Contents
Editorial:
To Bring Justice Within the Reach of All Men
2
Civil Justice Forum:
Justice Is Blind
4
The Hamlyn Lectures: Civil Justice
8
Adjudication and Inquisition: inquisito cum promovente Revisited
10
Case Update:
No Bond On the Dome
11
Gone With the Wind
12
Holding Out
13
Litigant in Person’s Costs
13
Construction Adjudication:
Adjudication: Is There a Flaw in the Logic?
Simon J A Tolson
14
Jurisdiction and the Adjudicator - and Then There Were Three
Simon J A Tolson
15
Book Reviews
18
Editorial Board
Honorary Members:
President: The Rt Hon Lord Justice Otton
Vice President: HH James Fox-Andrews QC
General Editor:
Michael P Reynolds, LLM, MSc, FCIArb,
Solicitor
International:
Laure Leserviosier (International Commercial
Arbitration Group, Clifford Chance,
London)
Insurance:
Alison Green (4, Field Court)
Arbitration:
Alan Shilston, BSc, CEng, FICE, FCIWEM,
FIHT, FCIArb
The information provided and the views expressed in this publication are for further consideration and should not be acted upon
without independent consideration and professional advice. The views of contributors are not necessarily those of the Publishers or
Editor(s). Neither CLT Professional Publishing Ltd, the Editor(s), nor the contributors to this service will accept any responsibility
for any loss occasioned to any person acting or refraining from acting as a result of material contained in this publication.
Construction & Engineering Law January / February 2000
Contents
Members:
Roger Bloomfield BSc, FRIBA, (Bickerdike
Allen Partners)
Suzanne Burn LLB, LLM, M.Phil, Deputy
District Judge
Ronan Champion BSc, (Northcroft)
Chris Ennis MSc, FRICS, FCIArb, (Northcroft)
Dr Robert Gaitskell QC, (Keating Chambers)
Fiona Hammond, Solicitor, (BAA)
Rudi Klein
Joe Jacob, (Law Dept., London School of
Economics)
Vivian Ramsey QC, MA, CEng, MICE,
(Keating Chambers)
Nick Stuart BSc, MSc, CEng, MIStructE,
FCIArb
John Riley (Member, Joint Contracts Tribunal)
Leslie Rothwell LLM, MSc, FCIArb, MICE,
MIStruct, MCIOB
Simon Tolson, Partner, (Fenwick Elliot)
Professor Ian Duncan Wallace QC, MA
(Oxon)
John Wasilewski BSc, CEng, MICE, (Harris &
Sutherland)
.1
Editorial
To Bring
Justice
Within the
Reach of All
Men 1
quick to recognise the distinction between
party autonomy and the freedom of the parties
to present the case as they saw fit in England
and the practices of the continental civil law
system where the courts do not respect the
principle of party autonomy. He also placed
high value on the orality principle. He saw the
English judge as commanding respect because
of his passive and strictly neutral position. He
respected the lawyer’s role of representing his
client and the lawyer’s freedom to present it as
he saw fit. It was his experience that litigants
preferred their lawyers to deal with the case
rather than the judge; people would only
litigate as the very last resort.
To mark the end of the century it is fitting to
pay tribute to those who are regarded as
having made an outstanding contribution to
Justice in construction and engineering law and
to the legal system itself. Possibly, a senior
member of the bar might select an eminent
member of the House of Lords such as Devlin,
Atkin or Denning. Their place in legal history
is undoubted. But for the solicitor he may be
minded to select someone at first instance.
Someone before whom he appeared and
someone who made such contribution to
procedural law and someone who unselfishly
devoted himself to the enhancement of the
Official Referee’s Court.
Sir Jack Jacob
So far as procedural law is concerned that
person would have to be Sir Jack Jacob. He
was not only an excellent practitioner and
procedural judge but also an academic. He
wrote numerous papers on the reform of civil
procedure and established an excellent course
in the subject at University College London. It
was fitting that the law school concerned was
named after Jeremy Bentham whose influence
on society and the law remains. Sir Jack
however had a particular advantage over
Bentham: he understood human nature and
advocated reform derived from practical
experience. He understood the evolution of the
law, its essential place in society and that
Justice should be accessible to any citizen, a
right derived from Magna Carta itself. In his
Hamlyn lecture on The Fabric of Civil Justice
he said:
“what is needed above all today is a breath
of fresh air to blow through the corridors
of civil justice to de-mystify this process ...
to bring Justice closer to the common
people.”
As a student of the civil justice system he was
2.
He recognised clear failings in the system
which he sought to redress: the inequality in
the resources available to the parties; and the
mystique that surrounded the system in the
mind of the citizen. He considered the
attributes of the continental civil law system
and its inquisitorial methods but did not think
they would be practical in English proceedings.
But twelve years before Lord Woolf’s Final
Report he advocated an active role for the
courts; that the courts would control the
procedure; that the courts would define the
real issues between the parties. He advocated
the exchange of witness statements and experts’
reports, and suggested that the court should
act on its own initiative in calling witnesses
and experts. He also suggested that the courts
should endeavour to promote settlement or
compromise of the proceedings.
Despite his preference for orality he foresaw
fundamental changes:
“The whole thrust of advocacy is likely to
undergo a fundamental change as written
procedures take the place of oral
procedures since orality is the lifeblood of
advocacy.”
He believed there would always be a place for
a specialist Bar. He considered as a matter of
practicality that integration of the County and
High Courts would become necessary. Such an
idea was very much in the minds of jurists
when in 1872 the Judicature Commissioners in
their Second Report suggested that the County
and High Courts should be converged into a
single Supreme Court of Judicature.2 He
favoured a code of civil procedure in order to
obtain:
“the actual, palpable and widespread
improvement of the quality of Justice,
bringing Justice within the reach and the
understanding of all and providing a simple
Construction & Engineering Law January / February 2000
speedy inexpensive accessible and effective
system for its dispensation free from
formalism and technicalities.”
From a practical point of view he suggested
many improvements in the courtroom itself.
For instance; that the judges should sit at a
lower level and Counsel be seated at tables
rather than stand in benches. He suggested
witnesses should be seated. In a paper which he
prepared for the 10th Common Law
Conference in 1980 on the Administration of
Civil Justice, he advocated the identification
and exchange of witness statements so that the
gamesmanship and forensic arts could be
avoided. It was in 1978 that he wrote “Access
to Justice in England” in which he said:
“The fundamental principle of equality for
the law becomes the equally fundamental
principle of equality of access to the law.”
And in his paper, “Justice between Man and
Man”, a title he derived from the opening
statements of Justinian’s Institutes, he
contemplated the new civil procedure rules
suggesting that there should be a Code of Civil
Procedure which should be imaginative,
creative, courageous and constructive.
John Newey
It was a privilege to often appear before Judge
Newey in the mid to late 1980s and more so to
complete my arbitration training with him by
observing the way he dealt with interlocutory
applications on Fridays. He was undoubtedly a
good judge and an excellent lawyer, above all
infinitely patient. He was devoted to his work
and his court and beyond that devoted his
energies to improving the system and
procedure of the court. Today the court is
enjoying many of the benefits he fought hard
to achieve.
