of the protection,
not the specific level.
The measurement procedures are designed to be as non-site-specific as possible, so that
electrical characteristics measured at for example a test site can be considered
representative for other sites.
IEC 61400-21-1 is for testing of wind turbines; all procedures, measurements and tests
related to wind power plants are covered by 61400-21-2.
Further
comments
The procedures for assessing electrical characteristics are valid for wind turbines with the
connection to the PCC in power systems with stable grid frequency.
This document will replace IEC 61400-21
21
PROJECT REPORT
Document
Timeline
Scope
Number
Title
IEC 61400-21-2
TC88. Wind energy generation systems.
Part 21-2. Measurement and assessment of electrical characteristics –
Wind power plants.
Begin year
End year
Stage
2012
?
„Table of content“
This part of IEC 61400 includes:
– Definition and specification of the quantities to be determined for characterizing
the electrical characteristics of grid connected wind power plants;
– Measurement procedures for quantifying the electrical characteristics;
o Power quality aspects
o Steady state operation
o Control performance
o Dynamic response
o Grid protection
– Define measurement methods and requirements for fault recording
– Definition of measurement equipment, control signals & measurement points,
references
– Aggregation methods for power quality aspects (Flicker, Harmonics, Switching
events ? ..)
– Not included is e.g. reactive power capability of WPP, control performance for
the planning phase etc. ( refer to e.g. loadflow studies etc.)
– Procedures for wind power plant controller test
The measurement procedures are valid for Wind Power Plants. The measurement
procedures are valid for any size of wind power plant.
– Connected to One connection point
Included:
– Turbine mix, ( Aggregation method ?)
– Included HVDC connected power plants ( AC side) wind power plant connection
point
– Focus is the electrical characteristics on the connection point.
– Compensation equipment, Tap changer etc. if this is part of the WPP
– Storage equipment ?
Not included:
– Multi park control / cluster control
– Compliance test / Evaluation assessment ( Pass / fail)
– EMC test
– Component test, SVC, switch gear, …
– Communication interface test ( protocols, …)
Not included: Switch gear, SVC, Storage systems, component test, they are covered by
other IEC standards.
The measured characteristics are valid for the specific configuration and operational
mode of the assessed wind power plant only. If a measured property is based on control
parameters and the behaviour of the Wind power plant can be changed for this property,
it must be stated in the report. Example: Grid protection, where the disconnect level is
based on a parameter and the test only verifies the proper functioning of the protection,
not the specific level.
Further
comments
The procedures for assessing compliance with grid connection requirements are valid for
wind power plants in power systems with fixed frequency and a sufficient short circuit
power.
The writing of this document has never really started, MT21 has been busy with the other
parts.
22
PROJECT REPORT
Document
Timeline
Scope
Number
Title
IEC 61400-21-3
TC88. Wind energy generation systems.
Part 21-3. Measurement and assessment of electrical characteristics –
Technical Report: Wind turbine harmonic model and its application.
Begin year
End year
Stage
2014
2019
Final draft
This Technical Report, which is informative in its nature, provides guidance on principles
which can be used as the basis for determining the application, structure, requirements
for wind turbine harmonic model. For the purposes of this report, a harmonic model
means a model that represents harmonic emissions of different wind turbine types
interacting with the connected network.
This Technical Report is focused on providing technical guidance concerning the wind
turbine harmonic model. The Technical Report describes the harmonic model in detail
covering such aspects as application, structure as well as validation. By introducing a
common understanding of the wind turbine representation from a harmonic performance
perspective, the technical report aims to bring the overall concept of the harmonic model
closer to the industry (e.g. suppliers, developers, system operators, academia, etc.).
A standardized approach of wind turbine harmonic model representation is presented in
this Technical Report. It is expected that the harmonic model will find a broad application
in many areas of electrical engineering related to design, analysis, and optimisation of
electrical infrastructure of onshore as well as offshore wind power plants.
The structure of the harmonic model presented in this Technical Report will find an
application in the following potential areas:
– Evaluation of the wind turbine harmonic performance during the design of
electrical infrastructure and grid-connection studies.
– Harmonic studies/analysis of modern power systems incorporating a number of
line side converters.
– Active or passive harmonic filter design to optimize electrical infrastructure as
well as meet requirements in various grid codes.
– Sizing of electrical components (e.g. harmonic losses, static reactive power
compensation, noise emission, harmonic compatibility levels, etc.) within wind
power plant electrical infrastructure.
– Wind power plant electrical infrastructure optimisation on a system level, e.g.
resonance characteristic shaping, planning levels definition and evaluation, etc.
– Evaluation of external network background distortion impact on wind turbine
harmonic assessment.
– Standardised communication interfaces in relation to wind turbine harmonic data
exchange between different stakeholders (e.g. system operators, generators,
developers, etc.).
– Universal interface for harmonic studies for engineering software developers.
– Possible benchmark of wind turbines introduced to the academia and the
industry.
– The advantage of having standardized wind turbine harmonic performance
measure by means of the harmonic model is getting more and more crucial in
case of large systems with different types of wind turbines connected to them,
e.g. multi-cluster wind power plants incorporating different types of wind turbines
connected to the same offshore or onshore substation.
Further
comments
23
PROJECT REPORT
Working group
Number
Title
TC88 WG27
Wind energy generation systems –
Electrical simulation models
Timeline
Past / Ongoing / Planned
Begin year
Ongoing
2009
Promotion
partner
involvement
Scope
–
Person name(s)
Partner(s)
Role(s)
Poul Sørensen
DTU
Convener
Documents
Number
Title
IEC 61400-27-1 Ed1
IEC 61400-27-1 Ed2
IEC 61400-27-2
Wind turbines
Generic models
Model validation
End year
The scope of this working group is to specify generic electrical simulation models for wind
turbines and wind power plants, and to specify procedures for validation of such models.
Further
comments
Document
Timeline
Scope
Number
Title
IEC 61400-27-1
Ed 1
TC88. Wind turbines –
Part 21-1. Electrical simulation models –
Wind turbines.
Begin year
End year
Stage
2009
2015
Published
IEC 61400-27 defines standard electrical simulation models for wind turbines and wind
power plants. The specified models are time domain positive sequence simulation
models, intended to be used in power system and grid stability analyses. The models are
applicable for dynamic simulations of short term stability in power systems. IEC 61400-27
includes procedures for validation of the specified electrical simulation models. The
validation procedure for IEC 61400-27 is based on tests specified in IEC 61400-21.
IEC 61400-27-1 Ed1 specifies dynamic simulation models for generic wind turbine
topologies/ concepts / configurations on the market. IEC 61400-27-1 defines the generic
terms and parameters with the purpose of specifying the electrical characteristics of a
wind turbine at the connection terminals. The models are described in a modular way
which can be applied for future wind turbine concepts. The dynamic simulation models
refer to the wind turbine terminals. The validation procedure specified in IEC 61400-27-1
focuses on the IEC 61400-21 tests for response to voltage dips, reference point changes
and grid protection.
The electrical simulation models specified in IEC 61400-27 are independent of any
software simulation tool.
Further
comments
24
PROJECT REPORT
Document
Timeline
Scope
Number
Title
IEC 61400-27-1
Ed2
TC88. Wind energy generation systems
Part 27-1. Electrical simulation models –
Generic models
Begin year
End year
Stage
2015
2019?
CD 2016
IEC 61400-27-1 defines standard electrical simulation models for wind turbines and wind
power plants. The specified models are time domain positive sequence simulation
models, intended to be used in power system and grid stability analyses. The models are
applicable for dynamic simulations of short term stability in power systems.
IEC 61400-27-1 defines the generic terms and parameters for the electrical simulation
models.
IEC 61400-27-1 specifies electrical simulation models for the generic wind power plant
topologies / configurations currently on the market. The wind power plant models include
wind turbines, wind power plant control and auxiliary equipment. The wind power plant
models are described in a modular way which can be applied for future wind power plant
concepts and with different wind turbine concepts.
IEC 61400-27-1 specifies electrical simulation models for the generic wind turbine
topologies/ concepts / configurations currently on the market. The purpose of the models
is to specify the electrical characteristics of a wind turbine at the wind turbine terminals.
The wind turbine models are described in a modular way which can be applied for future
wind turbine concepts. The specified wind turbine models can either be used in wind
power plant models or to represent wind turbines without wind power plant relationships.
Further
comments
The electrical simulation models specified in IEC 61400-27-1 are independent of any
software simulation tool.
