JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT
2010
16(1): 33–46
RISK ASSESSMENT OF CONSTRUCTION PROJECTS
Edmundas Kazimieras Zavadskas1, Zenonas Turskis2, Jolanta Tamošaitienė3
Vilnius Gediminas Technical University,
Department of Construction Technology and Management, Saulėtekio al. 11, LT-10223 Vilnius, Lithuania
E-mails: 1edmundas.zavadskas@vgtu.lt; 2zenonas.turskis@vgtu.lt; 3jolanta.tamosaitiene@vgtu.lt
Received 18 Feb. 2009; accepted 23 Nov. 2009
Abstract. The paper presents risk assessment of construction projects. The assessment is based on the multi-attribute decision-making methods. The risk evaluation attributes are selected taking into consideration the interests and goals of the
stakeholders as well as factors that have influence on the construction process efficiency and real estate value. Ranking of
objects and determination of their optimality are determined by applying TOPSIS grey and COPRAS-G methods with attributes values determined at intervals. A background and a description of the proposed model are provided and key findings of the analysis are presented.
Keywords: decision- making, construction, project, risk, assessment, multi-attribute, TOPSIS grey, COPRAS-G.
1. Introduction
The risk factor in construction business is very high.
Construction objects are unique and built only once. Construction objects life cycle is full of various risks. Risks
come from many sources: temporary project team that is
collected from different companies, construction site, etc.
Moreover, the size and complexity of construction objects are increasing which adds to the risks. This is in
addition to the political, economic, social conditions
where the object is to be undertaken. Object risk can be
defined as an uncertain event or condition that, if it occurs, has a positive or negative effect on at least one project objective, such as time, cost, quality (Project Management Institute Standards Committee 2004). The risks
cause cost and time overruns in construction projects.
2. Description of the risk assessment model
Risk management is activity process about defining
sources of uncertainty (risk identification), estimating the
consequences of uncertain events/conditions (risk analysis), generating response strategies in the light of expected outcomes and finally, based on the feedback received on actual outcomes and risks emerged, carrying
out identification, analysis and response generation steps
repetitively throughout the life cycle of an object to ensure that the project objectives are met. Risk management
in construction is a tedious task as the objective functions
tend to change during the object life cycle (Dikmen et al.
2008). Tserng et al. (2009) presented a study of ontologybased risk management framework of construction projects through project life cycle variance – covariance.
Risk value model for currency market is presented by
Aniūnas et al. (2009). Isaac and Navon (2009) described
models of building projects as a basis for change control.
JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT
http:/www.jcem.vgtu.lt
Risk management processes of construction project describe the work of all project life cycle. The risk assessment problem is analysed by many authors (Shevchenko
et al. 2008; Suhobokov 2008; Zavadskas et al. 2008a;
Zavadskas and Vaidogas 2008; Schieg 2008, 2009; Šarka
et al. 2008). Proper risk allocation in construction contracts has come to assume prominence because risk identification and risk allocation have a clear bearing on risk
handling decisions (Perera et al. 2009).
Hassanein and Afify (2007) analysed risk indentification procedure for construction contracts. Albert et al.
(2008) pointed on the investigated risk assessment. ElSayegh (2008) presented risk assessment and allocation
problem, Han et al. (2008) described web-based integrated system, Gao (2009) presented strategies with the
risk adjustment. Graves and Ringuest (2009) analysed
probabilistic dominance criteria for comparing uncertain
alternatives. Lahdelma et al. (2009) investigated uncertainties in multi-criteria decision problems.
Cost-effective solutions that meet the performance criteria can be achieved, especially if the principle of whole-life
costing is being adopted (Straub 2009). The risk management in construction object’s life cycle stages can be divided
into: macro, meso and micro levels (Fig. 1). The project life
cycle includes five steps of process management:
− Initiating;
− Planning;
− Executing;
− Monitoring and Controlling;
− Closing.
The process of risk management can be divided into
three stages:
− Identification;
− Analysis;
− Control.
ISSN 1392–3730 print / ISSN 1822–3605 online
doi:10.3846/jcem.2010.03
33
34
E. K. Zavadskas et al. Risk assessment of construction projects
RISK
ASSESSMENT
RISK
ASSESSMENT
INFORMATION
INFORMATION
MESO
LEVEL
MICRO
LEVEL
INITIATING
STAGE
INITIATING
STAGE
INFORMATION
RISK
ASSESSMENT
INFORMATION
INFORMATION
MACRO
LEVEL
INFORMATION
INITIATING
STAGE
RISK
ASSESSMENT IN
CONSTRUCTION
PROJECT
MICRO
LEVEL
MESO
LEVEL
MACRO
LEVEL
FINISHING
STAGE
CONCEPT
STAGE
PLANNING
STAGE
ORGANIZATION
STAGE
CONCEPT
STAGE
PLANNING
STAGE
CONCEPT
STAGE
PLANNING
STAGE
FINISHING
STAGE
ORGANIZATION
STAGE
FINISHING
STAGE
ORGANIZATION
STAGE
Fig. 1. Risk assessment divided according to object life cycle environment
Fig. 2. Risk allocation structure by level in construction object
The risk management process in construction is extreme and important. Risk measure includes risk level
determination of each objective and the risk analysis
estimation by applying various approaches and technology. Risk control process evaluates performance of risk
control.
2.1. Risk identification
Risk identification is the first and main step of risk management process. It is describing the competitiveness conditions and the clarification of risk and uncertainty factors
(Rutkauskas 2008; Zayed et al. 2008), recognition of potential sources of risk and uncertainty event responsibilities. The project risks can be divided into three groups:
− External;
− Project;
− Internal.
External risks are those risks that are beyond the
control of the project management team. Internal risks
can be divided according to the party who might be the
originator of risk events such as stakeholders, designer,
contractor, etc. There are various classification ways of
risk management methods.
The risk allocation structure of construction objects
is presented in Fig. 2.
External risks (environmental criteria):
− Political risk;
− Economic risk;
− Social risk;
− Weather risk.
Political risks. There are changes in government
laws of legislative system, regulations and policy and
improper administration system, etc. (Li and Liao 2007).
Economic risks. There is inconstancy of economy in
the country, repayment situation in manufacture sphere,
inflation and funding. Considering the current economic
situation, this result can be reasonably expected. Tvaronavičienė and Grybaitė (2007) analysed Lithuanian economic activities in construction. Economic disasters, as
referred to herein, are periodic economic disasters of such
magnitude that a contractor could not properly assess
either their probability or their cost impact.
35
Journal of Civil Engineering and Management, 2010, 16(1): 33–46
Social risks are the growing importance to any effort
at risk allocation. It is an area in which political and social pressures from parties having little interest in a project but having a great impact on such a project greatly
influence its outcome. The impact of the financial aid on
social and economic development of the region is analysed by Ginevičius and Podvezko (2009), risk communication in organizations is analysed by Conchie and Burns
(2008).
Weather risk. Except for extremely abnormal conditions, it is a risk for the contractor to assume, as its impact
on construction methods can by assessed by the contractor.
Project risks (construction process criteria):
− Time risk;
− Cost risk;
− Work quality;
− Construction risk;
− Technological risk.
Time risk can be determined by appraisal of the delay at construction, technology and for all works.
Cost risk. The cost of opportunity product rises due
to neglecting of management (Zavadskas et al. 2008a).
Work quality. Deflective work is considered a significant risk factor in this category because not only does
it result in construction delays and additional cost to the
contractor but it easily leads to disputes on the liability
for the deflection.
Construction risk. The risks are involved in construction delay, changes in the work and construction
technology.
Technological risk. Designing errors; lack of technologies; management errors; shortage of the qualified
labour.
Internal risks (intrinsic criteria):
− Resource risk;
− Project member risk;
− Construction site risk;
− Documents and information risk.
Resource risk. Materials and equipment involve
considerable risks. The availability and productivity of
the resources necessary to construct the project are risks
which are proper for the contractor to assume (Fisk
2003).
Project member risk. Team risk refers to issues associated with the project team members, which can increase the uncertainty of a project’s outcome, such as
team member turnover, staffing build up, insufficient
knowledge among team members, cooperation, motivation, and team communication issues.