In other words, John Newey clearly had, in the
opinion of leading practitioners, the particular
qualities of a first rate judge. He understood
the legal arguments and the technical facts
well, and had that essential quality of the best
judges; an understanding of human nature.
He had perhaps something more that I detected
in my many appearances before him, and that
was that he never had to assert his authority
with lawyers. He could master the proceedings
without any robust interventions. In the best
English judicial tradition he would simply
enquire in order to clarify and often make
practical time-saving and cost-saving
suggestions. It was clear in some of the
exchanges that he was ever searching for better
ways to do things. He would probably have
welcomed the Woolf reforms because they are
based on the concept of case-flow management
which his court had been pioneering in its own
way for more than a decade before. In my
experience he did not discriminate between
solicitor or barrister and always treated the
advocate with courtesy and patience. He was a
father-like figure of the court who always left a
good impression. He was very well liked not
only in the profession but outside it and was
patron of the South East Branch of the
Chartered Institute of Arbitrators. As I told
that Branch on the occasion of a tribute to him:
the name John Newey would long be
remembered for his name was already legend.
If that legend means anything to this
profession today it means that there will be
mutual respect between the judges and the
practitioners, whether they be barristers or
solicitors.
Michael P Reynolds
References
1. Epitaph of David Dudley Field cited by Sir
Jack Jacob in Civil Procedure since 1800.
2. Second Report of the Judicature
Commissioners (1872) c.631, pp. 10, 13,
14, and 19.
Construction & Engineering Law January / February 2000
Editorial
He studied law at Cambridge and graduated
First Class. For some years he was a Treasury
Junior and took silk in 1970. He was Head of
Lamb Chambers for eight years before being
appointed an Official Referee. In the tributes
that were paid to the judge at the time of his
retirement Mr Anthony Butcher QC said that
he had been devoted to “the development of
the law along liberal lines”. In his tribute to
him Mr Richard Fernyhough QC said that
Judge Newey showed “a deep instinct for
justice and for where the real merits of the case
lay”. John Bishop, the leading construction
solicitor in England, paid tribute to the way in
which Judge Newey had fought for recognition
that the court deserved and the innovative
procedures that had benefited its users. He had
also been impressed by the judge’s kindness
and dedication. Mr Norman Royce, a leading
construction arbitrator, spoke of “gifts all too
rare in the commercial world - a capacity for
warmth and understanding; an openness and
lack of self-importance”.
.3
Civil Justice Forum
Justice Is
Blind
Nemo Index In Re Sua
The maxim nemo index in re sua requires that
a man may not be a judge in his own cause.
This maxim has been at the heart of the
administration of justice for centuries to the
extent that the rule denies the Head of State the
right to sit in her own courts to administer
justice.1 The credibility of the judiciary cannot
be discussed without reference to it.
Various appeals concerning alleged bias were
heard in the Court of Appeal on 17 November
1999. The Court consisted of the Lord Chief
Justice of England, the Master of the Rolls, and
the Vice Chancellor of the Chancery Division.
They had five different but consolidated
applications for permission to appeal on
grounds of bias. The applications were listed
together because they raised common questions
concerning disqualification of judges on
grounds of bias. Such appeals are very rare but
are of considerable public concern and interest.
Such matters go back to the Magna Carta
itself, to the fundamental freedoms and rights
of the citizen and fundamental aspects of
human rights. It is a matter that has concerned
many judges including Lords Denning,
Diplock, Cooke CJ, Blackburn and Mansfield,
as well as the writings of Hobbes. It is a subject
therefore striking at the heart of the law and
the constitution.
The Lord Chief Justice, Master of the Rolls
and Vice Chancellor, have reiterated this
fundamental principle not only for Judges of
the Civil and Criminal Courts but also for all
those who act in a judicial capacity, lay justices
and jurors. Any such person who allows any
judicial decision to be influenced by partiality
or prejudice violates one of the most
fundamental principles underlying the
administration of justice. Where such prejudice
or partiality is shown the litigant will have
irresistible grounds for objecting to the trial by
that judge (if objection is made before the
hearing) or for applying for judgment to be set
aside. Proving actual bias is very difficult.
On proof of requisite facts, the existence of
bias is effectively presumed and gives rise to
automatic disqualification, e.g. where a judge
is shown to have an interest in the outcome of
4.
a case. Their Lordships referred to the leading
case where a judge is shown to have an interest
in the outcome of the matter which he has to
decide or has decided. In Dimes v Grand
Junction Canal (1852) 3 HL Cas 759, an
action was brought in the Court of Chancery
by a public company in a matter affecting the
interests of the company. The case was tried by
the Vice Chancellor of the Court and on appeal
by the Lord Chancellor who affirmed that
decision in the company’s favour. Unknown to
the defendant the Lord Chancellor owned 90odd shares in the canal company. Dimes issued
further proceedings and the House of Lords set
aside Lord Cottenham’s Decree on the basis
that the Lord Chancellor was disqualified on
the grounds of interest and not according to
law. Lord Campbell giving judgment said that
that would be a lesson for all inferior tribunals
to take care not only that in their decrees they
are not influenced by personal interest, but to
avoid the appearance of labouring under such
influence.2 The rule has been expressed
differently over the years. In R v Rand (1866)
LRI QB 230 Blackburn J said:
“There is no doubt that any direct
pecuniary interest, however small, is
subject to enquiry, and does disqualify a
person acting as a judge in the matter.”
In R v Camborne Justices ex parte Pearce
[1955] 1 QB 41 Slade J said:
“It is, of course, clear that any direct
pecuniary or proprietary interest in the
subject matter of a proceeding, however
small, operates as an automatic
disqualification.”
Their lordships said:
“The basic rule is not in doubt. Nor is the
rationale of the rule; that if a judge has a
personal interest in the outcome of an issue
which he is to resolve, he is improperly
acting as judge in his own cause; and that
such a proceeding would, without more,
undermine public confidence in the
integrity of the administration of justice.
Dimes v Grand Junction Canal (1852) 3
HL Cas 759 at 793 and R v Gough [1993]
AC 646 at 661 per Lord Goff of Chieveley.
The automatic disqualification factor was
expressed by Winneke P in the Victoria
Court of Appeal in Clenae Pty Limited and
others versus Australia and New Zealand
Banking Group Limited [1999] VSCA 35
(Supreme Court of Victoria) where he said
that it was not the mere shareholding held
by a judicial officer which constituted the
disqualifying pecuniary interest, ‘but rather
Construction & Engineering Law January / February 2000
regard (or have unfairly regarded) with
favour or disfavour, the case of a party to
this issue under consideration by him.”
it is the potential interest’ created by that
shareholding in the subject matter or
outcome of the litigation which is the
disqualifying factor.”
The point of public concern was expressed by
Lord Hutton at page 293 who observed that
where a Judge had a strong commitment to
some cause or belief or association with a body
or person involved in the litigation it could
shake public confidence in the administration as
much as a shareholding (which might be small)
in a public company involved in proceedings.