IEC 61400-27-1 Ed2 and IEC 61400-27-2 Ed1 shall replace IEC 61400-27-1 Ed1
25
PROJECT REPORT
Document
Timeline
Scope
Number
Title
IEC 61400-27-2
Wind energy generation systems –
Electrical simulation models –
Model validation
Begin year
End year
Stage
2015
2019?
CD 2016
IEC 61400-27-2 specifies procedures for validation of electrical simulation models for
wind turbines and wind power plants, intended to be used in power system and grid
stability analyses. The validation procedures are based on the tests specified in IEC
61400-21. The validation procedures are applicable to the generic models specified in
IEC 61400-27-1 and other fundamental frequency wind power plant models and wind
turbine models.
The validation procedures for wind turbine models focus on tests for response to voltage
dips, voltage swells and reference point changes. Those validation procedures refer to
the wind turbine terminals.
The validation procedures for wind power plant models focus on tests for response to
reference point changes as well as voltage dips and voltage swells. Those validation
procedures refer to the point of connection of the wind power plant.
The validation procedures specified in IEC 61400-27-2 are based on comparisons
between test results and simulations, but they are independent of choice of software
simulation tool.
Further
comments
26
PROJECT REPORT
2.2.4
TC95. MEASURING RELAYS AND PROTECTION EQUIPMENT
Technical
Committee
Activity
Timeline
Scope
Further
comments
Number
Title
TC95
Measuring relays and protection equipment
Past / Ongoing / Planned
Begin year
End year
Ongoing
–
Standardisation of measuring relays and protection equipment used in various fields of
electrical engineering covered by IEC, taking into a ccount combinations of devices to
form schemes for power system protection including the control, monitoring and process
interface equipment used with those systems. Excluded are the following: All devices
covered by standards prepared by other IEC Technical Committees, for example
instrument transformers (TC 38)
Future activity is planned for HVDC relays (also known as HVDC protection IEDs),
although there is no known active working group or document.
27
PROJECT REPORT
2.2.5
TC115. HIGH VOLTAGE DIRECT CURRENT (HVDC) TRANSMISSION FOR DC VOLTAGES ABOVE 100 KV
Document
Number
Title
IEC TS 630141:2018
Timeline
Scope
High voltage direct current (HVDC) power transmission-System
requirements for DC-side equipment
Part 1: Using line-commutated converters
Technical Specification
Stage
Begin year
End year
2018
Published
This Technical Specification is intended to provide an overall and consistent set of
guidelines to facilitate the specification of equipment for the DC-side of a high-voltage
direct current (HVDC) system using line-commutated converters. For point-to-point HVDC
transmission systems, this document covers all DC-side equipment located between the
converter valves and the DC overhead line or cable termination, excluding the converter
valves themselves. For back-to-back HVDC systems, this document covers all DC-side
equipment excluding the converter valves themselves. Throughout this publication, the
terms 'direct voltage' and 'DC voltage' are used interchangeably, as are 'direct current'
and 'DC current'.
Traditionally, the largest items of such equipment, such as the DC smoothing reactor and
DC harmonic filters, have generally been located outdoors but increasingly the trend is to
locate such equipment indoors (although not in the valve hall itself) to provide protection
from pollution. Although product standards exist for some DC-side equipment types,
many such items of equipment have only standards written for AC applications and, in
such cases, the purpose of this document is to provide guidance as to how to specify the
additional requirements (particularly with regard to testing) for such equipment to cover
their use in DC conditions.
The converter itself is excluded from this scope, being covered by IEC 60700-1 and
IEC 60700-2.
Although this document includes requirements for DC disconnectors and certain types of
specialised DC switching devices (such as the Metallic Return Transfer Switch (MRTS)),
it excludes any type of DC circuit-breaker designed to interrupt fault currents. DC-side
equipment for HVDC systems based on voltage-sourced converter (VSC) technology
is excluded from this document and will be covered in a future Part 2 of IEC 63014.
Further
comments
28
PROJECT REPORT
2.3
CENELEC
2.3.1
TC 8X SYSTEM ASPECTS OF ELECTRICAL ENERGY SUPPLY
Working group
Number
Title
TC 8X/WG 06
System Aspects of HVDC grids
Timeline
Past / Ongoing / Planned
Begin year
Ongoing
2013
-
Promotion
partner
involvement
Scope
Documents
Person name(s)
Partner(s)
Role(s)
Frank Schettler
Stephan Wietzel
Siemens
Siemens
Convenor
Member
Further
comments
Document
Timeline
Scope
Number
End year
Title
FprTS_50654-1 &
FprTS_50654-2
HVDC Grid Systems and connected Converter Stations - Guideline
and Parameter Lists for Functional Specifications - Part 1:
Guidelines & Part 2: Parameter Lists
The working group is divided in five subgroups:
Coordination of HVDC Grid and AC Systems (Tasks are completed – not active)
HVDC Grid Control
HVDC Grid Protection
HVDC Grid System Characteristics and HVDC Grid Equipment
Models and Validation, HVDC Grid System Integration Tests
Number
Title
FprTS_50654-1
HVDC Grid Systems and connected Converter Stations - Guideline
and Parameter Lists for Functional Specifications - Part 1: Guidelines
Begin year
End year
Stage
2013
2018
Published
„1.1 General:
These Guidelines and Parameter Lists to Functional Specifications describe specific
functional requirements for HVDC Grid Systems. The terminology "HVDC Grid Systems"
is used here describing HVDC systems for power transmission having more than two
converter stations connected to a common d.c. circuit. While this document focuses on
requirements, that are specific for HVDC Grid Systems, some requirements are
considered applicable to all HVDC systems in general, i.e. including point-to-point HVDC
systems. Existing IEC, Cigré or other documents relevant have been used for reference
as far as possible. Corresponding to electric power transmission applications, this
document is applicable to high voltage systems, i.e. .only nominal d.c. voltages equal or
higher than 50 kV with respect to earth are considered in this document.
NOTE While the physical principles of d.c. networks are basically voltage independent,
the technical options for designing equipment get much wider with lower d.c. voltage
levels, e.g. in case of converters or switchgear. Both parts have the same outline and
headlines to aid the reader.
1.2 About the Present Release:
The present release of the Guidelines and Parameter Lists for Functional Specifications
describes technical guidelines and specifications for HVDC Grid Systems which are
characterized by having exactly one single connection between two converter stations,
often referred to as radial systems. When developing the requirements for radial systems,
care is taken not to build up potential show-stoppers for meshed systems. Meshed HVDC
Grid Systems can be included into this specification at a later point in time. The
Guidelines and Parameter List to the Functional Specification of HVDC Grid Systems
cover technical aspects of
- Coordination of HVDC Grid and a.c. Systems
- HVDC Grid System Characteristics
- HVDC Grid System Control
- HVDC Grid System Protection
- Models and Validation
29
PROJECT REPORT
Beyond the present scope, the following aspects are proposed for future work:
- AC/DC converter stations
- HVDC Grid System Equipment
- HVDC Grid System Integration Tests” [CENELEC]
Outline of the document:
1. Scope
2. Normative references
3. Terms, definitions and abbreviations
4. Coordination of HVDC Grid System and AC systems
5. HVDC Grid System Characteristics
6. HVDC Grid System Control
7. HVDC Grid System Protection
8. AC/DC Converter Stations
9. HVDC Grid System Installations
10. Models and Validation
11. HVDC Grid System Integration Tests
12. Bibliography
Further
comments
Document
Timeline
Scope
Number
Title
FprTS_50654-2
HVDC Grid Systems and connected Converter Stations - Guideline
and Parameter Lists for Functional Specifications - Part 2: Parameter
List
Begin year
End year
Stage
2013
2018
Published
This document contains a parameter list complementary to the guidelines in Part 1. It
covers both parameters for Operating Conditions and Performance Requirements.
Further
comments
30
PROJECT REPORT
2.4
IEEE-SA
Working group
Number
Title
WGI10
HVDC Working Group
Timeline
Past / Ongoing / Planned
Begin year
Ongoing
-
Promotion
partner
involvement
Scope
Documents
Person name(s)
Partner(s)
Further
comments
Mikael Kipness
Number
1240 –
End year
Role(s)
Convenor
Title
Guide for the Evaluation of the Reliability of HVDC Converter Stations
1378 –
Guide for Commissioning High-Voltage Direct-Current (HVDC) Converter
Stations and Associated Transmission Systems
2656 -
Guide for Functional Specification of Voltage-Sourced Converter for HVDC
Stations
Main IEEE-HVDC working group. Check if Promotion members are involved. Sponsored
by IEEE-PES
31
PROJECT REPORT
2.5
GRID CODES
2.5.1
COMMISSION REGULATIONS (EU)
Document
Timeline
Scope
Number
Title
COMMISSION
REGULATION
(EU) 2016/1447
Network code on requirements for grid connection of high voltage
direct current systems and direct current-connected power park
modules
Date of publication
Stage
09/2016
Published, entered into
force
This Regulation establishes a network code which lays down the requirements for grid
connections of high-voltage direct current (HVDC) systems and DC-connected power
park modules. It, therefore, helps to ensure fair conditions of competition in the internal
electricity market, to ensure system security and the integration of renewable electricity
sources, and to facilitate Union-wide trade in electricity. This regulation also lays down the
obligations for ensuring that system operators make appropriate use of HVDC systems
and DC-connected power park modules capabilities in a transparent and nondiscriminatory manner to provide a level playing field throughout the Union.