Stakeholders’ risks rightfully belong to the stakeholder alone and should be retained by stakeholders except to the extent that they are influenced by construction
methods determined by the contractor, or created by suppliers controlled by the contractor. Stakeholders’ influence on the external environment is analysed by Mitkus
and Šostak (2008).
Designers risk. The expansion of construction has
placed great burdens upon the design professions. Main-
taining performance standards in the face of this is quite
difficult, and occasionally, design or specification deflections occur that create construction problems. Design
failures or constructability errors are becoming more and
apparent, and the architect should bear the true cost of
such failures.
Contractor risk. The prime or general contractors
are in the best position to assess the capacity of their subcontractors, and therefore it is they who should bear the
risk of not assessing the risk properly.
Subcontractor risk is that is properly assumed by the
contractor except where it arises from one of the other
listed risks attributable to stakeholder or architect (Fisk,
2003).
Suppliers risk. Default from obligations of the supplier (Fisk 2003).
Team risk. Team risk refers to issues associated with
the project team members that can increase the uncertainty of a project’s outcome, such as team member turnover, staffing build up, insufficient knowledge among
team members, cooperation, motivation, and team communication issues. Working team must analyse the business activities of all alliance members and identify various risk factors in business activities and their characters
(Gunstone 2003; Li and Liao 2007; Li et al. 2007).
Construction site risk. Accident exposures in workplace are inherent in the nature of the work and are best
assessed by the contractors and their insurance and safety
advisors (Fisk 2003).
Documents and information risk assumes: contradiction in documents; pretermission; legal and communication. Changed order negotiation and delayed dispute
resolution are significant risks during project construction. Communication is very important at all construction
period and after finishing construction work.
Protracted negotiation on disputes or valuation of
changed work is undesirable to most contractors.
Connections of the contractors with subcontractors
and suppliers are analysed by Mitkus and Trinkūnienė
(2008).
2.2. Risk analysis and control
Risk analysis. Risk and uncertainty rating identifies the
importance of the sources of risk and uncertainty about
the goals of the project. Risk assessment is accomplished
by estimating the probability of occurrence and severity
of risk impact.
More detailed information available in the construction process can be effectively used for traditional risk
management schemes such as risk control. Risk control
can be described as the five-stage process (Han et al.
2008):
− Identification;
− Analysis;
− Evaluation;
− Response;
− Monitoring.
36
E. K. Zavadskas et al. Risk assessment of construction projects
Fig. 3. Decision making model of risk assessment
Risk control establishes a plan, which reduces or
eliminates sources of risk and uncertainty impact on the
project’s deployment.
Options available for mitigation are:
− Commercial insurance;
− Self- insurance;
− Merger and diversification.
Decision making model of risk assessment is shown
in Fig. 3.
This model must be filled at every turn of risk management process.
3. Grey research methodology of risk assessment
3.1. Grey system theory
Deng (1982) developed the Grey system theory. Grey
relational analysis possesses advantages (Deng 1988,
1989):
− involves simple calculations,
− requires smaller samples,
− a typical distribution of samples is not needed,
− the quantified outcomes from the Grey relational
grade do not result in contradictory conclusions to
qualitative analysis and
Journal of Civil Engineering and Management, 2010, 16(1): 33–46
− the Grey relational grade model is a transfer func-
tional model that is effective in dealing with discrete data.
The risk assessment always deals with future and
values of criteria cannot be expressed exactly. This
multi-criteria decision-making problem can be determined not with exact criteria values, but with fuzzy values or with values at some intervals (Fig. 4).
−∞
−∞
−∞
White number
Grey number
w
Black number
w → −∞
+∞
w=b
+∞
b
+∞
b → +∞
Fig. 4. White, grey and black numbers by Deng
(Yamaguchi et al. 2007)
The Deng’s grey numbers are given as follows:
[0, 1] k ∈ [ w, b]
X ( k ,⊗ x ) =
.
0 k < w, b < k
(1)
The use of grey relational analysis in solving multiple attribute decision-making problems is analysed by
Kuo et al. (2008) and Cakir (2008).
Grey theory was applied in evaluating of national
economic strength (Lin and Liu 2007), selection of an
ERP system and intelligent sensors (Yang et al. 2007)
and in the assessment of information security (Shen et al.
2009).
3.2. MADM methods for solving the problem
Multiple attributes decision aid provides several powerful solution tools (Hwang and Yoon 1981; Figueira et al.
2005) for confronting sorting the problems. There can be
used very simplified techniques for the evaluation such
as the Simple Additive Weighting – SAW; TOPSIS –
Technique for Order Preference by Similarity to Ideal
Solution (Hwang and Yoon 1981).
A more detailed survey of multi-attribute decisionmaking methods in the construction context is presented
by many authors. Zavadskas and Antuchevičienė (2006)
presented construction objects renewal modelling by
applying multi-attribute evaluation of rural buildings’
regeneration alternatives; the multi-alternative design and
multiple criteria analysis of the life cycle of a building is
described by Banaitienė et al. (2008); selection of the
37
effective dwelling house walls by applying attribute values determined at intervals is described by Zavadskas et
al. (2008c).
The purpose is to be achieved by using attributes of
effectiveness, which have different dimensions, different
significances as well as different directions of optimization (Kendall 1970; Zavadskas 1987). The discrete criteria values can be normalized by applying different normalization methods (Zavadskas and Turskis 2008;
Ginevičius 2008). The purpose of analysis also can be
different (Kaklauskas et al. 2007; Ginevicius et al. 2007;
Bregar et al. 2008). Multiple criteria decision aid
(Hwang and Yoon 1981) provides several powerful and
effective tools (Figueira et al. 2005; Zavadskas et al.
2008b; Dzemyda et al. 2007; Ginevičius et al. 2008a, b;
Ginevičius and Podvezko 2009) for confronting sorting
the problems.
There is a wide range of methods (Ulubeyli and Kazaz 2009; Jakimavicius and Burinskiene 2009a, b;
Plebankiewicz 2009; Liaudanskiene et al. 2009; Liu
2009; Dytczak and Ginda 2009; Podvezko 2009) based
on multi-criteria utility theory: SAW – Simple Additive
Weighting (Ginevičius et al. 2008b); SAW-G (Zavadskas
et al. 2010); MOORA – Multi-Objective Optimization on
the basis of Ratio Analysis (Brauers and Zavadskas
2006; Brauers et al. 2007, 2008a, b; Kalibatas and Turskis 2008); TOPSIS – Technique for Order Preference by
Similarity to Ideal Solution (Hwang and Yoon 1981);
VIKOR – compromise ranking method (Opricovic and
Tseng 2004); COPRAS – COmplex PRoportional ASsessment (Zavadskas and Kaklauskas 1996); Game theory methods (Zavadskas and Turskis 2008; Peldschus
2008, 2009; Ginevičius and Krivka 2008; Turskis et al.
2009) and other methods (Turskis 2008).
TOPSIS is a method to identify solutions from a finite set of alternatives based upon simultaneous minimization of distance from an ideal point and maximization
of distance from a negative ideal point. The TOPSIS
method was developed by Hwang and Yoon (1981). The
only subjective input needed is relative weights of attributes. An extension of TOPSIS for group decision making
is analysed by Shih et al. (2007) and incremental analysis
of MCDM with an application to group TOPSIS is developed by Shih (2008). Lin et al. (2008) applied
TOPSIS method with grey number operations.
The COPRAS method determines a solution with
the ratio to the ideal solution and the ratio with the idealworst solution. Zavadskas et al. (2008c, d) applied
COPRAS-G method with grey number operations to the
problem with uncertain information.
The algorithm of problem solution applying
TOPSIS grey and COPRAS-G methods is presented in
Fig. 5. Either method is applicable to the solution of problems in construction: Lin et al. (2008) applied TOPSIS
method with grey number operations to the contractor
selection problem solution with uncertain information.
Zavadskas et al. (2008c) applied COPRAS-G method
with grey number operations to the selection of the effective dwelling house walls problem with uncertain information, Zavadskas et al. (2009).
E. K. Zavadskas et al. Risk assessment of construction projects
38
Fig. 5. The main algorithm of problem solution applying TOPSIS grey and COPRAS-G methods
3.2.1. TOPSIS method with attributes values
determined at intervals
The TOPSIS method is one of the best described mathematically and not simple for practical using. Lin et al.