The test of bias has previously been expressed
in various cases: a reasonable suspicion or
apprehension of bias in Law v Chartered
Institute of Patent Agents [1919] 2 Ch 276 at
p. 290; R v Sussex Justices ex parte McCarthy
[1924] 1 KB 256 at 259; real danger or
likelihood of bias in R v Gough.3
Lord Goff in his judgment said that justice
“must manifestly be seen to be done”. Further
in his judgment Lord Goff referred to:
“the test in terms of real danger rather than
real likelihood to ensure that the Court is
thinking in terms of possibility rather than
probability bias. Accordingly having
ascertained the relevant circumstances
there was a real danger of bias on the part
of the relevant member of the tribunal in
question, in the sense that he might unfairly
The Lords Justices having considered their
authorities then went on to say:
“Provided the Court personifying the
reasonable man takes an approach which is
based on broad common sense, without
inappropriate
reliance
on
special
knowledge, the minutiae of court
procedure or other matters outside the ken
of the ordinary, the reasonably well
informed member of the public, there
should be no risk that the courts will not
ensure both that justice is done and that it
is perceived by the public to be done.”
In reviewing judicial conduct, the reviewing
court will not have regard to any statement
made by the judge concerning the impact of
knowledge on his mind or on his decision. The
burden is on the court reviewing the judge’s
conduct to assess the risk that “some
illegitimate extraneous consideration may have
influenced his mind”.
Solicitors as Judges
The solicitor who becomes a judge may have a
more difficult time than a barrister, albeit
barristers chambers, which are becoming very
large, may soon develop partnerships of their
own or merge with solicitors as economic
factors dictate in future. If the solicitor is a
partner or remains a partner after a part-time
judicial appointment he is still legally liable for
the acts of his partners. The question which
concerned the court was whether the partner
owed a duty to clients of the firm for whom he
or she personally may never have acted and of
whose affairs he or she personally may have
known nothing. The court was careful to
safeguard the integrity of the court but at the
same time recognised that the rules were not
unfairly applied against solicitors in such a
way as “to inhibit the increasingly important
contribution which solicitors are making to the
discharge of judicial function”. The court had
some concern over solicitors as part-time
judges in civil rather than criminal cases.
However, the concern can be overcome very
simply by the solicitor conducting a conflict
search in the firm. The same difficulty may face
a barrister, but the difficulty for both lies in the
existence of remote indirect associations which
may not be so readily identifiable by a search
or check. In these circumstances the judge
concerned would disclose such interest if and
when it became known to him.
Construction & Engineering Law January / February 2000
Civil Justice Forum
Their lordships also considered other recent
authority from South Africa and New Zealand
that supported a “diminimus” exception where
the potential effect on a judge’s decision is so
small as to be incapable of affecting his
decision one way or the other, but they went on
to say: “bearing in mind the rationale of the
rule, that any doubt should be resolved in
favour of disqualification”. Where the judge’s
interest was derived from a family link that
link would have to be “so close and direct as to
render the interest of that other person, for all
practical purposes, indistinguishable common
interest of the judge himself”. The automatic
disqualification does not end there. In R v Bow
Street Metropolitan Magistrates ex parte
Pinochet Ugarte (No. 2) [1999] 2 WLR 272
the House of Lords said the disqualification
extended to a limited class of non-financial
interest. Lord Browne Wilkinson, the most
senior judge in England, said that if the interest
was concerned with “the promotion of the
cause, the rationale disqualifying a judge
applies just as much as if the judge’s decision
would lead to the promotion of a cause in
which the judge is involved together with one
of the parties”.
.5
Civil Justice Forum
What the Judge Should Do
Decisions on the Case
In automatic disqualification cases the judge
should excuse himself as soon as he knows.
The judge should do this before objection is
raised or where he feels embarrassed for
hearing the case for personal reasons. If the
judge knows of or becomes aware of any
matter which arguably could be said to give
rise to a real danger of bias it is generally
desirable that disclosure should be made to the
parties in advance of the hearing.
The judge should not yield to any tenuous or
frivolous objection. On the other hand, he
should not ignore an objection of substance.
Factors Not Giving Rise to Bias
The Court of Appeal could not give an
exhaustive list of factors that would not give
rise to bias, but subject to the particular facts
and nature of the issue to be decided it could
not conceive of circumstances in which
objection could be soundly based on religion,
ethnic or national origin, gender, age, class,
education or employment, background of the
judge, extra curricular utterances (whether in
text books, lectures, speeches, articles,
interviews, reports or responses to consultation
papers); or previous instructions to work for or
against any party, solicitor or advocate
engaged in a case before him, etc.
Factors Giving Rise to Bias
However, the court considered that a real
danger of bias could exist if there were a
personal friendship or animosity between the
judge and any member of the public involved
in the case, or if the judge had pronounced on
the person’s credibility in a previous case, or if
the judge expressed extreme views in
unbalanced terms as to throw doubt on his
ability to try the issue with an objective judicial
mind, or there was other reason to judge the
objective reason of the judge.
Judges’ Duty
If before a matter has commenced, the judge is
alerted to a matter which might throw doubt
on his ability to act, the judge should enquire
into the full facts so far as ascertainable in
order to make disclosure. If the judge knows
something he should disclose it, but he cannot
disclose what he does not know.
6.
Having considered the general principles
applicable, the Court then gave its decisions in
several appeals before it:
Locabail (UK) Ltd v Bayfield Properties Ltd
& Another
Locabail (UK) Ltd & Another v Waldorf
Investment Corporation & Others
In this case Mr Lawrence Collins QC, solicitor
and deputy High Court Judge, a senior partner
and the former head of Herbert Smith’s
litigation and arbitration department,
disclosed to counsel before him in this case that
his firm at one time had attempted to get a
bankruptcy order against one of the parties.
Neither counsel took any objection on the
point. It was denied there was any conflict of
interest between Mr Collins position as a judge
and that as a partner in his firm. The Court of
Appeal considered the R v Gough test and
found that there was no real danger of bias.
The deputy judge did not know the facts that
would give rise to a conflict of interest. The
court did not consider that the discovery of a
conflict of interest which under The Law
Society rules would disqualify a solicitor from
acting for one or other of the parties to a case
necessarily bars the solicitor from hearing the
case as a deputy judge or requires a hearing
already started to be aborted or a judgment
given on the case to be set aside. Everything
depends entirely on the facts and circumstances
of the case. In this case there was no real
danger that the judge had been biased.
Timmins v Gormley
This was an appeal against a Recorder at
Liverpool County Court on the grounds of bias
or apparent bias. The Recorder concerned is a
consultant editor of Kemp and Kemp. He
wrote an article for The Lawyer on 21 June
1999 after he had given judgment in favour of
a claimant in a road traffic personal injury
case. In the article the judge had referred to
Access to Justice being likely “to remain a
dream”. The article suggested that the
adversarial system was inconsistent with the
new culture and the article continued to be
critical of the “delaying tactics” of insurers.