Further
comments
Document
Timeline
Scope
Number
Title
COMMISSION
REGULATION
(EU) 2016/631
Network code on requirements for grid connection of generators
Date of publication
Stage
05/2016
Published, entered into
force
This Regulation establishes a network code which lays down the requirements for grid
connection of power-generating facilities, namely synchronous power-generating
modules, power park modules and offshore power park modules, to the interconnected
system. It, therefore, helps to ensure fair conditions of competition in the internal
electricity market, to ensure system security and the integration of renewable electricity
sources, and to facilitate Union-wide trade in electricity. 27.4.2016 L 112/4 Official Journal
of the European Union EN
This regulation also lays down the obligations for ensuring that system operators make
appropriate use of the power- generating facilities' capabilities in a transparent and nondiscriminatory manner to provide a level playing field throughout the Union.
Further
comments
Document
Timeline
Number
Title
COMMISSION
REGULATION
(EU) 2016/1388
Network Code on Demand Connection
Date of publication
Stage
09/2016
Published, entered into
force
32
PROJECT REPORT
Scope
1. This Regulation establishes a network code which lays down the requirements for grid
connection of:
(a) transmission-connected demand facilities;
(b) transmission-connected distribution facilities;
(c) distribution systems, including closed distribution systems;
(d) demand units, used by a demand facility or a closed distribution system to
provide demand response services to relevant system operators and relevant
TSOs.
2. This Regulation, therefore, helps to ensure fair conditions of competition in the internal
electricity market, to ensure system security and the integration of renewable electricity
sources, and to facilitate Union-wide trade in electricity.
3. This Regulation also lays down the obligations for ensuring that system operators
make appropriate use of the demand facilities' and distribution systems' capabilities in a
transparent and non-discriminatory manner to provide a level playing field throughout the
Union.
Further
comments
2.5.2
ENTSO-E
Document
Number
Title
Report on Inter-TSO coordination in connection network codes (CNC)
implementation
Timeline
Scope
Date of publication
Stage
01/2018
Published
Pursuant to Commission Regulation (EU) No 2016/631 establishing a network code on
requirements for grid connection of generators (NC RfG), Commission Regulation (EU)
2016/1388 establishing a network code on demand connection (NC DCC) and
Commission Regulation (EU) 2016/1447 establishing a network code on requirements for
grid connection of high voltage direct current systems and direct current-connected power
park modules (NC HVDC) – later on referred to as the Connection Network Codes
(CNCs) – transmission system operators (TSOs) are responsible to coordinate when
establishing certain requirements at the national level. For some requirements, the
coordination shall take place at the synchronous area level; for others, it is required
between adjacent TSOs.
The objective of this report is to present the process of explicitly required coordination or
reasonably undertaken collaboration between European TSOs when implementing at
national level the CNCs, because of the cross-border impact of these specifications at
synchronous area level. This report shall provide an overview over coordination and
collaboration activities performed so far (until the date of collection of TSO’s answers)
between adjacent TSOs or at synchronous area level. TSOs’ coordination/collaboration
when implementing the CNCs consists of working closely together in specifications for
national implementation to ensure that the objectives of NCs RfG, DCC and HVDC are
achieved. This coordination/collaboration shall guide the national implementation but not
impair the decision making prerogatives of the relevant entities at national level.
Chapter 2 provides an overview over the CNC topics, which are subject to TSO
coordination/collaboration, either explicitly required by each of the CNCs or reasonably
undertaken, because of the cross-border impact of these specification s at synchronous
area level.
33
PROJECT REPORT
Chapter 3 describes the process how the relevant information/data have been collected
and compiled for this report.
Chapter 4 provides a detailed analysis on the extent of TSO coordination/collaboration
perceived so far based on the feedback received from the TSOs.
The conclusions/recommendations from this report are summarized in Chapter 5.
Further
comments
2.6
CHINESE STANDARDS
Document
Timeline
Scope
Number
Title
GB/T 25091-2010
(Chinese National
standard)
High-voltage direct-current disconnectors and earthing switches
Stage
Begin year
End year
2010
Published
This national standard specifies the service conditions, rated values, design and
construction, tests and guide to the selection of disconnectors and earthing switches so
as to unify the basic design and test requirements of the equipments and to guarantee the
system operate safely.
This national standard is applicable to disconnectors and earthing switches, designed for
indoor and outdoor installations in HVDC system for voltages below ±800kV. It also
applies to the operating devices of these disconnectors and earthing switches and their
auxiliary equipment.
Further
comments
Document
Timeline
Scope
Number
Title
GB/T 25307-2010
(Chinese National
standard)
High-voltage direct current by-pass switches
Stage
Begin year
End year
2010
Published
This national standard specifies the ratings, design and construction as well as tests of
high-voltage direct current by-pass switches.
This national standard is applicable to the by-pass switches designed for indoor or
outdoor installation and for operation in high-voltage direct current systems having
voltage of ± 800kV or below.
This national standard is also applicable to the operating devices and auxiliary equipment.
Further
comments
34
PROJECT REPORT
Document
Timeline
Scope
Title
Number
GB/T 25309-2010
High-voltage direct current transfer switches
(Chinese Standard)
Stage
Begin year
End year
2010
Published
The national standard specifies the terms and definitions, the operational environment,
the rating, the technical requirement, the type test, the routine test, the special test, the
field test, etc. of high-voltage direct current transfer switches.
The national standard is applicable to the high-voltage direct current transfer switches of
HVDC transmission system under ±800kV, including metal return transfer breakers
(MRTB), earth return transfer breakers (ERTB), neutral bus switches (NBS) and neutral
bus grounding switches (NBGS).
The national standard is also applicable to the operating mechanism and auxiliary
equipment of these switches.
Further
comments
Document
Timeline
Scope
Title
Number
NB/T 42107-2017
High-voltage direct current circuit-breakers
(Chinese Standard)
Stage
Begin year
End year
2017
Published
The national standard specifies the terms and definitions, the operational environment,
the rating, the technical requirement, the type test, the routine test, the special test, the
field test, etc. of high-voltage direct current circuit breakers.
The national standard is applicable to the high-voltage direct current circuit breakers
above 6 kV.
The national standard is also applicable to the operating mechanism and auxiliary
equipment of these switches.
Further
comments
In Chinese, no authorized English translation available
To be addressed by IEC TC 17A AGH60
35
PROJECT REPORT
3 POTENTIAL NEW CONTRIBUTIONS
There are numerous technical activities ongoing within the PROMOTioN project, many of which are in fields
where there are known gaps in standardisation. In order to fully exploit the technical work within PROMOTioN,
contribution to harmonisation is strongly encouraged. Chapter 2 of this harmonisation catalogue has evaluated
relevant harmonisation working groups and bodies. This chapter will consider gaps in existing harmonisation
and standardisation documents, and will include contributions from PROMOTioN technical work packages in
order to evaluate possible contributions from the PROMOTioN project towards best practices, harmonisation
and standardisation.
The following sections contain topics that have been identified as of interest. For each topic, the following
aspects are considered:
Introduction to the topic and perceived gaps in harmonisation
Analysis of ongoing and planned work from PROMOTioN in this field
Analysis of topics for which PROMOTioN work is contributing, or could contribute, to best practices and
harmonisation.
SPECIFICATION AND CONTROL OF HVDC SYSTEMS
3.1
3.1.1
NOMENCLATURE
As the application of HVDC converters in multi-terminal systems is a rather new field, there is not yet complete
agreement on the suitable terms for the configurations and concepts. There is still discussion ongoing about
seemingly simple terms like grid and system, the naming of the monopole and bipolar configurations or circuit
topologies and the definitions with regard to protection concepts among other aspects. The overall aim of the
discussions is the creation of a consistent and clear set of terms to describe the HVDC grids, its components
and functionalities.