(2008) proposed the model of TOPSIS method with attributes values determined at intervals which includes the
following steps:
Step 1: Selecting the set of the most important attributes,
describing the alternatives;
Step 2: Constructing the decision-making matrix ⊗ X .
Grey number matrix ⊗ X can be defined as:
k
k
⊗ x11
⊗ x12
... ⊗ x1km
k
k
... ⊗ x2km
k ⊗ x21 ⊗ x22
⊗X =
; i = 1, n; j = 1, m , (2)
M
O
M
M
k
k
k
⊗ xn1 ⊗ xn 2 ... ⊗ xnm
where ⊗ xijk denotes the grey evaluations of the i-th al-
ternative with respect to the j-th attribute by decision
[
]
k
is the
maker k (k = 1, ..., K ) ; ⊗ xik1 , ⊗ xik2 , ..., ⊗ xim
grey number evaluation series of the i-th alternative
given by decision maker k. It is noted that there should
be K grey decision matrices for the K members of the
group.
Journal of Civil Engineering and Management, 2010, 16(1): 33–46
Step 3: Establish the weights of the attributes q j .
Step 4: Construct the normalized grey decision matrices:
⊗ xijk,b =
wk
bijk
ij
=
,
.
k
k
k
max (bij ) max (bij ) max (bij )
i
i
i
⊗ xijk
(3)
On the other hand, the normalization of the smallerthe-better type attribute can be calculated as:
⊗ xijk, w = −
− bk
− wijk
ij
+
2
;
+
2
+
2
=
.(4)
k
k
k
min ( wij )
min ( wij )
min ( wij )
i
i
i
⊗ xijk
Step 5: Determining weights of the attributes q j .
Step 6: Construct the grey weighted normalized decision
making matrix.
Step 7: Determine the positive and negative ideal alternatives for each decision maker. The positive ideal alternak−
k+
tive – A , and the negative ideal alternative – A , of
decision maker k can be defined as:
Ak + = max bijk j ∈ J , min wijk j ∈ J '
i
i
i∈n =
[ x1k + , x2k + , ..., xmk + ] and
Ak − = min wijk j ∈ J ,
i
[ x1k − ,
(5)
max bijk j ∈ J ′
i
x2k − , ...,
i∈n =
xmk − ].
1
= ∑ mj=1 q j x kj + − wijk
2
1
d ik − = ∑ mj=1 q j x kj − − wijk
2
p
+
x kj +
(6)
k
− b ij
1/ p
p
; (7)
1/ p
p
p
k
+ x kj − − b ij
. (8)
In equations (6) and (7), for p ≥ 1 and integer, q j is
the weight for the attribute j which can be determined by
attributes’ weight determination methods. If p = 2 , then
the metric is a weighted grey number Euclidean distance
function. Equations (6) and (7) will be as follows:
d ik + =
2
2
1 m
∑ j =1 q j x kj + − wijk + x kj + − bijk ,
2
d ik − =
2
k
1 m
∑ j =1 q j x kj − − wijk + x kj − − bij
2
(9)
2
. (10)
Step 8.2: Aggregate the measures for the group. The
group separation measure of each alternative will be
aggregated through an operation, ⊗ for all decision
makers. Thus, the two group measures of the positive and
negative ideal alternatives: di* + and di* − , respectively,
are the following two equations:
d i* + = ⊗d i1+ ,..., ⊗d iK + for alternative i, and (11)
d i* − = ⊗d i1− ,..., ⊗d iK − for alternative i.
(12)
Geometric mean is adopted, and the group measures of
each alternative will be:
1/ K
K
d i* + = Π d ik +
k =1
1/ K
K
d i* − = Π d ik −
k =1
, for alternative i,
(13)
, for alternative i.
(14)
Step 9: Calculate the relative closeness Ci*+ , to the positive ideal alternative for the group. The aggregation of
relative closeness for the i-th alternative with respect to
the positive ideal alternative of the group can be expressed as:
Ci*+ =
Step 8: Calculate the separation measure of the positive
and negative ideal alternatives, dik + and dik − , for the
group. There are two sub-steps to be considered: the first
one concerns the separation measure for individuals; the
second one aggregates their measures for the group.
Step 8.1: Calculate the measures of the positive and
negative ideal alternatives individually. For decision
maker k, the separation measures of the positive ideal
alternative – dik + and negative ideal alternative – dik −
are computed through weighted grey number as:
d ik +
39
d i*−
d i*+ + d i*−
,
(15)
where 0 ≤ Ci* + ≤ 1 . The larger the index value is, the
better evaluation of alternative will be.
Step 10: Rank the preference order. A set of alternatives
now can be ranked by the descending order of the value
of Ci*+ .
3.2.2. COPRAS-G method with attributes values
determined at intervals
The procedure of using the COPRAS-G method includes
the following steps:
Step 1: Selecting the set of the most important attributes,
describing the alternatives;
Step 2: Constructing the grey decision-making matrix ⊗ X :
[⊗ x11 ] [⊗ x12 ] ... [⊗ x1m ]
[⊗ x21 ] [⊗ x22 ] ... [⊗ x2m ]
⊗X =
=
M
O
M
M
[⊗ xn1 ] [⊗ xn 2 ] ... [⊗ xnm ]
[w11; b11 ] [w12 ; b12 ] ... [w1m ; b1m ]
[w21; b21 ] [w22 ; b22 ] ... [w2m ; b2m ]
;
M
M
O
M
[wn1; bn1 ] [wn 2 ; bn2 ] ... [wnm ; bnm ]
i = 1, n; j = 1, m .,
(16)
40
E. K. Zavadskas et al. Risk assessment of construction projects
where ⊗ xij is determined by wij and bij .
Step 7: Calculating the sums Pi of the attribute values,
whose larger values are more preferable, for each alternative:
Step 3: Establishing the weights of the attributes q j .
Step 4: Normalizing the decision-making matrix ⊗ X :
wij =
bij =
wij
=
1
∑ wij + ∑ bij
2 i =1
i =1
n
n
bij
2 wij
n
;
n
∑w + ∑b
ij
ij
i =1
i =1
2bij
=
n
1 n
∑ wij + ∑ bij
2 i =1
i =1
Pi =
n
;
(17)
+ bij )
∑ (w
ij
i =1
In formula (17), wij is the lower value of the j attribute
in the alternative i of the solution; bij is the upper value
of the attribute j in the alternative i of the solution; m
is the number of attributes; n is the number of the alternatives compared.
Then, the decision-making matrix is normalized:
[⊗ x11 ]
⊗ X = [⊗ x21 ]
M
[⊗ xn1 ]
[⊗ x12 ]
[⊗ x22 ]
M
[⊗ xn 2 ]
... [⊗ x2m ] =
O
M
... [⊗ xnm ]
...
] [w12 ; b12 ]
...
[w1m ; b1m ]
[
] [w21; b22 ]
...
[w2m ; b2m ].
[
] [wn2 ; bn2 ]
(18)
n
n
∑ i =1 Pi + ∑i =1 Ri = 1.
M
...
[wnm ; bnm ]
] [wˆ ;bˆ ]
] [wˆ ;bˆ ]
12 12
21 22
M
] [wˆ
...
...
... [⊗ xˆ1m ]
... [⊗ xˆ2m ] =
O
M
... [⊗ xˆnm]
[wˆ
[wˆ
ˆ
]
ˆ
]
].
2m ; b2m
... wˆ nm; bˆnm
O
n2 ; bn2
ˆ
1m ; b1m
M
[
]
.
(24)
1
Ri ∑
R
i =1 i
1
Ri ⋅ ∑ in=1
1
Ri
.
(25)
Step 10: Determining the optimality criterion L :
L = max Qi ; i = 1, n.
i
(19)
In formula (19), q j is the weight of the j-th attribute.
[⊗ xˆ11] [⊗ xˆ12 ]
ˆ
ˆ
⊗ Xˆ = [⊗ x21] [⊗ x21]
M
M
ˆ
[⊗ xn1 ] [⊗ xˆn2 ]
i =1
n
Pi = 0 and ∑ nj =1 Ri = 1 . The formula (24) can by written
as follows:
(26)
Step 11: Determining the priority of the project.