The court referred to another article in which
the Recorder considered the decision in Wells v
Wells [1999] 1 AC 345 to be a “wonderful
victory” for claimants generally. The two
articles generally demonstrated the Recorder’s
sympathy for personal injury claimants and
reservations about the change of culture.
Construction & Engineering Law January / February 2000
The Recorder wrote another article in the
Personal and Medical Injuries Law Letter
which according to him had lessons for
plaintiffs’ lawyers concerning the intimidatory
tactics of the defendants and suggesting that a
properly prepared and researched claim by the
plaintiffs ought to succeed.
was a former Inland Revenue employee who
had not dealt impartially with the applicant’s
claim for discrimination against the Board of
Inland Revenue. The Court considered that it
was fanciful to suggest that the Chairman’s
decision was affected in any way by his
employment with the Revenue 30 years before.
The court had to consider the weight which
would attach to such articles to see whether
they showed a real danger of bias.
R v Bristol Betting & Gaming Licensing
Committee ex parte O’Callaghan
The Lords Justices said:
“Anyone writing in an area in which he sits
judicially has to exercise reasonable care
not to express himself in terms which
indicate that he has preconceived views
which are so firmly held that it may not be
possible for him to try the case with an
open mind ... The specialist judge must
therefore be circumspect in the language he
uses and the tone in which he expresses
himself. It is always inappropriate for a
judge to use intemperate language about
subjects on which he has adjudicated or
will have to adjudicate.”
“an ill defined line beyond which the
expression by a trial judge of preconceived
views about the reliability of particular
medical witnesses could threaten the
appearance of impartial justice.”
The Court of Appeal considering the
applicable authorities had difficulty with this
case. There was in their opinion a real danger
of bias. They took a broad common sense
approach, whether a person holding the
pronounced pro-claimant anti-insurer views
expressed by the recorder in the articles might
not unconsciously have leant in favour of the
claimant and against the defendant in resolving
the factual issues between them. They
concluded, not without misgiving, that there
was on the facts, a real danger of such result.
Williams v Inspector of Taxes
In this case the Chairman of an industrial
tribunal was challenged on the basis that he
Comment
In dealing with this particular appeal the Lords
Justices gave some very interesting
pronouncements concerning the writing of
articles in legal journals, books and reports
and the giving of opinions and difficulties that
may arise. Sometimes publication can be
hazardous not only for judges but for experts
who may be cross-examined on previous
published opinions. But for judges the tradition
is as ancient as Bracton and de Glanville’s
Treatises and as modern as Goff and Jones,
Dicey & Morris and Keating. It is not
inconsistent with the holding of judicial office
or the discharge of the judicial function.
However, authors must be careful to present a
view which will not impinge upon the exercise
of the judicial function. It is therefore
sometimes difficult for judges to write and yet
it is only they who can truly give authoritative
experienced guidance e.g. Coke, Blackstone,
Construction & Engineering Law January / February 2000
Civil Justice Forum
The court went on to refer to Vakauta v Kelly
[1989] 167 Crim LR 568 in which the High
Court of Australia dealt with some intemperate
judicial remarks by the trial judge about
medical evidence in a personal injury action.
The majority of that appellate Federal Court
held that intemperate remarks would have
given the parties a reasonable apprehension of
prejudice. They considered that there was:
This case concerned the Judge in Charge of the
TCC, Mr Justice Dyson, who had dealt with an
application by the appellant for an order
extending time in which to challenge a decision
of the Bristol Betting and Gaming Licensing
Committee by way of judicial review. The
application before Mr Justice Dyson was
without merit and time was not extended.
Subsequently the appellant read an article in
the Sunday Times which stated that the judge
was a director of a property company, one of
whose tenants was the bookmaker whose
licence the appellant had wanted to revoke.
The company was a family property company
formed several years before by the judge’s
parents in which he, his mother and brother
were directors. The judge took no part in the
management of the company. At the time the
judge dealt with the case he had not known
that his family’s company had let property to
the particular tenant. The judge’s interest was
indirect and nominal. There could be no
danger of bias. No reasonable or fair-minded
person sitting in court and knowing the
relevant facts would have considered there was
a real as opposed to a fanciful danger of a fair
trial not being possible.
.7
Civil Justice Forum
8.
and Wright. It is only, it is suggested, in a tiny
minority of cases that conflicts may occur. If it
were otherwise then legal literature and the
courts themselves would be seriously impeded
with a lack of authoritative guidance as would
all students of law. The law would never
advance. Perhaps if Gaius and Justinian had
never bothered to codify the Roman law we
would never have had that particular
civilisation for so long. One therefore hopes
that whatever the outcome of the appeal in
Timmins v Gormley such experienced authors
will continue to contribute to our
understanding of the law without unnecessary
bias or prejudice. In those exceptional cases
where judges should take a lead, e.g.
constitutional matters and access to justice, it is
The Hamlyn
Lectures:
Civil Justice
This year Professor Michael Zander QC,
Emeritus Professor of Law at the London
School of Economics, University of London,
gave this series of lectures. This annual series
of lectures is shortly to be published. The
lectures derive from a scheme approved by the
Chancery Division of the High Court in
November 1948 by virtue of which a
charitable trust was set up to develop the
knowledge and understanding of comparative
jurisprudence and ethnology of European
States. It is fitting that it was Professor Zander
QC who gave this series devoted to the
important subject of civil justice. He has long
been a campaigner for civil justice reforms in
England and someone who in his academic
career has made an outstanding contribution
not only in terms of his writings but also, and
especially, in the way in which he has inspired
many of his students and members of the
profession to seek better standards of justice in
practice. These lectures have been delivered by
the most eminent in the profession and
academia, including Lord Denning, Professor
Glanville Williams, Lord Devlin, Professor C H
S Fifoot, Sir Robert Megarry, Henry Cecil, Sir
Rupert Cross, Sir Otto KahnFreund, Lord
Scarman, Sir Desmond Heap, Professor Sir
William Wade, Sir Gordon Borrie, Professor P
S Atiyah, Sir Jack Jacob, and Lord Woolf.
hoped they will continue to do so in line with
the noblest traditions of the English judiciary.
Michael P Reynolds
References
1. Professor Paul Jackson. “Natural Justice.”
Modern Legal Studies, Sweet & Maxwell
(1979) p. 27.
2. Six years after this case Lord Wensleydale
refused to hear an appeal because he had
shares in the appellant’s company. London
and North Western Railway Company v
Lindsay (1858) 3 Macq 59.
3. Op cit.
In his second lecture, given at the London
School of Economics on 23 November 1999,
Professor Zander referred to some of the
changes that have taken place recently in the
civil justice system. He noted that in the last
100 years there had been 60 reports into civil
justice and that Access to Justice, Lord Woolf’s
Report, would not be the last. He further noted
that in terms of jurisprudence there had been a
curious neglect of this subject. A reason for this
may be that of all those who have rights to
make a claim, empirical evidence suggests only
one in seven do so. He referred to Professor
Hazel Genn’s recent survey, Paths to Justice
(260pp), where there was a sample of 4000
persons and interviews with 1100.