3.1.1.1
RELEVANT PROMOTION ACTIVITY
The discussion on suitable terms for HVDC systems has accompanied the work in PROMOTioN from the start
and has been carried on in all work packages. The topics covered among others are:
-
The differentiation between grids, systems, network, configurations and topologies
-
Protection system related vocabulary with regard to protection philosophies or fault handling concepts
-
Specification of HVDC breakers capabilities and interfaces
3.1.1.2
EXISTING AND PROSPECTIVE CONTRIBUTIONS
All PROMOTioN members active across the range of standardisation bodies contributed to the definition of
terms based on their insights in PROMOTioN. Moreover, the IEC vocabulary on HVDC was extended during the
36
PROJECT REPORT
course of PROMOTioN due to the increased relevance worldwide. WP11 partners reviewed the existing draft
and commented based on the discussions going on in all work packages. As HVDC grids are a rather new
technological development, it is expected that there will be ongoing discussion and new definitions emerging
over the next years.
3.1.2
FUNCTIONAL HVDC SYSTEM SPECIFICATION
Future multi-terminal HVDC systems will integrate different types of controllable equipment from different
manufacturers. To allow the interconnection of different components, the interfaces between the components
and the requirements on them have to be well defined. All existing HVDC links in Europe are turnkey projects,
therefore there were few requirements on the DC side behaviour defined in the specifications. The
specifications were mostly given for the AC side, with the basis being the relevant HVDC grid code. The
extension to HVDC grids results in a need for detailed specifications for the DC side. This starts from the
nominal voltage and powers and allowable voltage bands and includes the definition of the used system
configuration, the definition of the DC side points of common coupling between the converters, the transmission
lines, the switching stations and possible additional equipment. Furthermore, to allow a stable and optimised
operation of the system, there needs to be an exchange of relevant parameters between the components and a
coordinated operation of the equipment, potentially governed by an overlaying grid control, similar to existing
SCADA systems and control centres for AC systems. As there is no corresponding system in operation today
first the relevant data to be exchanged between all system components, the relevant control schemes
implemented in each converter and the role of the overlaying grid control have to be defined.
3.1.2.1
RELEVANT PROMOTION ACTIVITY
Within WP2, and WP4 of PROMOTioN the DC-side system behaviour is analysed in detail for offshore HVDC
grids. The analyses takes into account a variety of system topologies, configurations, control concepts,
contingencies and fault handling strategies to be able to specify the DC side system behaviour and the
requirements on it in a general manner.
3.1.2.2
EXISTING AND PROSPECTIVE CONTRIBUTIONS
The work of the CENELEC working group TC 8X WG06 is specifically dedicated to set up a set of functional
specifications for HVDC systems summarising all relevant parameters in a parameter list and giving the
background behind each parameter in a guidelines document. PROMOTioN has been granted liaison
organisation status with CENELEC to contribute to the ongoing efforts based on the analyses undertaken in the
PROMOTioN project.
37
PROJECT REPORT
3.1.3
HVDC CONVERTER CONTROLS
Modern voltage source converters like the modular multilevel converter enable a flexible and fast control of the
AC- and DC-side values within the limitations given by the design and components of the converter. While the
hardware set-up of each converter might be similar the main distinction often lies in the controls used. The
converter behaviour and its response to dynamic events is, in many respects, defined by its control system.
When considering HVDC systems integrating converters of several manufacturers or types, it has to be ensured
that there is no adverse interaction of the controls used. Therefore detailed specifications of the converter
behaviour under a broad range of situations must be specified.
3.1.3.1
RELEVANT PROMOTION ACTIVITY
While in PROMOTioN the investigations are based on generic converter models, such that no direct vendorinteroperability issues between converters can be observed, PROMOTioN aims to analyse the HVDC grid
system behaviour in a broad range of scenarios, including different topologies, configurations, faults and
protection sequences to define the requirements on the converters in a stringent fashion. The analysis takes
into account the knowledge gained on interoperability issues in the EU project Best Paths. Based on
discussions at the control and protection workshop including the input from the relevant work package in Best
Paths the following approaches for a standardisation of the upper level controls were identified:
As interoperability issues might not only occur under faults, but also under dynamic events such as load changes,
a very detailed specification of the converter behaviour is required. The specification from the CENELEC working
group TC 8X WG06 can be taken as a starting point. Furthermore, dynamic controls such as droop controls were
identified as requiring further specification. A stricter approach could be pursued by standardising the upper level
controls, such that only the lower level controls are vendor specific.
The developed controls in PROMOTioN will be demonstrated on the MMC test bench.
3.1.3.2
EXISTING AND PROSPECTIVE CONTRIBUTIONS
As the standardisation of converter controls is a highly sensitive topic for manufacturers, it is not expected that
there will be a standardisation of the controls within the runtime of PROMOTioN. However, the above mentioned
functional specifications and requirements will help to specify HVDC systems including several vendors.
3.1.4
HARMONIC MODELS FOR MMCS
Some of the early windfarm connections employing full scale converter wind turbines and MMCs have been
experiencing resonance issues leading to partial destruction of equipment and disconnection of components. The
cause of observed oscillations has been attributed to interactions of control systems with the AC grid or other
power electronic controlled components. A promising methodology to investigate this harmonic resonance
phenomena is to model the system in the frequency domain and apply classical control theory. This approach
38
PROJECT REPORT
requires the frequency response of the investigated components modelled as impedance. These harmonic
models can be either measured or derived analytically. Many analytically derived models have been developed
and described in literature for this purpose. However, the confidence level is still low when offline EMT simulation
tools are used for the impedance measurement and harmonic model validation. Therefore, Hardware-in-the-loop
(HiL) investigations are considered for model validation.
3.1.4.1
RELEVANT PROMOTION ACTIVITY
Within WP 16 harmonic models, more specifically frequency dependent impedance models of voltage source
converter (VSC) wind turbines, diode rectifier units (DRU) including wind power plants (WPP) and modular
multilevel converter (MMC) will be investigated to gain a better understanding of the harmonic resonant
phenomena occurring in offshore wind farm connections. Task 16.5 develops and describes the theoretical
background of frequency impedance models Different approaches for modelling the frequency dependent
impedances are investigated. Thereafter, task 16.6 performs studies to investigate the developed harmonic
models on the test bench system including lab-scale MMCs to validate the developed models in a HiL setup by
means of defined test cases. This way confidence can be gained about the applicability of the models and
investigation approach when studying the phenomena in the frequency domain by means of harmonic models
and classical control theory. For a more detailed insight into the relevant activities with regard to wind power plants
please refer to section 3.4.1.
3.1.4.2
EXISTING AND PROSPECTIVE CONTRIBUTIONS
The outcomes of Task 16.5 with regard to MMCs will serve as input for CIGRE WG C4.49 on Multi-frequency
Stability Of Converter-based Modern Power Systems.
3.2
PROTECTION OF HVDC SYSTEMS
3.2.1
DESIGN OF PROTECTION SYSTEMS
While in AC systems the used protection systems have long been standardised there is no standard protection
system design for HVDC systems yet. There have been several proposals with regard to the detection and
localisation of faults, the associated fault clearing process applying different devices, additional equipment needed
for a selective line protection and the recovery process after the fault. As the solutions are manifold there is still
the need to identify all implications of a certain protection system design choice on the overall system operation,
its control, stability and availability.
There are several aspects of HVDC protection system design that have been suggested as topics where
standardisation could be useful. Many of these topics are highly relevant for both control and protection:
Fault ride-through envelopes for HVDC converters (DC- and AC-side), and associated characteristics
for offshore wind farms.
Requirements imposed on protection strategy, including requirements for redundancy and
requirements for backup protection.
39
PROJECT REPORT
Basic requirements for protection functions (minimum pick up time, minimum sensitivity, fault cases to
consider).
3.2.1.1
Location of breakers, inductors, measurements.
RELEVANT PROMOTION ACTIVITY
Several studies in WP2, WP3, WP4 and WP5 analyse the effect of faults on the system in different scenarios
taking into account a variety of proposed system designs, thereby giving insight into the different implications of
the design factors.
3.2.1.2
EXISTING AND PROSPECTIVE CONTRIBUTIONS
While the standardisation of the algorithms and components might limit the development of certain technologies
at this point in time, the definition of requirements on the protection systems and the relevant performance
indicators have been discussed and defined in more detail, see section 3.2.3.
3.2.2
CLASSIFICATION OF PROTECTION SYSTEMS: FAULT SEPARATION CONCEPTS AND PROTECTION PHILOSOPHIES
As stated above there is no standardised HVDC protection system yet. Different approaches for classifying the
different concepts have been proposed. One of the classifications has been proposed by Cigré in TB 739 which
calls the different approaches “Protection Philosophies” and differentiates them into selective, non-selective and
partially selective strategies. A second approach is defined by the CENELEC working group TC8X WG06. It
focuses on the impact on the controllability at defined interface points. The different concepts are called “Fault
separation concepts” and are distinguished into the following categories: Continuous operation, temporary stop
and permanent stop.