Step 12: Calculating the utility degree of each alternative:
Ni =
⊗ xˆij = ⊗ xij ⋅ q j ; wˆ ij = wij ⋅ q j bˆij = bij ⋅ q j .
(23)
Step 9: Calculating the relative weight of each alternative
Qi :
Qi =
calculated as follows:
[
In formula (22), (m − k ) is the number of attributes
which must be minimized.
The sum of all Ri and Pi equals 1.
Step 9*: If all attributes should be minimized then
O
(22)
j = k +1
Qi = Pi +
Step 6: Calculating the weighted normalized decision
)
matrix ⊗ X . The weighted normalized values ⊗ x̂ij are
[
[
m
∑ ( wˆ ij + bˆij ).
n
Step 5: Determining weights of the attributes q j .
wˆ11; bˆ11
wˆ ; bˆ
21 21
M
wˆ n1; bˆn1
1
2
∑ Ri
M
(21)
j =1
[⊗ x1m ]
[
w11 ; b11
w21 ; b21
M
wn1 ; bn1
k
∑ ( wˆ ij + bˆij ).
Step 8: Calculating the sums Ri of attribute values,
whose smaller values are more preferable, for each alternative:
Ri =
i = 1, n and j = 1, m.
1
2
Qi
.
L
(27)
3.3. Establishing the general solution
There are two different multi-attribute decision-making
methods presented: TOPSIS grey and COPRAS-G. Solution results for the problem under investigation are
obtained compared to solution results and generated aggregated results of problem solution.
(20)
4. Case study: risk assessment of construction
projects
Application of different solution methods sometimes
yields different results. It is recommended to use several
multi-attribute decision making methods for real problem
solution and compare the results.
Due to a lack of information the attributes were determined at intervals. The TOPSIS method with attributes values determined at intervals and COPRAS-G
Journal of Civil Engineering and Management, 2010, 16(1): 33–46
method were applied to construction objects risk assessment of small-scale objects in construction. Risk assessment of four small-scale objects was made by 3 experts.
The small-scale objects are of different design, architecture, construction technology, area, different number of
floors and they are in different sites of the Vilnius region.
The initial decision making data are presented in
Table 1. In Table 1 qj is the attribute weight and alternative objects are v1 , …, v4 .
To determine the weights of the attributes, the experts’ judgment method is applied (Kendall 1970), which
has been successfully used in research by the authors
since 1987 (Zavadskas 1987). In order to establish the
weights, a survey has been carried out and 43 experts
have been questioned. These experts, basing their answers on their knowledge, experience and intuition, had
to rate attributes of effectiveness starting with the most
important ones. The rating was done on a scale from 1 to
13, where 13 meant “very important” and 1 “not important at all”. The weights of attributes were established
according to the rating methods (Zavadskas 1987) of
these experts and also demonstrated the priorities of the
user (stakeholder). The weights of the attributes obtained
by this method are presented in Table 1. All risks in construction should be as minimal as possible – optimization
direction is minimum. In Table 1 data on the following
attributes are presented:
a) External risk assessment:
⊗ x1 – political,
⊗ x2 – economic,
41
⊗ x 3 – social,
⊗ x4 – weather;
b) Project risk assessment:
⊗ x5 – time,
⊗ x6 – cost,
⊗ x7 – quality,
⊗ x8 – technological,
⊗ x9 – construction;
c) Internal risk assessment:
⊗ x10 – resource,
⊗ x11 – project member,
⊗ x12 – site,
⊗ x13 – documents and information.
Each attribute is given zero to ten score. Every expert is allowed to give grey number evaluations.
In Table 2 the normalised decision-making matrix is
presented with value of each attribute expressed at intervals, for the calculation of both: TOPSIS grey and
COPRAS-G methods. Fig. 6 is a graphic view showing
the calculation results according to TOPSIS grey method.
The calculation results according to COPRAS-G method
are presented in Fig. 7. Fig. 8 is a graphic view showing
the aggregated results.
The calculation results for each project are presented in Table 3.
Overall least risk according to calculation results by
applying TOPSIS grey method (Table 3) ranks as follows:
Project 1 f Project 3 f Project 4 f Project 2 .
Table 1. Initial decision-making matrix with values at some intervals
Expert 1
Weight
Attribute
qj
Expert 2
Expert 3
Project
v1
v2
v3
v4
v1
v2
v3
v4
v1
v2
v3
v4
⊗ x1
[w1; b1 ]
0.05
[6.0;7.0] [6.5;7.5] [5.0;5.5] [6.0;6.5] [7.0;8.0] [7.5;8.0] [6.5;8.5] [7.0;8.0] [7.5;8.5] [6.0;8.0] [6.5;8.0] [7.5;9.0]
⊗ x2
[w2 ; b2 ]
0.09
[6.0;6.5] [7.0;7.5] [5.0;6.0] [6.0;7.0] [7.0;8.5] [7.5;8.5] [6.0;7.0] [6.5;7.0] [6.5;8.0] [4.0;5.5] [5.5;6.0] [7.0;7.5]
⊗ x3
[w3 ; b3 ]
0.06
[6.0;6.5] [5.0;5.5] [4.0;5.0] [5.5;6.0] [8.0;8.5] [6.5;7.5] [5.5;6.5] [8.0;8.5] [7.0;8.5] [7.0;8.0] [5.5;6.5] [5.5;6.5]
⊗ x4
[w4 ; b4 ]
0.04
[4.5;5.5] [5.0;6.5] [5.5;7.5] [6.0;6.5] [4.0;5.0] [4.5;5.0] [6.5;7.0] [6.5;7.5] [4.5;5.0] [5.5;6.0] [5.5;7.0] [8.0;8.5]
⊗ x5
[w5 ; b5 ]
0.09
[8.0;8.5] [8.5;9.0] [6.0;6.5] [7.0;8.5] [4.0;5.0] [6.0;6.5] [7.0;7.5] [5.0;7.0] [6.5;7.0] [6.0;7.0] [5.5;6.5] [6.0;7.0]
⊗ x6
[w6 ; b6 ]
0.11
[7.0;7.5] [8.0;8.5] [4.5;5.0] [8.0;8.5] [6.0;6.5] [7.0;7.5] [5.0;5.5] [7.5;8.0] [8.0;9.0] [7.0;8.0] [5.0;6.0] [7.5;8.5]
⊗ x7
[w7 ; b7 ]
0.12
[5.0;5.5] [6.0;6.5] [5.5;7.0] [4.0;6.0] [4.5;5.5] [5.5;7.5] [7.5;8.0] [5.0;6.5] [7.0;7.5] [4.0;5.0] [6.5;7.5] [6.0;7.0]
⊗ x8
[w8 ; b8 ]
0.07
[2.0;4.0] [5.0;6.5] [4.5;5.5] [4.0;6.5] [4.0;5.5] [4.0;6.0] [4.0;5.5] [3.5;5.0] [4.0;4.5] [5.5;6.5] [3.5;6.0] [6.0;5.0]
⊗ x9
[w9 ; b9 ]
0.09
[8.0;9.0] [7.5;8.0] [7.0;8.5] [5.0;7.5] [7.0;8.5] [6.5;7.0] [7.5;9.0] [6.0;7.0] [6.0;8.0] [7.0;7.5] [6.5;7.0] [7.0;7.5]
⊗ x10 [w10 ; b10 ]
0.06
[7.0;7.5] [6.0;7.5] [5.0;6.5] [5.0;6.5] [4.5;6.5] [7.5;8.0] [6.5;7.5] [7.0;8.0] [5.0;6.0] [7.5;8.0] [6.5;8.0] [7.0;7.5]
⊗ x11 [w11; b11 ]
0.11