Interestingly, 95% of those questioned had
tried to do something and deal with the
problem. Mostly they tried to take direct
action. Sometimes they got results, sometimes
they did not. One third of the disputes were
resolved by agreement, and 50% of the people
in those cases had received advice. Some
disputes were resolved by adjudication. But in
over half of the cases there was no result. This
was curious bearing in mind that one fifth of
all respondents were aware of the Citizen’s
Advice Bureau and its facilities. Nine out of ten
received advice. Professor Genn’s study
suggests that most people do something,
namely complain, but very few use the
resources of the legal system and most give up.
Professor Zander questioned whether this was
a good or a bad thing. What most people
seemed to be concerned about was time, cost
and stress.
Professor Zander considered that ADR was the
flavour of the month. However, it did not
appear from Professor Gann’s survey to be
Construction & Engineering Law January / February 2000
particularly popular with litigants because only
5% of litigants appeared to be taking to
mediation. It is questionable whether ADR can
save costs. If the parties agreed to mediate and
come to a settlement, that may well save costs;
if the parties litigate, then try and mediate, and
there is no agreement, costs are increased.
Professor Zander referred to the Rand
Corporation study in the United States, a study
of ten thousand cases which indicated that
there been no fundamental shift towards ADR
and that the pyramid structure of litigation
would remain. This was supported by the
recent study carried out by Professor Hugh
Collins.
It is proposed that the civil justice system in
England and Wales be self funding. Indeed it
has been suggested by the Lord Chancellor that
the further on in the case litigants get, the
higher the court fees. This would seem to be
contrary to the whole basis of the civil justice
system as has existed in this jurisdiction for
centuries. Professor Zander considered this to
be highly objectionable.
Under the new rules the courts may not be
consistent as between procedural judges; some
judges may take a different approach to others
as their particular interpretation of a particular
rule. How can allocation of costs be just when
the criteria for the award of costs is subjective
and wholly imprecise? Do the new rules as to
allocation of costs not create further
uncertainties and difficulty for lawyers in how
they advise their clients as to the likely
outcome of costs applications? There may also
be difficulty for the judge in getting the
allocation of costs right.
The key test for the Civil Procedure Rules
according to Professor Zander amounts to this:
do their strengths outweigh their weaknesses
when compared to the Rules of the Supreme
Court?
Editorial Comment
Professor Zander has raised many issues for
Professor Gann’s study is interesting because it
possibly suggests the limits to which Access to
Justice has gone. It means that for a high
proportion of the population access to justice
is not a reality. People do not want to make the
effort or give the time or money to get redress
for infringement of their rights in court or by
other means. That will remain the case
whatever publicity is given to whatever means
of dispute resolution. The problem was
articulated by Professor A V Dicey KC,
Vinerean Professor of Law, University of
Oxford, almost a century ago, and remains one
of understanding and education. In practice
one sometimes finds the small builder who
takes issue with a stronger commercial party
and who is quite incapable for commercial/
financial reasons of pursuing the case to a
satisfactory solution. There are two primary
reasons for this: a failure by the State to
provide the financial safety net for access to
justice and the costs indemnity rules whereby
the losing party pays the other sides costs. The
costs risk is too great despite the new
allocation of costs provisions. The costs risk is
double that in the United States where each
side pays its own costs. That may not be good
for the winner but at least there is more
certainty in the system. Secondly the almost
total withdrawal of legal aid from the poorer
classes of contractor and even from the middle
class contractors and employers who would
not be able to devote adequate resources to the
disputes process. These litigants will have more
reason to avoid litigation, arbitration and
other means of dispute resolution. In a sense
people will only go to litigation if they have to
and when all else has failed. But then that is
how it should be; the difference here in
England is that the State appears to be asking
a high price.
It is trite law that parties freely entering into a
contract are bound by the obligations they give
to one another so that if they agree to resolve
their disputes in a certain manner the law
recognizes their right to do so and will not
force them to use courts. These days lawyers
advise on a wide range of disputes procedures.
Indeed many lawyers promote particular forms
of disputes procedures fearing perhaps that the
traditional work of lawyers in the courts will
be less and that there is more work to be had
in ADR. The problem is, as Professor Zander
rightly identifies, that this is “the flavour of the
month”. Lawyers must be careful in advising
Construction & Engineering Law January / February 2000
Civil Justice Forum
The new Rules had been in operation for
several months and the feeling generally was
“so far so good”. However, Professor Zander
had concerns about increased costs through
observance of pre-action protocols and the
unnecessary effect of front-end loading of cases
to comply with the protocols. How can this be
justified in the sense that cases might otherwise
settle without such preliminary work? It maybe
that parties will spend more than they did
formerly before they are able to settle.
debate affecting civil justice as a whole. In so
far as his comments may have implications to
practitioners in this field it is right that they be
carefully considered at a practical and
economic level.
.9
Civil Justice Forum
10.
on alternative means of dispute resolution
because of the risk of error; for example failure
to learn of the relevant facts; incorrect
weighing of facts; lack of expertise; scarcity of
time and lack of thoroughness in
investigation.1
The penalisation of litigants with higher court
fees the further they go in the process would
seem to inhibit justice rather than provide
access to it. The strict adherence to timetables
and robustness of judges may be considered
essential in attempting to curb procedural
delay and to prevent others in having to wait
too long to get a hearing. Nevertheless, the
question of fairness and balance must be
considered along with practical experience.
A procedural judge can be fair as well as being
robust and keep to a timetable. As Professor
Adjudication
and Inquisition:
Inquisito Cum
Promovente
Revisited
Zander said, he can do that by regarding Rules
as guidelines and not trip-wires.
Michael P Reynolds
The Editor would like to thank Professor
Michael Zander, Professor of Law, London
School of Economics, for his kind permission
to use the material quoted. The full series of his
lectures is expected to be published by Sweet &
Maxwell in March.
References
1. All these were identified as early as 1979 by
Professor Earl Johnson Jr, Professor of Law,
University of California, in his contribution
to Volume III of Access to Justice:
Emerging Issues and Perspectives Typology of Possible Strategies.
the witness statements were treated as
testimony, the English judge treated such
evidence as mere accusation. Having made his
enquiries the judge then proceeded to hear the
evidence and give judgment. The essential
saving feature of English practice was that the
judge actually saw and heard the witnesses
(jurors) give their evidence and was able to
form a view as to the credibility of a witness
and evaluate the weight of that evidence.
Section 108(2)(f) of the Housing Grants
Construction and Regeneration Act 1996
provides that the adjudicator can take the
initiative in ascertaining the facts and the law.
It appears he can adopt an inquisitorial
approach. Inquisitorial procedure is not
unknown under English law, but those who
framed the legislation were probably unaware
of the trials and tribulations of its evolution in
England.