3.2.2.1
RELEVANT PROMOTION ACTIVITY
Both classification concepts were applied to the analysis and comparison of a broad range of protection
concepts in WP4. Based on the application the definitions were discussed in detail and potential modifications
were derived.
3.2.2.2
EXISTING AND PROSPECTIVE CONTRIBUTIONS
Feedback on the defined classifications will be provided to the CENELEC working group TC8X WG06.
3.2.3
PERFORMANCE EVALUATION OF PROTECTION SYSTEM
When developing a protection strategy for an HVDC system there are numerous design choices, many of which
are co-dependent and have various implications (e.g. cost, functionality, impact). When making such design
choices, comparing the implications of each option is clearly essential to enable an informed decision. The
40
PROJECT REPORT
importance of a specific factor is project dependent, however, the means of comparison should be applicable to
all projects. Although existing projects will have used their own methods of benchmarking performance, when
we move towards larger scale and multi-vendor systems, harmonisation of the performance indicators is likely to
be of interest.
Standardisation of Key Performance Indicators (KPIs) would enable reliable and effective comparison between
different protection strategies and also between different implementations of a particular protection strategy.
3.2.3.1
RELEVANT PROMOTION ACTIVITY
Within WP4 (Deliverable 4.3) KPIs are developed with the aim of demonstrating how effectively a protection
system achieves key objectives. While many possible performance indicators have been discussed, the decided
upon KPIs are as follows:
Efficiency indicators:
o
Fault interruption time
o
Voltage restoration time
o
Active power restoration time
o
Reactive power restoration time
o
Transient energy imbalance
Failure indicators:
o
Backup probability
o
Non-cleared fault probability
Cost indicators
Each KPI has been defined in a robust manner to compare a diverse selection of protection strategies and also
different implementations of those protection strategies. Definitions have been determined to allow comparison
within the deliverable (e.g. in some cases numerical values have been given for comparison purposes),
however, the KPIs can also be used in a generic manner (i.e. without specific numerical values).
3.2.3.2
EXISTING AND PROSPECTIVE CONTRIBUTIONS
Given that the core content of each performance indicator developed in WP4 can be considered generic, the
PROMOTioN work could be useful to harmonisation organisations. The most valuable information for
standardisation in this area is the generic definitions – i.e. the structures with which to compare – rather than the
exact values which should be compared.
3.2.4
CABLE OVERVOLTAGES
Overvoltages on an HVDC network must be managed effectively to avoid damage to system equipment.
Protection is provided using varistor (surge arrester) elements at strategic locations across the network – e.g. at
the cable termination and/or the busbar. Protection must be provided against sustained overvoltage due to poleto-ground short circuit faults in symmetrical monopolar HVDC systems. Overvoltages could also occur due to
switching of switchgear (e.g. HVDC circuit breaker isolating a fault). Such protection must also be coordinated
41
PROJECT REPORT
with lightning protection. The optimal solution could therefore require a co-design between system components
(e.g. defining the allowable cable overvoltage characteristic), protection equipment (e.g. circuit breaker
properties, controllable energy dissipation devices) and the locations and ratings (voltage, energy) of surge
arresters on the network. Differences for mixed transmission medium should also be explored (cable only,
mixed cable and overhead line, overhead line only).
3.2.4.1
RELEVANT PROMOTION ACTIVITY
Simulation studies have taken place to examine overvoltages on HVDC networks and methods to mitigate
persistent overvoltages (e.g. using converter control or controllable energy dissipation devices). There has not
been detailed study of the coordination requirements between different network locations.
3.2.4.2
EXISTING AND PROSPECTIVE CONTRIBUTIONS
The relevant PROMOTioN activity has been presented to CIGRE WG B4/B1/C4.73 “Surge and extended
overvoltage testing of HVDC Cable Systems” during a WG meeting.
Existing results from PROMOTioN could be useful to standardisation organisations interested in this field. It
could be possible to generate a short introductory document, providing a summary of relevant PROMOTioN
work in this field and indicating why insulation coordination for multi-terminal HVDC systems is an area of
ongoing interest.
3.2.5
COMMUNICATION PROTOCOLS
Operation of modern power systems is increasingly relying on digital communication to enable a more
controllable and reliable system with a reduced requirement for communication conductors. IEC 61850, for
example, is a standard governing digital substation communication. Due to its popularity and benefits, it seems
highly probable that the intelligent electronic devices (IEDs) in a HVDC substation would communicate using a
digital communication protocol such as IEC 61850. Although certain manufacturers market the HVDC circuit
breaker and the protection IED as one product, as the market moves towards networks with more terminals and
requires multivendor solutions, fast and standardised communication will be required for the protective devices.
Some protection algorithms require fast communication between IEDs across a network. Communication is
therefore of interest both within the HVDC substation and between HVDC substations.
3.2.5.1
RELEVANT PROMOTION ACTIVITY
The applicability of communication protocols to multi-terminal HVDC system protection strategies has been
examined. It is shown that IEC 61850 (in its present application note IEC 61850-9-2 LE) is not fast enough for
selective fault clearing strategies [Jahn2018DPSP], however, is appropriate for non-selective fault clearing
strategies. It should be noted that some fast communication may still be required for any fault clearing strategy
(e.g. within a converter station, where high speed and reliable communication can be relied upon) but
communication between remote devices remains a challenge. The constraining factor here is the speed of
42
PROJECT REPORT
operation, something which could be addressed in a future revision of the standard. It is known that there is an
IEC workgroup developing a part of IEC 61850 for application to FACTS data modelling (including development
for DC line fault sequences, power converters, and DC circuit), therefore future revisions of the standard might
allow for effective use in HVDC protection. Other communication protocols were under theoretical examination
as part of the HVDC protection IED work in PROMOTioN WP4. Work on implementation of a real-time Ethernet
communication protocol (HSR – high availability, seamless redundancy) is currently ongoing.
Protection algorithms have been studied extensively within PROMOTioN WP4, including communication based
(unit) protection. Work is ongoing to determine the application cases for which communication is of use. In such
cases, faster communication is expected to be highly beneficial. Within WP9 there is work ongoing to examine
the impact of communication on non-selective fault clearing strategies, with application of the existing IEC
61850 protocol.
3.2.5.2
EXISTING AND PROSPECTIVE CONTRIBUTIONS
There are no known existing contributions to standardisation.
A summary sheet will be provided to the IEC workgroup involved in the ongoing development of the IEC 61850
standard, such that they are aware of the requirements from an HVDC protection point of view. This will include
contributions from WP4 and WP9.
3.2.6
COMMUNCATION INTERFACES
The interfaces for communication between different devices with protective functions should be well defined in a
multivendor system. It is highly likely that a protection IED will communicate with an HVDC circuit breaker,
however the types of signals to be communicated could differ (e.g. trip signal, pre-activation, status signals,…)
and the format of the signals must be well defined. It is also possible that the protection IED could communicate
with the converter station, or that the converter station could communicate with the circuit breaker (e.g. to
coordinate current limiting, or for status transfer). Communication beyond the substation is also likely to be
required (e.g. with remote substations). For each of these applications, the communication requirements,
protocols, signals, and other information must be well defined.
3.2.6.1
RELEVANT PROMOTION ACTIVITY
Collaboration between WP4 and WP6 has resulted in discussion and definition of the required interfaces
between a circuit breaker and a protection IED. To achieve multivendor interoperability and to avoid excluding
technologies, minimally required and auxiliary interfaces have been defined, e.g., to allow the breaker to
perform its basic function (interrupting a current) and other functions (pro-active opening, current limiting).
3.2.6.2
EXISTING AND PROSPECTIVE CONTRIBUTIONS
There are no known existing contributions in this field.
A publication detailing required communication interfaces between circuit breakers and protection IEDs is
planned. It is hoped that this document could be used as input for future standardisation.
43
PROJECT REPORT
3.2.7
TESTING OF PROTECTION DEVICES
Standardised testing of protection IEDs is widespread and commonplace for AC protection devices. There are
numerous such tests, ranging from electromagnetic compatibility to functionality during operation, each with
associated standards and test procedures. Such tests, however, are not yet well developed for HVDC protection
equipment. Although existing projects are typically provided by a single vendor (and therefore there is no strong
requirement for standardisation), future projects are expected to be multi-vendor, and therefore standardisation
of specifications and requirements is highly desirable to ensure effective interoperability.