[5.0;6.5] [7.0;8.0] [5.5;6.0] [6.0;7.5] [4.0;5.0] [7.0;7.5] [5.0;5.5] [6.5;7.0] [5.0;6.0] [6.5;7.0] [6.0;6.5] [6.5;7.0]
⊗ x12 [w12 ; b12 ]
0.04
[7.0;7.5] [4.0;5.5] [6.0;6.5] [5.0;6.0] [5.0;5.5] [7.0;8.0] [7.0;7.5] [8.0;8.5] [7.0;8.0] [5.0;6.0] [6.5;7.0] [6.0;6.5]
⊗ x13 [w13; b13 ]
0.07
[5.0;6.0] [3.0;4.5] [6.0;7.0] [6.0;6.5] [4.0;5.0] [4.5;5.0] [6.5;7.5] [4.5;5.0] [4.0;5.0] [4.5;5.5] [5.0;5.5] [7.0;7.5]
42
Table 2. Normalized decision-making matrix
Expert 1
Expert 2
Project
Attribute
v1
⊗ x1
⊗ x2
⊗ x3
⊗ x4
⊗ x5
⊗ x6
⊗ x7
⊗ x8
⊗ x9
⊗ x10
⊗ x11
⊗ x12
⊗ x13
v2
v3
v4
v1
Expert 3
[w1 ; b1 ]
[w2 ; b2 ]
[0.80;0.60]
[0.92;0.50]
[1.00;0.90]
[0.80;0.70]
[0.92;0.77]
v2
v3
TOPSIS grey method
[0.85;0.92]
[1.00;0.69]
v4
v1
v2
v3
v4
[0.80;0.70]
[0.60;0.50]
[1.00;0.80]
[0.80;0.60]
[0.83;0.67]
[0.75;0.58]
[1.00;0.83]
[0.92;0.83]
[0.38;0.13]
[1.00;0.63]
[0.63;0.50]
[0.25;0.13]
[w3 ; b3 ]
[w4 ; b4 ]
[w5 ; b5 ]
[0.50;0.38]
[0.75;0.63]
[1.00;0.75]
[0.63;0.50]
[0.55;0.45]
[0.82;0.64]
[1.00;0.82]
[0.55;0.45]
[0.60;0.30]
[0.60;0.40]
[1.00;0.70]
[0.90;0.70]
[1.00;0.78]
[0.89;0.56]
[0.78;0.73]
[0.67;0.78]
[1.00;0.75]
[0.88;0.75]
[0.38;0.25]
[0.38;0.13]
[1.00;0.89]
[0.78;0.67]
[0.78;0.44]
[0.22;0.11]
[0.67;0.58]
[0.58;0.50]
[1.00;0.92]
[0.83;0.58]
[1.00;0.75]
[0.50;0.38]
[0.25;0.13]
[0.75;0.25]
[0.82;0.73]
[0.91;0.64]
[1.00;0.82]
[0.91;0.73]
[w6 ; b6 ]
[0.44;0.33]
[0.33;0.11]
[1.00;0.89]
[0.44;0.11]
[0.80;0.70]
[0.60;0.50]
[0.55;0.90]
[0.50;0.40]
[0.40;0.20]
[0.60;0.40]
[1.00;0.80]
[0.50;0.30]
[w7 ; b7 ]
[0.75;0.63]
[0.50;0.38]
[0.63;0.25]
[1.00;0.50]
[1.00;0.78]
[0.78;0.33]
[0.33;0.22]
[0.89;0.56]
[0.25;0.13]
[1.00;0.75]
[0.38;0.13]
[0.50;0.25]
[w8 ; b8 ]
[1.00;0.86]
[0.57;0.14]
[0.71;0.43]
[0.86;0.14]
[0.86;0.43]
[0.86;0.29]
[0.86;0.43]
[1.00;0.57]
[0.86;0.71]
[0.43;0.14]
[1.00;0.29]
[0.29;0.57]
[0.92;0.77]
[0.75;0.58]
[1.00;0.67]
[0.92;0.67]
[0.75;0.50]
[w9 ; b9 ]
[0.40;0.20]
[0.50;0.40]
[0.60;0.30]
[1.00;0.50]
[0.83;0.58]
[0.92;0.83]
[0.75;0.50]
[0.80;0.82]
[1.00;0.67]
[0.83;0.75]
[0.92;0.83]
[0.83;0.75]
[w10 ; b10 ]
[0.60;0.40]
[0.80;0.50]
[1.00;0.70]
[0.80;0.70]
[1.00;0.56]
[0.33;0.22]
[0.56;0.33]
[0.44;0.22]
[1.00;0.80]
[0.50;0.30]
[0.70;0.40]
[0.60;0.50]
[1.00;0.70]
[0.60;0.40]
[0.90;0.80]
[0.80;0.50]
[1.00;0.75]
[0.25;0.13]
[0.75;0.63]
[0.38;0.25]
[1.00;0.80]
[0.70;0.60]
[0.80;0.70]
[0.70;0.60]
[0.25;0.13]
[1.00;0.63]
[0.50;0.38]
[0.86;0.50]
[1.00;0.90]
[0.60;0.40]
[0.60;0.50]
[0.40;0.30]
[0.60;0.40]
[1.00;0.80]
[0.70;0.60]
[0.80;0.70]
[w13 ; b13 ]
[0.75;0.50]
[1.00;0.88]
[0.38;0.25]
[0.50;0.38]
[1.00;0.75]
[0.88;0.75]
[0.38;0.13]
[0.88;0.75]
[1.00;0.75]
[0.88;0.63]
[0.75;0.63]
[0.25;0.13]
COPRAS-G method
⊗ x1
⊗ x2
⊗ x3
⊗ x4
⊗ x5
⊗ x6
⊗ x7
⊗ x8
⊗ x9
⊗ x10
⊗ x11
⊗ x12
⊗ x13
[ w1 ; b1 ]
[w2 ; b2 ]
[w3 ; b3 ]
[0.24;0.28]
[0.26;0.30]
[0.20;0.22]
[0.24;0.26]
[0.23;0.26]
[0.25;0.26]
[0.21;0.28]
[0.23;0.26]
[0.25;0.28]
[0.20;0.26]
[0.21;0.26]
[0.25;0.30]
[0.24;0.25]
[0.27;0.29]
[0.20;0.24]
[0.24;0.27]
[0.24;0.28]
[0.26;0.30]
[0.21;0.24]
[0.23;0.24]
[0.26;0.30]
[0.16;0.22]
[0.22;0.24]
[0.28;0.30]
[0.28;0.30]
[0.23;0.25]
[0.18;0.23]
[0.25;0.28]
[0.27;0.29]
[0.22;0.25]
[0.19;0.22]
[0.27;0.29]
[0.26;0.31]
[0.26;0.30]
[0.19;0.24]
[0.20;0.24]
[w4 ; b4 ]
[w5 ; b5 ]
[0.19;0.23]
[0.21;0.28]
[0.23;0.32]
[0.26;0.28]
[0.17;0.22]
[0.20;0.22]
[0.28;0.30]
[0.28;0.33]
[0.18;0.20]
[0.22;0.24]
[0.22;0.28]
[0.32;0.34]
[0.26;0.27]
[0.27;0.29]
[0.19;0.21]
[0.23;0.27]
[0.17;0.21]
[0.25;0.27]
[0.29;0.31]
[0.21;0.29]
[0.25;0.27]
[0.23;0.29]
[0.21;0.25]
[0.23;0.27]
[w6 ; b6 ]
[0.25;0.27]
[0.27;0.31]
[0.16;0.18]
[0.25;0.31]
[0.23;0.25]
[0.26;0.28]
[0.19;0.21]
[0.28;0.30]
[0.27;0.31]
[0.24;0.27]
[0.17;0.20]
[0.25;0.29]
[w7 ; b7 ]
[0.22;0.24]
[0.26;0.29]
[0.24;0.31]
[0.18;0.26]
[0.18;0.22]
[0.22;0.30]
[0.30;0.32]
[0.20;0.26]
[0.28;0.30]
[0.16;0.20]
[0.26;0.30]
[0.24;0.28]
[w8 ; b8 ]
[0.18;0.20]
[0.25;0.33]
[0.23;0.28]
[0.20;0.33]
[0.21;0.29]
[0.21;0.32]
[0.21;0.29]
[0.19;0.27]
[0.20;0.22]
[0.27;0.32]
[0.17;0.29]
[0.24;0.29]
[w9 ; b9 ]
[0.26;0.30]
[0.25;0.26]
[0.23;0.28]
[0.17;0.25]
[0.24;0.29]
[0.22;0.24]
[0.26;0.31]
[0.21;0.24]
[0.21;0.28]
[0.25;0.27]
[0.23;0.25]
[0.25;0.27]
[w10 ; b10 ]
[0.27;0.30]
[0.23;0.29]
[0.19;0.25]
[0.23;0.25]
[0.16;0.23]
[0.27;0.29]
[0.23;0.27]
[0.25;0.29]
[0.18;0.21]
[0.27;0.30]
[0.23;0.29]
[0.25;0.27]
[w11; b11 ]
[0.19;0.25]
[0.27;0.31]
[0.21;0.23]
[0.23;0.29]
[0.17;0.21]
[0.29;0.32]
[0.21;0.23]
[0.27;0.29]
[0.20;0.24]
[0.26;0.28]
[0.24;0.26]
[0.26;0.28]
[w12 ; b12 ]
[0.29;0.32]
[0.17;0.23]
[0.25;0.27]
[0.21;0.25]
[0.18;0.19]
[0.25;0.28]
[0.25;0.27]
[0.28;0.30]
[0.27;0.31]
[0.19;0.23]
[0.25;0.27]
[0.23;0.25]
[w13 ; b13 ]
[0.22;0.26]
[0.18;0.20]
[0.29;0.31]
[0.26;0.29]
[0.19;0.24]
[0.21;0.24]
[0.31;0.36]
[0.21;0.24]
[0.18;0.23]
[0.20;0.25]
[0.23;0.25]
[0.32;0.34]
E. K. Zavadskas et al. Risk assessment of construction projects
[w11; b11 ]
[w12 ; b12 ]
Journal of Civil Engineering and Management, 2010, 16(1): 33–46
43
Table 3. Solution results by applying TOPSIS grey and COPRAS-G methods
Expert 1
d
Calculation results by
applying TOPSIS grey
method
Calculation results by
applying COPRAS-G
method
v1
v2
v3
v4
v1
v2
v3
v4
1+
d
0.449
0.532
0.379
0.496
Expert 2
1−
0.510
0.307
0.447
0.438
d
2+
d
0.489
0.725
0.503
0.493
Expert 3
2−
0.637
0.318
0.402
0.555
d
3+
d
0.513
0.387
0.393
0.520
Aggregated
3−
0.385
0.448
0.421
0.224
d
d *−
Ci*+
Rank
0.511
0.358
0.423
0.406
0.514
0.395
0.499
0.446
1
4
2
3
*+
0.484
0.548
0.425
0.503
N1
N2
N3
NA
0.931
0.877
1.000
0.931
1.000
0.857
0.865
0.877
0.946
0.984
1.000
0.883
0.959
0.906
0.955
0.897
Rank
1
3
2
4
The projects risk according to COPRAS-G method
ranks as follows:
Project 1 f Project 3 f Project 2 f Project 4 .
The calculation results showed that the first project
has the least risk and the second or the fourth project are
most risky. The first alternative was selected and implemented.