It should be noted that such an exceptional
process was applicable in the criminal and
heretical cases where there were different
burdens of proof for crime committed by
“thought”. Such extremes of torture as were
practised in other jurisdictions implementing
the inquisition were not known in the practice
of English law. On the civil side certain
inquisitorial methods were featured in the
system but they were balanced so that a
defendant had a fair chance to put his case.
It is well to remember that inquisition,
according to Pollock and Maitland,1 was
introduced to English law by Pope Innocent III.
The judge proceeded ex officio of his own a
motion or at the suggestion of the claimant
(inquisito cum promovente). He collected
witness statements which were not shown to
the defendant and of which the defendant had
no notice. The process was secret with
appalling consequences for the defendant. The
Papal Decree was interpreted more
pragmatically in England by the Judges and
modified by King Henry II. In practice the
English judge was fairer than his continental
counterpart because, whereas on the continent
The history and practice of the English legal
system has been based on the idea of fair trial
since Magna Carta and before. English lawyers
may therefore have historical reasons to be
concerned about the practices of adjudicators
who may think they know what ‘inquisitorial’
may mean but are ignorant of the context in
which English law has dealt with it. Whilst
such practices undoubtedly got a bad name in
the excessive practices of the civil law in
continental systems, equity seems to have
prevailed in England in its subsequent
adoption in the Chancery Courts. What
adjudicators in this jurisdiction will have to
watch is the application of the Human Rights
Construction & Engineering Law January / February 2000
Act 1998 which in many ways reflects
traditional English principles of fairness. The
recent warning given by Judge Anthony
Thornton QC2 in his lecture to the Society of
Construction Law should be noted by all
engaged in adjudication.
Under Article 6 of the Act an applicant is
entitled to access to a court that is both
realistic and effective, to a fair public hearing
at a reasonable time, to a fair public hearing
that embodies both equality of arms and a
reasoned decision. According to Judge
Thornton the position may be tricky because
the adjudicator may be fulfilling a function of
a public nature or may be acting in the nature
of an administrative decision-maker. The
parties must therefore be provided with
convention rights and failure to do so may
render the process in breach of the convention.
Breaches of the convention might arise in
failure to follow the Housing Grants
No Bond On
the Dome
Koch Hightex GMBH v New
Millennium Experience Co Ltd
Facts
The contractor claimants appealed from an
order of Mr Justice Lindsay who struck out the
claim for monies due under the contract for the
construction of the roof of the Millennium
Dome. The claimants failed because the
defendant was held not to be under any
liability because of the claimants’ failure to
provide forms of bond and guarantee required
under the contract. The contract expressly
provided that the provision of the documents
was a condition precedent to any liability on
the part of the defendant. The claimants
admitted that their remedy was not barred by
reliance on the facts. They submitted that they
In the historical context one can anticipate
why an English court would not be too
sympathetic to an over-zealous inquisitorialstyle process.
Michael P Reynolds
References
1. Source: History of English Law, Pollock
and Maitland, Vol II, p. 657, Cambridge
University Press, 1923.
2. The Human Rights Act and Construction
Disputes, HHJ A Thornton QC, Lecture to
Society of Construction Law, 5 October
1999.
had tendered for work on the dome roof. They
had received a Letter of Intent which was to
precede the building contract.
The contractors started to build the Dome
roof. They entered into the contract which
contained a provision for the bond and
guarantee and purported to make such
provision a condition precedent to any liability
on the part of the employer. Another condition
gave the employer the right to determine
without cause upon payment of compensation.
Shortly afterwards the employer changed its
mind and decided to use another material for
the roof. The claimants were in the process of
doing the work and preparing the documents.
The
claimants
thereupon
claimed
compensation in the sum of £2.2 million. The
defendant rejected this claim on the basis that
the claimants had failed to fulfil the obligation
to provide the bond and guarantee. The
defendant applied to strike out the claim whilst
the claimants cross-appealed for an interim
declaration under Rule 25.1(1)(b) of the CPR,
as to whether the claim was barred by the
condition precedent. Mr Justice Lindsay
dismissed the claimants’ application and struck
out the claims.
The Court of Appeal decided that the
defendants case was misconceived. The Court
considered the real issue here was not the
matter of the clause creating a contingent
condition precedent or a promissory condition
but the more fundamental question on the
Construction & Engineering Law January / February 2000
Case Update
In this case the Court of Appeal (Civil
Division) held that the failure of a claimant
contractor to provide a performance bond and
guarantee could not be relied upon where the
building contract had been determined for
reasons other than failure to provide the bond
or guarantee.
Construction and Regeneration Act itself, the
use or abuse of power under the statutory
scheme, and from the way the adjudicator
conducts the process itself.
.11
Case Update
facts of the case as to whether the parties had
intended the provision of the documents was
so fundamental that the result of failure to
provide them would be that the contractor
would lose its right to payment under the
contract and under the letter of intent. To the
Court of Appeal this represented ‘commercial
nonsense’ because on a true construction of the
contract the parties could not have intended
Gone With
the Wind
Michael P Reynolds
The case was appealed because an agent of the
MOD gave an instruction within a condition
7(1)(a) GC/Works 1 (Ed 2) as to a variation
modification or substitution of work under the
contract. D&D also appealed on the grounds
that MOD had waived their rights.
Remedial Work
Scott Wilson Kirkpatrick &
Partners v Dean and Dyball
Construction Ltd & the Ministry
of Defence
In Scott Wilson Kirkpatrick & Partners v Dean
and Dyball Construction Ltd & the Ministry
of Defence, CA, 30 November 1999, the
defendants were not liable in respect of the
repair for works done to a higher standard
than their contractual obligations required.
Facts
In 1993 the roof of No. 1 slip dockyard in
Plymouth was blown off in a wind gust. Both
the consulting engineers Scott Wilson
Kirkpatrick Partners (SWK) and Dean and
Dyball Construction Limited (D&D) were held
to be jointly liable for damages for loss by Mr
Recorder Bruce Coles QC. D&D appealed on
issues of liability, quantum and apportionment
of blame. It was required to show the Court
that the contractual obligations were varied or
that the MOD precluded itself from insisting
on these obligations or from alleging breach.
The judge held that D&D were in breach of
Condition 13 (4) GC/Works 1 requiring D&D
to execute the works “in a workmanlike
manner” and for breach of an obligation
contained in notes to a drawing by way of an
instruction to “ensure boarding rafters purlins
and other materials” were well fixed as
existing. The Court found that the roof came
off because of inadequate fixings and that the
contractors, who could have used nine-inch cut
nails, had used only four-inch long galvanized
nails which insecurely fastened the roof so that
it became detached under wind pressure.
12.
that the contract should have that effect. They
also said that in terminating the contract for
reasons other than failure to provide
documents the defendant had waived the
claimants’ failure in that regard and triggered
the contractual obligation to make
compensation payment.
When the roof was rebuilt the purlins were
affixed to the main frame rafters using straps,
saddles and bolts in addition to nails. The
defendants argued that these materials were
betterment and added an extra cost of
£27,285.28. The judge held that MOD acted
reasonably and awarded damages for that sum
against D&D.