3.2.7.1
RELEVANT PROMOTION ACTIVITY
Within WP4, an HVDC protection IED has been developed and test routines are under development to evaluate
the functional performance of HVDC IEDs. Such tests can be considered to be ‘unit tests’ – i.e. testing that the
functionality of the device meets the expected functional requirements. Additionally, in WP9, tests will be
performed on a replica system and the HVDC IED performance will be evaluated at the system level. These
tests can be considered to be ‘commissioning tests’. Within these activities test routines and methods have
been developed to examine the functional performance of an HVDC IED in the context of the complete
protection system.
3.2.7.2
EXISTING AND PROSPECTIVE CONTRIBUTIONS
There are no known existing contributions to harmonisation.
Discussion is ongoing between PROMOTioN partners and IEC TC 95 (Measuring relays and protection
equipment), who are interested in developing standards for testing of HVDC IEDs. It is hoped that ongoing
PROMOTioN work will contribute to harmonisation in this field in the future. A summary of the relevant
PROMOTioN work could be sent to harmonisation bodies such that work will be considered as input for future
standardisation. It is thought that functional testing of HVDC IEDs is a topic that is highly relevant for future
standardisation.
3.3
HVDC SWITCHGEAR
The functionality of reconfiguring, isolating and/or earthing parts of networks, necessary for the optimal and safe
operation of the power system is achieved by switchgear. Different types of switchgear can be distinguished
based on their current interruption capability, insulating medium and speed of operation. Switchgear capable of
interrupting fault currents are referred to as circuit breakers, switchgear which cannot interrupt any current are
referred to as disconnectors. Typically, modern switchgear is insulated in air, or in a specific insulating gas in
which case it is referred to as gas insulated switchgear (GIS). More generally, GIS often also include other
components such as voltage and current measurement devices (RC dividers, Rogowski coils) and surge
arrestors for overvoltage protection.
44
PROJECT REPORT
These technologies have been developed and are mature for AC applications. For HVDC, only a few HVDC
circuit breakers and HVDC gas insulated systems have been put in operation, all in Asia. Several manufacturers
have developed products and started or completed qualification, but a lack of understanding of the application
and hence specification of HVDC switchgear, a lack of standardisation regarding testing, and a lack of
operational experience proving the technologies’ robustness have hampered their uptake, especially in Europe.
PROMOTioN addresses these challenges in several work packages split into two streams dealing with HVDC
circuit breakers and HVDC GIS separately.
HVDC circuit breakers are systems which are able to interrupt DC (fault) currents and isolate parts of an HVDC
network. Based on their application, these two functions can be combined to achieve continuous operation of
the HVDC power system in case of a fault and any desired selectivity in fault clearing (although not all
topologies and configurations would achieve this). Several different technologies exist which are distinguished
by the current interruption mechanism which is deployed and can be largely classed into mechanical circuit
breakers (consisting of a high speed AC mechanical interrupter, passive components, and a metal oxide varistor
stack) and hybrid circuit breakers (consisting of a high speed mechanical disconnector, power electronics and a
metal oxide varistor stack). The main differences between different types are speed of operation, cost,
functionality and size/weight.
In PROMOTioN, the development and application of HVDC circuit breakers are addressed in the following work
packages:
Work Package 6 – HVDC Circuit Breaker Performance Characterisation
Work Package 4 – DC Grid Protection System Development
Work Package 2 – Grid Topology & Converters
Work Package 5 – Test Environment for HVDC Circuit Breakers
Work Package 9 – Demonstration of DC Grid Protection
Work Package 10 – Circuit Breaker Performance Demonstration
The contributions made in this field by PROMOTioN are in the modelling and design, application and
specification and in the testing of HVDC circuit breakers, which will be discussed in the following sections.
3.3.1
APPROACH TO MODELLING OF HVDC CIRCUIT BREAKERS
In order to be able to study the application of HVDC circuit breakers and their subsequent specification, their
behaviour and operational characteristics should first be modelled.
45
PROJECT REPORT
3.3.1.1
RELEVANT PROMOTION ACTIVITY
In work package 6, the functional behaviour of different types of HVDC circuit breakers (hybrid IGBT-based,
hybrid thyristor-based, mechanical and VARC) and their control and protection systems have been modelled.
High-level models suitable for protection system studies in work package 2 and 4, as well as detailed models
suitable for analysing the stresses on the component and sub-component level have been developed. The highlevel models have also been implemented in RSCAD for later use in RTDS real-time simulations with protection
IED hardware in the loop in work package 9. The models have been cross-checked against one another using a
standardised simulation model test circuit. The detailed models will be verified by means of the results of tests
on real HVDC circuit breakers in work package 10, to the extent possible. The effect of different failure modes
on the HVDC circuit breaker operation has been modelled and will be demonstrated on scaled hardware
models, and the scaling of HVDC circuit breakers to EHV levels is studied. Finally, a bottom-up cost model of
the IGBT-based hybrid and mechanical HVDC circuit breakers has been created in order to study the technoeconomic performance of different ways of application in work package 4.
3.3.1.2
EXISTING AND PROSPECTIVE CONTRIBUTIONS
It is foreseen that the models and modelling approaches including the defined levels of abstraction/detail are
useful input to future standardisation activities regarding HVDC system studies including the effect of HVDC
circuit breakers. Examples of such studies are switching studies, protection studies, insulation coordination
studies and dynamic studies.
3.3.2
APPLICATION AND SPECIFICATION OF HVDC CIRCUIT BREAKERS
HVDC circuit breakers are likely to cost several orders of magnitude more than their AC counterparts, and the
cost of implementing fully selective fault clearing schemes with HVDC circuit breakers at each line end may be
prohibitive. Hence, different applications of HVDC circuit breakers which satisfy the system requirements as well
as economic considerations are investigated.
3.3.2.1
RELEVANT PROMOTION ACTIVITY
In work package 2 and work package 4, amongst others, the impact of different fault clearing strategies on the
HVDC power system stability and control and the connected AC power systems will be studied using the HVDC
circuit breaker models developed in work package 6.
Moreover, in work package 4, the techno-economic performance of different fault clearing strategies is analysed
and compared in detail, with the aim of selecting the best-performing strategies. Based on the performance of
the HVDC circuit breakers and the required properties, a suitable strategy can be chosen and a guide to the
specification of HVDC circuit breakers is written.
46
PROJECT REPORT
3.3.2.2
EXISTING AND PROSPECTIVE CONTRIBUTIONS
As stated in chapter 3.2 the requirements and the key performance indicators for the different possible
protection system designs were developed or extended in PROMOTioN and provide input to ongoing and future
harmonisation activities.
3.3.3
TESTING OF HVDC CIRCUIT BREAKERS
The operational principle of HVDC circuit breakers, being active systems, is substantially different from AC
circuit breakers, and most notably typified by being significantly faster (several ms vs 10s to 100s of ms), the
active generation of a counter voltage higher than the nominal system voltage and the characteristic of having to
absorb the magnetic energy stored in the HVDC system. These different characteristics place different
requirements on the way that HVDC circuit breaker design is qualified and functionality is tested.
3.3.3.1
RELEVANT PROMOTION ACTIVITY
In work package 5, the electrical stresses which different types of HVDC circuit breakers are likely to experience
during service life (steady-state operation and switching operations) were studied and translated to test
requirements. Different tests (dielectric, operational, current interruption and special tests) were defined. A
method to provide the current, energy and voltage stresses based on AC short-circuit generators (which are
available in most AC circuit breaker test facilities) operated at a low frequency was developed, tested and
demonstrated. In case the HVDC circuit breaker ratings exceed the laboratory’s capabilities, a method to test
EHV circuit breakers modularly was presented.
In work package 10, the test requirements, method and test circuit developed in work package 5 will be used at
DNV GL’s KEMA Laboratories to demonstrate the DC fault current interruption performance of commercial
prototypes of HVDC circuit breakers from PROMOTioN partners:
-
350 kV 16 kA hybrid circuit breaker from ABB
-
160 kV 16 kA mechanical circuit breaker from Mitsubishi Electric
-
120 kV 16 kA VARC circuit breaker from SCiBreak
In addition, an experimental mechanical HVDC circuit breaker has been set up and tested to analyse and
characterise the specific and unknown stresses on vacuum interrupters and surge arresters in this type of circuit
breakers. The test results are used to verify the sub-component models developed in work package 6.