5. Conclusions
Fig. 6. Calculation results according to COPRAS-G
method
Fig.7. Calculation results according to TOPSIS grey
method
Decision-making is very important in the construction
management, such as risk assessment results in construction projects, contractor and supplier selection, etc.
In real life multi-attribute modelling of multialternative assessment problems have some attribute values, which deal with the future and must be expressed at
intervals.
Sometimes calculation according to different methods yields different results. For decision-making it is
reasonable to apply several methods and select the best
alternative according to aggregated results.
This model and solution results are of both practical
and scientific interest. It allows all members of the construction business to make a decision by evaluating multiple attributes when values of initial data are given at
intervals.
The research results show the different risk levels of
construction objects.
References
Fig. 8. Aggregated calculation results (COPRAS-G and
TOPSIS grey methods)
Albert, I.; Grenier, E.; Denis, J.-B.; Rousseau, J. 2008. Quantitative risk assessment from farm to fork and beyond: a
global bayesian approach concerning food-borne diseases,
Risk Analysis 28(2): 557–571.
doi:10.1111/j.1539-6924.2008.01000.x
Aniūnas, P.; Nedzveckas, J.; Krušinskas, R. 2009. Variance –
covariance risk value model for currency market, Inzinerine
Ekonomika – Engineering Economics 1: 18–27.
Banaitienė, N.; Banaitis, A.; Kaklauskas, A.; Zavadskas, E. K.
2008. Evaluating the life cycle of building: A multivariant
and multiple criteria approach, Omega – International
Journal of Management Science 36(3): 429–441.
doi:10.1016/j.omega.2005.10.010
44
Brauers, W. K.; Zavadskas, E. K.; Peldschus, F.; Turskis, Z.
2008a. Multi-objective decision-making for road design,
Transport 23(3): 183–192.
doi:10.3846/1648-4142.2008.23.183-193
Brauers, W. K.; Zavadskas, E. K.; Turskis, Z.; Vilutienė, T.
2008b. Multi-objective contractor’s ranking by applying
the MOORA method, Journal of Business Economics and
Management 9(4): 245–255.
doi:10.3846/1611-1699.2008.9.245-255
Brauers, W. K. M.; Ginevicius, R.; Zavadskas, E. K.; Antucheviciene, J. 2007. The European Union in a transition economy, Transformation in Business and Economy 6(2): 21–37.
Brauers, W. K.; Zavadskas, E. K. 2006. The MOORA method
and its application to privatization in a transition economy, Control and Cybernetics 35(2): 443–468.
Bregar, A.; Györkös, J.; Jurič, M. B. 2008. Interactive aggregation/disaggregation dichotomic sorting procedure for
group decision analysis based on the threshold model, Informatica 19(2): 161–190.
Cakir, O. 2008. The grey extent analysis, Kybernetes 37(7):
997–1015. doi:10.1108/03684920810884379
Conchie, S. M.; Burns, C. 2008. Trust and risk communication
in high-risk organizations: a test of principles from social
risk research, Risk Analysis 28(1): 141–149.
doi:10.1111/j.1539-6924.2008.01006.x
Deng, J. L. 1982. Control problems of grey system, Systems and
Control Letters 1(5): 288–294.
doi:10.1016/S0167-6911(82)80025-X
Deng, J. L. 1988. Properties of relational space for grey system,
in Essential Topics on Grey System – Theory and Applications (J. L. Deng, Ed.). Beijing: China Ocean, 1–13.
Deng, J. L. 1989. Introduction to grey system theory, The Journal of Grey System 1(1): 1–24.
Dikmen, I.; Birgonul, M. T.; Anac, C.; Tah, J. H. M.; Aouad, G.
2008. Learning from risks: a tool for post-project risk assessment, Automation in Construction 18(1): 42–50.
doi:10.1016/j.autcon.2008.04.008
Dytczak, M.; Ginda, G. 2009. Identification of building repair
policy choice criteria role, Technological and Economic
Development of Economy 15(2): 213–228.
doi:10.3846/1392-8619.2009.15.213-228
Dzemyda, G.; Šaltenis, V.; Tiešis, V. 2007. Optimizavimo metodai [Optimization Methods]. Vilnius: Mokslo aidai (in
Lithuanian).
El-Sayegh, S. M. 2008. Risk assessment and allocation in the
UAE construction industry, International Journal of Project Management 26(4): 431–438.
doi:10.1016/j.ijproman.2007.07.004
Figueira, J.; Greco, S.; Ehrgott, M. (Eds.). 2005. Multiple Criteria
Decision Analysis: State of the Art Surveys. Springer, Berlin.
Fisk, E. R. 2003. Construction Project Administration. Seventh
Edition. Prentice Hall Upper Saddle River, New Jersey
Columbus, Ohio.
Gao, P.-W. 2009. Options strategies with the risk adjustment,
European Journal of Operational Research 192(3): 975–
980. doi:10.1016/j.ejor.2007.10.010
Ginevičius, R.; Podvezko, V. 2009. Evaluating the changes in
economic and social development of Lithuanian counties
by multiple criteria methods, Technological and Economic Development of Economy 15(3): 418–436.
doi:10.3846/1392-8619.2009.15.418-436
Ginevičius, R. 2008. Normalization of quantities of various
dimensions, Journal of Business Economics and Management 9(1): 79–86. doi:10.3846/1611-1699.2008.9.79-86
E. K. Zavadskas et al. Risk assessment of construction projects
Ginevičius, R.; Krivka, A. 2008. Application of game theory for
duopoly market analysis, Journal of Business Economics
and Management 9(3): 207–217.
doi:10.3846/1611-1699.2008.9.207-217
Ginevičius, R.; Podvezko, V.; Bruzgė, Š. 2008a. Evaluating the
effect of state aid to business by multicriteria methods,
Journal of Business Economics and Management 9(3):
167–180. doi:10.3846/1611-1699.2008.9.167-180
Ginevičius, R.; Podvezko, V.; Raslanas, S. 2008b. Evaluating
the alternative solutions of wall insulation by multicriteria
methods, Journal of Civil Engineering and Management
14(4): 217–226. doi:10.3846/1392-3730.2008.14.20
Ginevicius, R.; Podvezko, V.; Andruskevicius, A. 2007. Quantitative evaluation of building technology, International
Journal of Technology Management 40(1/2/3): 192–214.