The Court of Appeal considered the judge’s
findings and his award of damages. In the
court’s opinion the judge in the first instance
came to the right decision on condition 7(1)
and concluded that the contractors should
have executed the works in a workmanlike
manner ensuring the boarding, rafters, purlins
and other materials were as well fixed as the
existing ones. The court did not find there was
ever any instruction to vary or modify.
So far as the agent was concerned the agent’s
words and conduct did not constitute any
representation. There was no waiver or
estoppel by the MOD. The Court said that
conduct confirming or encouraging another
party to think that what would otherwise be a
breach would not be treated as such, could be
expected to have a greater clarity than was
present in this case. The Court on this point
distinguished Investment & Property Co Ltd v
Texas Commerce International Bank Ltd
[1982] 1 QB 84.
The Court found difficulty in relying upon the
agent’s supervision to inspect and discover
defects in the fixing members. The contractors
had not demonstrated how any or all written
representations by the agent and any reliance
thereon by the contractor could make the
Construction & Engineering Law January / February 2000
MOD insistence on performance of D&D’s
contractual responsibilities inequitable. The
estoppel was also rejected. The Court
considered that the judge of first instance was
in error in considering whether MOD had
acted reasonably in undertaking remedial
works in 1993. There was no reason for this
work to be upgraded at the contractors’
expense. D&D’s cross-appeal on quantum of
damages was allowed. Finally the Court
upheld the finding of Mr Recorder Coles on
the apportionment of 50/50 responsibility for
each party.
Comment
Holding Out
work for a development. The partnership
comprised of D1 and D2. D1 alleged he was a
sole trader and that D2 was his subcontractor.
The evidence included a letter heading of the
firm’s notepaper showing D1, D2, and H, with
whom the claimants had reached a settlement
discontinuing proceedings. Wendover submitted
that both D1 and D2 had held out D2 as being
part of the firm, under s 14 Partnership Act
1890, or at common law. D1 alleged the
contract was not made with Wendover but
with the second claimants. Upon hearing the
evidence on the preliminary issue the Court
was satisfied that there was an Appointment
dated 9 February 1996 between RFP and
Wendover. The evidence of the letter heading
left little doubt that RFP were holding out D2
as a partner. Wendover had no knowledge of
D1’s sole trader status and thus were entitled to
rely upon the holding out. In addition the court
considered there was sufficient evidence of
equitable estoppel.
Wendover Developments Ltd
and London and Newcastle
(Holdings) PLC v John Asquith
Fish and TCM Fidler
Judge Anthony Thornton QC gave judgment in
this action on 23 November 1999. The case
concerned the issues as to when and between
whom a contract for structural engineering
services had been made and whether the
second defendant had been held out as a
partner of the first defendant so as to be jointly
liable in negligence.
Wendover alleged that RFP (Robert Fish &
Partners) had been engaged under the terms for
an appointment to provide all relevant
structural engineering design and supervision
Dick Lucien Chitolie v H M C & E
Clearly in this case the builder was bound as at
the date of the contract by the current code of
practice and not by any subsequent codes.
Michael Reynolds
Michael P Reynolds
was entitled to an assessment of his costs based
on provable lost earnings, or two-thirds of the
fees that a lawyer would have charged,
whichever was the lower, and £9.25 per hour
for work carried out. The appellant’s costs in
this matter were assessed at £160 on 17 hours
work at £9.25 per hour.
Rule 48.6 and Practice Direction 48 of the
CPR were applied (Costs: Special Cases).
In Dick Lucien Chitolie v H M C & E the
Court of Appeal held that a litigant in person
Construction & Engineering Law January / February 2000
Michael P Reynolds
Case Update
Litigant in
Person’s
Costs
This case raises interesting questions of a
technical and legal nature. First, as to the
proper method of repair and remedial
standards and next as to responsibility to
comply with Codes of Practice.
.13
Construction Adjudication
Adjudication:
Is There a
Flaw in the
Logic?
In previous columns in this journal we have
looked at the steadily developing law that is
being handed down, mainly by the Technology
and Construction Court, in the field of
adjudication. This applies particularly in
relation to the question of enforcement and
recent jurisdictional points which have been
taken by parties to try and prevent a decision
perceived to be bad from seeing the light of
day. By and large some pretty major markers
have been set down to the effect that the courts
will largely uphold the process of adjudication,
in the spirit intended by parliament, save where
there might be a palpable lack of jurisdiction.1
Until very recently, there was little or no
reported authority on the courts’ attitude to
adjudicators’ decisions which are flawed not
on grounds of jurisdiction but on technical
inaccuracy. In other words getting the number
work wrong. As many readers will know,
unlike arbitration, where there is a slip rule
under section 57 of the Arbitration Act 1996
there is nothing comparable in adjudication. At
least not unless it is expressly provided for in
the contract or rules governing the
adjudication regime.
Parliament fully anticipated that because of the
nature of adjudication, which subject to certain
exceptions requires the adjudicator to reach his
decision within 28 days, the result of this might
lead on occasion to mistakes. That is why by s
108(4) an adjudicator is not liable for making
an error including getting his maths wrong
unless this is the result of some act of bad faith.
This immunity also extends to his employees
or agents, usually consultants the adjudicator
may have turned to in helping him ascertain
the facts and the law.
In the case of Bouygues UK Limited v DahlJensen UK Limited, Mr Justice Dyson had to
grapple with this very issue. The adjudication
was run under the CIC procedure with a
solicitors adjudicator appointed. The facts
briefly were these. Bouygues were the Main
Contractor for a project at Cornwall House,
Kings College in London, and Dahl-Jensen
were appointed as M & E domestic
subcontractors to Bouygues. Whilst the
contract was entered into before 1 May 1998
14.
condition 22 of the subcontract provided for
dispute resolution by adjudication in the form
contemplated for by the Housing Grants
Construction and Regeneration Act. The work
started in April 1998 but on July 8 things had
gone so badly that Bouygues purported to
determine the employment of Dahl-Jensen who
then promptly issued a notice to adjudicate
seeking inter alia £5,000,000 for claims arising
out of breaches of contract and/or additional
works plus a further £225,000 for wrongful
determination of the subcontract.
As is so often the case in this type of situation,
Bouygues then issued its own notice of
adjudication seeking repayment of sums
allegedly overpaid, together with liquidated
damages for delay to completion which it had
suffered as a result of the determination.
Bouygues’ claim was agreed to be treated as a
counterclaim in Dahl-Jensen’s adjudication.
Bouygues’ own counterclaim totalled a little
more than £5 million.
The adjudicator appointed a cost consultant
from a leading practice to assist him in matters
of quantum. No oral hearing ensued and the
decision of the adjudicator was reached on
document-only submissions. The adjudicator’s
decision was published on 5 October 1999. In
his decision he found for Dahl-Jensen. He
concluded that the subcontractor was entitled
to payment for additional work and for
damages for various breaches of contract prior
to the determination.
However in relation to the validity of the
determination, he found that Bouygues were
entitled to liquidated damages, and costs
relating to remedial works as well as damages
in relation to extra costs for completing the
subcontract operations.