3.3.3.2
EXISTING AND PROSPECTIVE CONTRIBUTIONS
WP5 and WP10 participants were and are actively involved in (pre-)standardization activities through the
following international committees:
47
PROJECT REPORT
Active participation in pre-standardization (see 2.1.1):
CIGRE JWG A3B4.34 (2014-2017) on HVDC switchgear (incl. HVDC circuit breakers)
CIGRE WGA3.39 (2017-2020) on surge arresters (including those used in HVDC circuit breakers)
CIGRE WG A3.40 (2018-2021) on MV HVDC systems and switchgear
CIGRE JWG B4A3.80 (2019-2022) on HVDC circuit breaker requirements
Active participation in IEC standardization activities (see 2.2.2):
IEC AHG4 (2016-2017), on market relevance of HVDC switchgear
IEC AHG60 (2017-2018), on existing standards of HVDC switchgear
3.3.4
GIS
HVDC GIS has been introduced as a promising technology where the benefits of the proven HVDC
transmission and AC gas-insulated switchgear/systems can be combined. Up to the present time, no
international standards describing the requirements, applicable tests and test procedures of HVDC gas
insulated systems (GIS) have been developed.
3.3.4.1
RELEVANT PROMOTION ACTIVITY
D15.2 on test requirements, procedures and methods is relevant for harmonization. This document provides a
general guideline for listing the tests that shall be applied to HVDC GIS to verify their designed performance.
Focus is given to the dielectric test requirements due to the different nature of DC electric fields in GIS
compared to AC fields. Additionally, due to lack of operational experience on HVDC GIS, a long-term test
method to prove the dielectric performance of a prototype installation under in-service conditions is described.
The described method will be applied to a prototype HVDC GIS which will be built by a GIS manufacturer (task
15.3 of PROMOTioN) based on the specifications and ratings that are defined in deliverable D15.1.
3.3.4.2
EXISTING AND PROSPECTIVE CONTRIBUTIONS
The PROMOTioN work on GIS test procedures should be combined with test results to contribute to prestandardization of HVDC GIS, as for example has already been started in IEC AHG 37 of IEC TC 17.
3.4
3.4.1
HVDC CONNECTED WIND POWER PLANTS
HARMONIC EMISSION AND STABILITY
Tests and assessment of harmonic emission has been an integral part of power quality standards for wind
power since first edition of IEC 61400-21 was published in 2001. The purpose has been to enable validation that
wind power complies with power quality requirements of grid operators. Because of the rapidly growing share of
wind and solar PV, the grid is becoming increasingly power electronics dominant, and for offshore HVDC
connected WPPs, the offshore AC grid has reached the ultimate 100% power electronics share. In such power
48
PROJECT REPORT
electronics dominant systems, the concern of harmonic stability has added to the power quality challenge.
Ensuring the harmonic stability relies on appropriate quantification of harmonic resonance phenomena between
converters and grid.
3.4.1.1
RELEVANT PROMOTION ACTIVITY
PROMOTioN WP16 includes the following activities regarding harmonic resonances:
First, task 16.5 deals with Implementation of an analytical method for analysis of harmonic resonance
phenomena. This work will be documented in the deliverable D16.5 with the same title as the task.
Secondly, development and demonstration of test methods for harmonic resonances is part of T16.6
Demonstration of defined test cases regarding interoperability, control schemes and protection. This work
includes input admittance measurement of kW setup using harmonic perturbation as a first step followed by a
wind turbine Controller Hardware In the Loop (CHIL) test system intended for MW systems.
3.4.1.2
EXISTING AND PROSPECTIVE CONTRIBUTIONS
The expected contribution to harmonization is a specification for CHIL Test Systems for MW wind turbine control
systems and input to IEC 61400-21-3 - Wind Turbine Harmonic Models and Its Application.
3.4.2
GRID FORMING CONTROL
The expected need for new grid forming control of wind power plants and other converter connected equipment
is also drawing increasing attention as the grid is becoming increasingly power electronics dominant. An
example where such grid forming capabilities are needed is offshore wind power plants connected to an HVDC
system through an offshore diode rectifier unit (DRU). If the offshore HVDC converter is a VSC type then the
HVDC-VSC converter will form the grid where the wind turbines will follow the grid and therefore standard wind
turbines developed for connection to AC grids can be used. But using an offshore DRU converter, the wind
turbine grid side converters are in charge of forming the offshore AC grid, i.e. control its voltage and frequency
and active power flow through the DRU. Therefore, the wind turbine control is different from standard control in
the sense that WT control needs to be grid forming and not grid following.
3.4.2.1
RELEVANT PROMOTION ACTIVITY
PROMOTioN includes the following activities regarding grid forming control:
Task 3.1 Functional requirements to WPPs reported in Deliverable 3.1: Detailed functional
requirements to WPPs. This document describes operational requirements in the DRU case
Task 3.2 General control algorithms reported in Deliverable 3.2: Specifications of the control strategies
and the simulation test cases. This document provides specification of control strategies for VSCHVDC as well as DRU-HVDC connections, i.e. both for grid following and grid forming WPPs
49
PROJECT REPORT
3.4.2.2
EXISTING AND PROSPECTIVE CONTRIBUTIONS
Grid forming is still at an early development stage, and therefore it is not realistic to harmonize controller models
or detailed performance specifications. At this stage, definition of control capability classes are established in
line with ENTSO-E classes:
Grid following: P-control, Q-control, connection to powered grid, high SCR, high inertia
Grid supporting: frequency support, voltage support, connection to powered grid, low SCR, low inertia
Grid forming: frequency control, voltage control, island connection, zero SCR, zero inertia
3.4.3
BLACK START CAPABILITY
Following a full or partial black-out in a power system, there is a need to restore the system in a fast and reliable
way. This restoration is traditionally done using synchronous power-generating modules with black-start
capabilities, i.e. the ability to start in an islanding mode and control voltage amplitude and frequency as loads
are connected.
Requirements are specified for synchronous power-generating modules in ENTSO-E RFG and within each
TSO’s agreements with the related power plants. These requirements are considered applicable here, as well.
These requirements include, among others, the following which are relevant for black-start capability:
-
capability of starting from shut-down without any external electrical energy supply within a specified
time frame
-
capability to synchronise within defined frequency limits
-
capability of automatically regulating dips in voltage caused by connection of load
-
capability of frequency control
3.4.3.1
RELEVANT PROMOTION ACTIVITY
Within WP 3 several deliverables address the topic of black start capability of HVDC connected wind power
plants.
D3.6 “Report with the compliance test procedures for DR and VSC connected WPPs” describes
compliance test requirements, procedures for simulation-based compliance evaluation and validation
procedures for the models and simulations applied for compliance evaluation.
D3.7 “Report with the compliance evaluation results using simulations” will include the results of
simulations for various scenarios and test cases in order to verify the effectiveness of the test
procedures for compliance evaluation.
In WP11 guidelines for best practice of compliance evaluation will be derived (D11.5 “Report with
recommendations to best practice for compliance evaluation”). These recommendations will also include
experiences of relevant parties like e.g. TSOs.
50
PROJECT REPORT
In WP16, it is planned to demonstrate black start capability of HVAC and DRU-connected offshore wind farms.
3.4.3.2
EXISTING AND PROSPECTIVE CONTRIBUTIONS
It is assumed that ongoing PROMOTioN work will contribute to harmonisation in this field in the future. A report
on justified recommendations to grid codes will be written within WP11 (D11.4) and could be sent to
harmonisation bodies as potential input for future standardisation. It is expected that functional specifications
and requirements for black start capability could be harmonised, but the specific hardware and control solutions
will not be harmonised.
3.4.4
ONSHORE FREQUENCY CONTROL FROM OFFSHORE WIND
As opposed to onshore AC grid connected WPPs, HVDC connected WPPs do not measure the onshore AC
frequency directly on the wind turbine terminals, and likewise the WPP controller of HVDC connected WPP
does not measure onshore frequency in the point of connection. Two classes of solutions have been proposed
to ensure that the offshore HVDC connected wind power plant can contribute to frequency control of the
onshore AC grid: either communication based or communication-less. The communication-less solutions can
work for two-terminal (point-to-point) HVDC connected WPPs, but for multi-terminal HVDC systems this solution
becomes very complex.
3.4.4.1
RELEVANT PROMOTION ACTIVITY
Within WP2 both communication-less and communication based frequency support from wind farms and
connected asynchronous grids is studied in multi-terminal cases to analyse the respective advantages and
disadvantages.
Frequency support from two-terminal DR-HVDC connection is studied in WP3 and reported in Deliverable 3.5:
Performance of ancillary services provision from WFs connected to DR-HVDC.
3.4.4.2
EXISTING AND PROSPECTIVE CONTRIBUTIONS
Based on the investigation recommendations on the frequency support approaches will be summarised and can
serve as input for future harmonisation and grid codes.