Graves, S. B.; Ringuest, J. L. 2009. Probabilistic dominance
criteria for comparing uncertain alternatives: A tutorial,
Omega – International Journal of Management Science
37(2): 346–357. doi:10.1016/j.omega.2007.03.001
Gunstone, S. 2003. Risk assessment and management of patients whom self-neglect: a ‘grey area’ for mental health
workers, Journal of Psychiatric and Mental Health Nursing
10(3): 287–296. doi:10.1046/j.1365-2850.2003.00568.x
Han, S. H.; Kim, D. Y.; Kim, H.; Jang, W.-S. 2008. A webbased integrated system for international project risk
management, Automation in Construction 17(3): 342–
356. doi:10.1016/j.autcon.2007.05.012
Hassanein, A. A. G.; Afify, H. M. F. 2007. A risk identification
procedure for construction contracts-a case study of power
station projects in Egypt, Civil Engineering and Environmental
Systems 24(1): 3–14. doi:10.1080/10286600600910104
Hwang, C. L.; Yoon, K. S. 1981. Multiple Attribute Decision
Making Methods and Applications. Springer-Verlag.
Berlin, Heidelberg, New York.
Isaac, S.; Navon, R. 2009. Modeling building projects as a basis
for change control, Automation in Construction 18(5):
656–664. doi:10.1016/j.autcon.2009.01.001
Jakimavicius, M.; Burinskiene, M. 2009a. Assessment of Vilnius city development scenarios based on transport system
modelling and multicriteria analysis, Journal of Civil Engineering and Management 15(4): 361–368.
doi:10.3846/1392-3730.2009.15.361-368
Jakimavičius, M.; Burinskienė, M. 2009b. A GIS and multicriteria-based analysis and ranking of transportation zones
of Vilnius city, Technological and Economic Development of Economy 15(1): 39–48.
doi:10.3846/1392-8619.2009.15.39-48
Kalibatas, D.; Turskis, Z. 2008. Multicriteria evaluation of inner
climate by using MOORA method, Information Technology and Control 37(1): 79–83.
Kaklauskas, A.; Zavadskas, E. K.; Trinkūnas, V. 2007. A multiple criteria decision support online system for construction, Engineering Applications of Artificial Intelligence
20(2): 163–175. doi:10.1016/j.engappai.2006.06.009
Kendall, M. G. 1970. Rank Correlation Methods. 4th ed.
London Griffin.
Kuo, Y.; Yang, T.; Huang, G.-W. 2008. The use of grey relational analysis in solving multiple attribute decisionmaking problems, Computers & Industrial Engineering
55(1): 80–93. doi:10.1016/j.cie.2007.12.002
Lahdelma, R.; Makkonen, S.; Salminen, P. 2009. Two ways to
handle dependent uncertainties in multi-criteria decision
problems, Omega – International Journal of Management
Science 37: 79–92. doi:10.1016/j.omega.2006.08.005
Journal of Civil Engineering and Management, 2010, 16(1): 33–46
Li, Y.; Liao, X. 2007. Decision support for risk analysis on
dynamic alliance, Decision Support Systems 42(4): 2043–
2059. doi:10.1016/j.dss.2004.11.008
Li, G.-D.; Yamaguchi, D.; Nagai, M. 2007. A grey-based decision-making approach to the supplier selection problem,
Mathematical and Computer Modelling 46(3–4): 573–
581. doi:10.1016/j.mcm.2006.11.021
Liaudanskiene, R.; Ustinovicius, L.; Bogdanovicius, A. 2009.
Evaluation of construction process safety solutions using
the TOPSIS method, Inzinerine Ekonomika – Engineering
Economics (4): 32–40.
Lin, Y.; Liu, S. 2007. National economic strength as evaluated
using grey systems theory, Kybernetes 36(1): 89–97.
doi:10.1108/03684920710741170
Lin, Y.-H.; Lee, P.-C.; Chang, T.-P.; Ting, H.-I. 2008. Multiattribute group decision making model under the condition of uncertain information, Automation in Construction
17(6): 792–797. doi:10.1016/j.autcon.2008.02.011
Liu, P. 2009. Multi-attribute decision-making research method
based on interval vague set and TOPSIS method, Technological and Economic Development of Economy 15(3):
453–463. doi:10.3846/1392-8619.2009.15.453-463
Mitkus, S.; Šostak, O. R. 2008. Modelling the process for defence of third party rights infringed while implementing
construction investment projects, Technological and Economic Development of Economy 14(2): 208–223.
doi:10.3846/1392-8619.2008.14.208-223
Mitkus, S.; Trinkuniene, E. 2008. Reasoned decisions in construction contracts evaluation, Technological and Economic Development of Economy 14(3): 402–416.
doi:10.3846/1392-8619.2008.14.402-416
Opricovic, S.; Tzeng, G.-H. 2004. Compromise solution by
MCDM methods: A comparative analysis of VIKOR and
TOPSIS, European Journal of Operational Research
156(2): 445–455. doi:10.1016/S0377-2217(03)00020-1
Peldschus, F. 2009. The analysis of the quality of the results
obtained with the methods of multi-criteria decisions,
Technological and Economic Development of Economy
15(4): 580–592. doi:10.3846/1392-8619.2009.15.580-592
Peldschus, F. 2008. Experience of the game theory application
in construction management, Technological and Economic Development of Economy 14(4): 531–545.
doi:10.3846/1392-8619.2008.14.531-545
Perera, B. A. K. S.; Dhanasinghe, I.; Rameezdeen, R. 2009. Risk
management in road construction: the case of Sri Lanka, International Journal of Strategic Property Management
13(2): 87–102. doi:10.3846/1648-715X.2009.13.87-102
Plebankiewicz, E. 2009. Contractor prequalification model
using fuzzy sets, Journal of Civil Engineering and Management 15(4): 377–385.
doi:10.3846/1392-3730.2009.15.377-385
Podvezko, V. 2009. Application of AHP technique, Journal of
Business Economics and Management 10(2): 181–189.
doi:10.3846/1611-1699.2009.10.181-189
Project Management Institute Standards Committee. A Guide to
the project management body of knowledge. 3rd ed. PMI
2004.
Rutkauskas, A. V. 2008. On the sustainability of regional competitiveness development considering risk, Technological
and Economic Development of Economy 14(1): 89–99.
doi:10.3846/2029-0187.2008.14.89-99
Shen, V. R. L.; Chung, Y.-F.; Chen, T.-S. 2009. A novel application of grey system theory to information security.
45
Part I, Computer Standards & Interfaces 31(2): 277–281.
doi:10.1016/j.csi.2007.11.018
Shevchenko, G.; Ustinovichius, L.; Andruškevičius, A. 2008.
Multi-attribute analysis of investments risk alternatives in
construction, Technological and Economic Development
of Economy 14(3): 428–443.
doi:10.3846/1392-8619.2008.14.428-443
Shih, H.-S. 2008. Incremental analysis for MCDM with an
application to group TOPSIS, European Journal of Operational Research 186(2): 720–734.
doi:10.1016/j.ejor.2007.02.012
Shih, H.-S.; Shyur, H.-J.; Lee, E. S. 2007. An extension of
TOPSIS for group decision making, Mathematical and
Computer Modelling 45(7–8): 801–813.
doi:10.1016/j.mcm.2006.03.023
Schieg, M. 2009. Model for integrated project management,
Journal of Business Economics and Management 10(2):
149–160. doi:10.3846/1611-1699.2009.10.149-160
Schieg, M. 2008. Strategies for avoiding asymmetric information in construction project management, Journal of Business Economics and Management 9(1): 47–51.
doi:10.3846/1611-1699.2008.9.47-51
Straub, A. 2009. Cost savings from performance-based maintenance contracting, International Journal of Strategic
Property Management 13(3): 205–217.
doi:10.3846/1648-715X.2009.13.205-217
Suhobokov, A. 2007. Application of Monte Carlo simulation
methods in risk management, Journal of Business Economics and Management 8(3): 165–168.