3.4.5
FAULT-RIDE-THROUGH
The topic of “fault ride through” is addressed in WP2 and WP3 including WPP response to faults in the offshore
AC system, fault in the DC system and faults in the onshore AC system. OWPP shall be capable of staying
connected to the network and continuing to operate stably after the (offshore) power system has been disturbed
by faults. That capability shall be in accordance with specific voltage-against-time profiles at the connection
point. It is important to note that classical voltage-time profiles originate from (onshore) power system response,
where the voltage ramp might take time. This profile is expected to be observed when there is connection
51
PROJECT REPORT
(umbilical cable) to the onshore AC system. For the offshore AC faults, when there is no connection to the
onshore AC (i.e. DR state) the voltage profile will depend on the response of the WTGs. However, it is also
important to note that DRU-connected WTGs would possibly be tested against DRU connection, rather than a
voltage-profile.
3.4.5.1
RELEVANT PROMOTION ACTIVITY
Three tasks in WP3 include parts about FRT of DR-HVDC connected WPPs . Those tasks are:
T3.1. Functional requirements to WPPs – including requirements to WPPs on FRT of symmetrical as
well as asymmetrical offshore AC faults, faults on the DC line and faults of DR-HVDC connected WPPs
T3.2. General control algorithms – including development and simulation of control algorithms in
normal operation and in FRT operation modes for DR-HVDC connected WPPs.
T3.3. Compliance evaluation procedure – including FRT of VSC-HVDC and DR-HVDC connected
WPPs.
Those WP3 contributions can be found in the following deliverables:
D3.1 “Detailed functional requirements to WPPs” describes system stability requirements for WPP
response to symmetrical as well as asymmetrical offshore AC faults.
Deliverable 3.4: Results on control strategies of WPPs connected to DR-HVDC. This deliverable
includes a section describing the FRT controls and a section with simulation of response to
symmetrical as well as asymmetrical faults in the offshore AC system.
D3.6 “Report with the compliance test procedures for DR and VSC connected WPPs” describes
compliance test requirements, procedures for simulation-based compliance evaluation and validation
procedures for the models and simulations applied for compliance evaluation.
D3.7 “Report with the compliance evaluation results using simulations” will include the results of
simulations for various scenarios and test cases in order to to verify the effectiveness of the test
procedures for compliance evaluation.
In WP11 guidelines for best practice of compliance evaluation will be derived (D11.5 “Report with
recommendations to best practice for compliance evaluation”). These recommendations will also include
experiences of relevant parties like e.g. TSOs with FRT of VSC-HVDC connected WPPs.
3.4.5.2
EXISTING AND PROSPECTIVE CONTRIBUTIONS
It is assumed that ongoing PROMOTioN work will contribute to harmonisation in this field in the future. A report
on justified recommendations to grid codes will be written within WP11 (D11.4) and could be sent to
harmonisation bodies as potential input for future standardisation.
52
PROJECT REPORT
3.4.6
EMT MODELLING
Stability evaluation of onshore AC systems are usually done using fundamental frequency models. However, for
weak systems connections and for HVDC connected WPPs, EMT models are often required.
3.4.6.1
RELEVANT PROMOTION ACTIVITY
WP3 has developed fundamental frequency models as well as EMT models of DRU-HVDC connected WPPs.
The outcome of this work is D3.3 Models for control of wind turbines / wind power plants connected to DRHVDC” including a model and a report.
3.4.6.2
EXISTING AND PROSPECTIVE CONTRIBUTIONS
Regarding harmonization of EMT models, it is the general opinion in the industry that because of the differences
in the detailed control and protection implementation, EMT models cannot be harmonized in the same way as
fundamental frequency models have been. Instead, functional requirements to models and procedures for
model validation could be specified.
3.5
OFFSHORE CONSUMPTION
It can also be relevant to connect offshore oil/gas installations to future offshore multi-terminal HVDC systems.
An offshore oil/gas installations has an electrical load potentially ranging from 10 MW to several hundreds of
MW.
Offshore Oil & Gas installations are today a significant load in the North Sea. An offshore Oil & Gas installation
has an electrical load potentially ranging from 10 MW to few hundreds of MW in general supplied by gas turbine
generator sets. With several offshore installations, the total generation capacity in the North Sea is significant.
For example, Equinor is today a large electricity generator in the North Sea with approximately 1.5 GW installed
offshore gas turbine generators capacity.
In a shift to reduced CO2 emissions, Oil & Gas installations are looking at the possibility to be connected to an
electrical grid. The possibility to supply offshore installation from an offshore grid may boost electrification of
installation at greater distance from shore. With an interconnection to an offshore grid infrastructure, synergies
and benefits of interconnection offshore wind generation and loads may be explored. Furthermore, the offshore
industry beyond O&G, for example with focus on blue industrial growth can benefit from a readily available
offshore grid infrastructure.
An offshore HVDC grid infrastructure prepared (through harmonization) to supply power to the offshore load
clusters will greatly promote the electrification of offshore loads. The offshore sectors (including transportation
and oil/gas facilities), plus emerging sectors (including offshore aquaculture, electrical vessels, desalination
plants, ocean cleaning, offshore mining) will have direct access to an offshore grid infrastructure with integrated
53
PROJECT REPORT
wind power instead of power supplied by either their stand-alone generating systems using offshore fossil fuels
or dedicated long electrical cables from an onshore site. Additional foreseen benefits of connection of offshore
loads are: funding of offshore grid infrastructure from multiple industries, balancing and grid stability of offshore
loads.
When the entrance level to offshore becomes lower, the offshore loads can increase, e.g. reaching several 10s
of GW by 2030 in the North Sea. The distributed nature of offshore load will challenge the offshore grid
topology.
3.5.1.1
RELEVANT PROMOTION ACTIVITY
The PROMOTioN project focuses on offshore connection of wind power and does as such not consider large
offshore consumption such as oil/gas installations in detail.
3.5.1.2
EXISTING AND PROSPECTIVE CONTRIBUTIONS
PROMOTiON contribution to harmonization is to promote the opportunity to connect relatively small offshore
load (10 MW to few hundreds of MW) to an offshore HVDC grid and influence grid codes and specifications.
54
PROJECT REPORT
4 INITIAL WORKSHOPS AND CONCLUSIONS
WORKSHOP ON HVDC CONTROL AND PROTECTION
4.1
A harmonisation workshop considering HVDC control and HVDC protection was held at CEN-CENELEC
(Brussels) on 6th December 2018 with project internal and external attendees, including representatives of
harmonisation working groups.
Based on input from the PROMOTioN technical work packages (WP2, WP4 and WP9), input from external
contributors, and the discussions that took place during the workshop, the scope of possible contributions to
harmonisation has been determined, and existing contributions from the PROMOTioN project have been
identified. New possibilities for contributions that were identified will take the form of feedback on documents
from harmonisation bodies, summary documents and technical application notes to provide to harmonisation
organisations and workgroups, as well as continuation of numerous personal contributions to harmonisation
workgroups, each incorporating PROMOTioN work.
WORKSHOP ON HVDC CONNECTED WIND POWER PLANTS
4.2
The workshop on HVDC connected wind power plants took place 15 January 2019 in DTU Wind Energy,
Roskilde.
Main conclusions from the workshop on HVDC connected wind power plants:
It is recommended not to make specific standards and requirements to tests, controls and modelling of
HVDC connected wind power plants. Instead, the existing standards and requirements should be
developed ensuring that they also apply to HVDC connected WPPs. This approach will also be useful
for the increasing power electronics dominant of onshore AC power systems.
The specific implementation of new advanced control such as grid forming control and black start
control should not be standardized because this would block the development of new solutions.
Instead, the harmonization should focus on providing functional specifications.
Tests of harmonic emission and resonances will be increasingly important in the future. PROMOTioN
should make sure that the results expected late in the project will be used in harmonization after
PROMOTioN ended.
Grid forming control and black-start capability of WPPs is also expected to be advanced in the end of
the PROMOTioN project. PROMOTioN should make sure that this work is concluded with functional
specifications which can be used in harmonization after PROMOTioN ended.
PROMOTioN should follow the development of new IEC SC8A proposals for large scale offshore wind
energy integration using multi-terminal HVDC. This work is expected to focus on best-practices, for
instance publishing technical reports.
55
PROJECT REPORT
4.3
OUTLOOK
Based on the content provided in this harmonisation catalogue WP11 strives to contribute to the indicated ongoing and future harmonisation activities. The work will included further workshops and discussions with
relevant stakeholder groups resulting in several reports about harmonisation activities and proposals.
56
PROJECT REPORT
57