Šarka, V.; Zavadskas, E. K.; Ustinovičius, L.; Šarkienė, E.;
Ignatavičius, Č. 2008. System of project multicriteria decision synthesis in construction, Technological and Economic Development of Economy 14(4): 546–565.
doi:10.3846/1392-8619.2008.14.546-565
Turskis, Z.; Zavadskas, E. K.; Peldschus, F. 2009. Multi-criteria
optimization system for decision making in construction
design and management, Inzinerine Ekonomika – Engineering Economics 1: 7–17.
Turskis, Z. 2008. Multi-attribute contractors ranking method by
applying ordering of feasible alternatives of solutions in
terms of preferability technique, Technological and Economic Development of Economy 14(2): 224–239.
doi:10.3846/1392-8619.2008.14.224-239
Tvaronavičienė, M.; Grybaitė, V. 2007. Impact of FDI on
Lithuanian economy: insight into development of main
economic activities, Journal of Business Economics and
Management 8(4): 285–290.
Tserng, H. P.; Yin, S. Y. L.; Dzeng, R. J.; Wou, B.; Tsai, M. D.;
Chen, W. Y. 2009. A study of ontology-based risk management framework of construction projects through project life cycle, Automation in Construction 18(7): 994–
1008. doi:10.1016/j.autcon.2009.05.005
Ulubeyli, S.; Kazaz, A. 2009. A multiple criteria decision making approach to the selection of concrete pumps, Journal
of Civil Engineering and Management 15(4): 369–376.
doi:10.3846/1392-3730.2009.15.369-376
Zayed, T.; Amer, M.; Pan, J. 2008. Assessing risk and uncertainty inherent in Chinese highway projects using AHP,
International Journal of Project Management 26(4): 408–
419. doi:10.1016/j.ijproman.2007.05.012
Zavadskas, E. K.; Vilutiene, T.; Turskis, Z.; Tamosaitiene, J.
2010. Contractor selection for construction works by applying SAW-G and TOPSIS grey techniques, Journal of
Business Economics and Management 11(1): 34–54.
E. K. Zavadskas et al. Risk assessment of construction projects
46
Zavadskas, E. K.; Kaklauskas, A.; Turskis, Z.; Tamosaitiene, J.
2009. Multi-attribute decision-making model by applying
grey numbers, Informatica 20(2): 305–320.
Zavadskas, E. K.; Turskis, Z. 2008. A new logarithmic normalization method in games theory, Informatica 19(2): 303–314.
Zavadskas, E. K.; Vaidogas, E. R. 2008. Bayesian reasoning in
managerial decisions on the choice of equipment for the
prevention of industrial accidents, Inzinerine Ekonomika –
Engineering Economics 5: 32–40.
Zavadskas, E. K.; Turskis, Z.; Tamošaitiene, J. 2008a. Contractor selection of construction in a competitive environment,
Journal of Business Economics and Management 9(3):
181–187. doi:10.3846/1611-1699.2008.9.181-187
Zavadskas, E. K.; Raslanas, S.; Kaklauskas, A. 2008b. The
selection of effective retrofit scenarios for panel houses in
urban neighbourhoods based on expected energy savings
and increase in market value: The Vilnius case, Energy
and Buildings 40(4): 573–587.
doi:10.1016/j.enbuild.2007.04.015
Zavadskas, E. K.; Kaklauskas, A.; Turskis, Z.; Tamošaitienė, J.
2008c. Selection of the effective dwelling house walls by
applying attributes values determined at intervals, Journal
of Civil Engineering and Management 14(2): 85–93.
doi:10.3846/1392-3730.2008.14.3
Zavadskas, E. K.; Turskis, Z.; Tamošaitienė, J. 2008d. Construction risk assessment of small scale objects by applying
TOPSIS method with attributes values determined at intervals, Computer Modelling and New Technologies
12(4): 38–43.
Zavadskas, E. K.; Antuchevičienė, J. 2006. Development of an
indicator model and ranking of sustainable revitalization
alternatives of derelict property: a Lithuanian case study,
Sustainable Development 14(5): 287–299.
doi:10.1002/sd.285
Zavadskas, E. K.; Kaklauskas, A. 1996. Pastatų sistemotechninis įvertinimas [Multiple criteria evaluation of buildings]. Vilnius: Technika (in Lithuanian).
Zavadskas, E. K. 1987. Complex estimation and choice of resource saving decisions in construction. Vilnius: Mokslas
(in Russian).
Yang, J.-B.; Wu, C.-T.; Tsai, C.-H. 2007. Selection of an ERP
system for a construction firm in Taiwan: A case study,
Automation in Construction 16(6): 787–796.
doi:10.1016/j.autcon.2007.02.001
Yamaguchi, D.; Li, G.-D.; Chen, L.-C.; Nagai, M. 2007. Reviewing Crisp, Fuzzy, Grey and Rough Mathematical
Models, in Proc. of 2007 IEEE International Conference
on Grey Systems and Intelligent Services, November 18–
20, 2007, Nanjing, China, 547–552.
STATYBOS PROJEKTŲ RIZIKOS VERTINIMAS
E. K. Zavadskas, Z. Turskis, J. Tamošaitienė
Santrauka
Straipsnyje vertinama statybos projektų rizika. Vertinimas pagrįstas įvairiais daugiatikslio vertinimo metodais. Rizikos
vertinimo rodikliai atrenkami, atsižvelgiant į suinteresuotų šalių interesus, tikslus ir veiksnius, kurie turi įtakos statybos
proceso efektyvumui ir nekilnojamojo turto vertės didinimui. Projektai surikiuoti pagal naudingumą, nustatyti santykiniai
jų optimalumo dydžiai. Uždavinio modeliui aprašyti ir jam išspręsti taikomi TOPSIS grey ir COPRAS-G metodai. Projektų savybės aprašomos efektyvumo rodiklių reikšmėmis, apibrėžiamomis intervaluose. Straipsnyje aprašomas taikomas
modelis, atlikta uždavinio analizė ir pateikiamos trumpos išvados.
Reikšminiai žodžiai: sprendimų priėmimas, statyba, rizika, įvertinimas, rodikliai, TOPSIS grey, COPRAS-G, rangavimas.
Edmundas Kazimieras ZAVADSKAS. Doctor Habil, the principal vice-rector of Vilnius Gediminas Technical University and Head of the Dept of Construction Technology and Management at Vilnius Gediminas Technical University, Vilnius, Lithuania. He has a PhD in building structures (1973) and Dr Sc (1987) in building technology and management. He
is a member of the Lithuanian and several foreign Academies of Sciences. He is doctore honoris causa at Poznan, SaintPetersburg, and Kiev. He is a member of international organisations and has been a member of steering and programme
committees at many international conferences. E. K. Zavadskas is a member of editorial boards of several research journals. He is the author of over 50 books published in Lithuanian, Russian, German, and English. He has published more
than 350 scientific papers. Research interests are: building technology and management, decision-making theory, grey relation, automation in design and decision support systems.
Zenonas TURSKIS. Doctor, a senior research fellow of Construction Technology and Management Laboratory of Vilnius Gediminas Technical University, Lithuania. He is the author of 1 book published in Lithuanian and 30 scientific
papers. His research interests include building technology and management, decision-making in construction, computeraided automation in design and expert systems.
Jolanta TAMOŠAITIENĖ. Doctor, Dean assistant of Civil Engineering Faculty, Vilnius Gediminas Technical University, reader of the Dept of Construction Technology and Management, Vilnius Gediminas Technical University, Lithuania. BSc degree (building technology and management), Vilnius Gediminas Technical University (2000). MSc degree
(Building management and economics), Vilnius Gediminas Technical University (2002). She published 9 scientific papers. Research interests: construction technology and organisation, construction project administration, decision-making
and grey theory.
View publication stats