The net result of the adjudicator’s findings was
a positive sum to Dahl-Jensen for £207,741.46.
There was however a rather major gaffe in the
numberwork. This arose from an error which
Mr Justice Dyson regarded as explicable. The
error arose from lack of consistency in dealing
with the netting off of retention monies. Had
the computational analysis been carried out
properly then instead of Dahl-Jensen being
awarded just over £200,000 the effect would
have been a net award of £141,254 to
Bouygues. In other words the error had
effectively worked an injustice to the tune of
£350,000.
Bouygues was quick to spot the error and
through their solicitors, Masons, invited him to
correct the “slip”. Predictably, Hammond
Suddards, for Dahl-Jensen, contended that the
Construction & Engineering Law January / February 2000
adjudicator was not functus officio and had no
jurisdiction to revisit his award. The
adjudicator responded to these arguments in a
letter to the parties in which he pointed out
that he had indeed reserved the right to rectify
any slip as if it were an award published
pursuant to s 57 of the Arbitration Act 1996.
In the circumstances quite a clever thing to do,
particularly in complex and detailed disputes.
Be that as it may, the adjudicator concluded
that his decision did not contain a clerical
mistake or error arising from an accidental slip
or omission.
Perhaps most worrying for some was what Mr
Justice Dyson made of all this. He concluded
that by simply making a mistake in the
ascertainment of the sum which was due, the
adjudicator had not exceeded his jurisdiction.
He came to this conclusion notwithstanding
Bouygues’
argument
that
in
these
circumstances such a decision might bring
adjudication into disrepute. Mr Justice Dyson
roundly disagreed. In a judgment in which he
referred to a number of earlier decisions2 he
noted that the purpose of the statutory scheme3
was to provide an expeditious machinery for
the settling of disputes in construction
Jurisdiction
and the
Adjudicator and Then
There Were
Three
This article considers three very recent cases
which have emphasised the important
constraints that jurisdictional issues impose
upon adjudication.
With some alacrity he concluded:
“It is inherent in the Scheme that injustices
will occur because, from time to time,
adjudicators will make mistakes.”
In other words he came to some sort of greater
good argument that whilst there will be
occasions, generally rare ones, where
adjudicators get it wrong, that does not mean
that the courts will necessarily interfere. Purists
may be unhappy with this concept but it does
represent sound common and commercial
sense. Perhaps the most unfortunate practical
aspect from this case comes from the fact that
Dahl-Jensen then went into liquidation in
circumstances where it had a lot of money it
should not have been entitled to. It is
understood leave is being pursued to appeal.
Simon J A Tolson
Partner, Fenwick Elliott Solicitors
References
1. The Project Consultancy Group v The
Trustees of Gray Trust.
2. Macob Civil Engineering Limited v
Morrison Construction Limited [1999]
BLR 93; The Project Consultancy Group v
Trustees of the Gray Trust (unreported);
Palmers v ABB Power Construction
Limited (unreported).
3. Scheme for Construction Contracts
(England and Wales) Regulations 1998.
Introduction
As most readers will know, Part II of the
Housing Grant, Construction & Regeneration
Act 1996 (“the Act”) which came into force on
1 May 1998 introduced adjudication and
payment provisions.
These provisions cannot be contracted out of
despite the attempts of a number of contractors
to do so, as reported recently by the
Constructors’ Liaison Group, and so as a body
of legislation and extra statutory provisions,
they represent a fundamental development in
the rights of the parties unique to the
construction industry.
Some aspects of adjudication remain uncertain
Construction & Engineering Law January / February 2000
Construction Adjudication
Dahl-Jensen then applied for summary
judgment under the new CPR Part 24 based on
the adjudicator’s decision. Bouygues defended
those proceedings on the basis that the
adjudicator had made a mistake which was so
radical as to award the whole of the retention
sum to Dahl-Jensen when it was neither due
nor claimable. It was on this basis that it
contended that the adjudicator has exceeded
his jurisdiction and that accordingly the
decision should not be enforced.
contracts on what he termed a “provisional
interim basis”.
.15
Construction Adjudication
and in this article we concentrate on three
decisions concerning jurisdiction.
The Jurisdiction Question
The Act sets the basic framework for the
jurisdiction, powers, and duties of the
adjudicator. There is no precise definition in
the Act of adjudication or adjudicator. The
right given under s 108(i) to refer disputes
under the contract to adjudication serves to
formalise the jurisdictional parameters but
significantly, this only deals with disputes
arising under the contract,1 not disputes that
do not concern obligations created by or
incorporated into the contract, such as tortious
claims for example, which fall outside the Act.
Only parties to a “construction contract” as
defined in ss 104 to 107 (but limited by the
Exclusion Order) may refer disputes to
adjudication.
Contracts may make express provision for
adjudication to go beyond the minima in the
Act. They will usually do so by the
incorporation of specific rules such as those
produced by TeCSA.2
The usual legal analysis for determining
jurisdiction applies the key test - what does the
contract say? If the contractual provisions
comply with the eight minimum criteria of the
Act the contract will be deemed compliant and
the Scheme3 will not apply. If a contract
furnishes the adjudicator with powers and
duties which go beyond the Act and is
otherwise compliant, then the adjudicator will
have the benefit of a greater field of operation,
ergo his decision will be prima facie
enforceable.
The wider powers provided by a construction
contract cannot be pared back to the statutory
minimum without a variation agreement or
deed.
One of the statutory exclusions to the right to
adjudicate arises where the works concern
residential occupiers and their dwellinghouses.
Certain standard forms get round that
situation by incorporating an adjudication
clause that binds the employer whatever his
status, for example the JCT Agreement for
Minor Works 1998 Edition.
Note that under s 107, the Act only applies to
agreements that are in writing. This definition
was lifted from provisions within the
Arbitration Act 1996 which were drafted to
16.
circumvent frequently litigated arguments4 over
whether or not an arbitration clause was
effectively incorporated into a contract.
Section 107 restricts the instances in which it
might be arguable that the contract was not
reduced to writing.
Against this backdrop there have been three
important decisions handed down by the
Technology and Construction Court since June
1999.
The first case considered is A&D Maintenance
and Construction Limited v Pagelhurst
Construction Services Limited.5 The case
concerned an application for summary
judgment under the new Rule 24 to enforce the
decision of an adjudicator. The claimant subcontractor had been appointed by the
defendant main contractor to install a boiler
and flue as part of a school refurbishment. A
fire ensued causing serious damage to the
school, and the defendant, simultaneously
pursuing a substantial claim in separate
proceedings against the claimant, contended
that the cause of the fire was incomplete and
defective work by the claimant. The claimant
asserted its work had been properly carried out
and that substantial invoices were due and
owing. Because of the fire the employer had
determined the main contract. On the same
day the defendant received notice of
determination, he served a similar notice on the
claimant and gave notice of intention to
withhold further payments. The claimant
commenced adjudication in respect of
outstanding
invoices.
The
defendant
threatened to apply to court to prevent the
adjudication from proceeding on the basis that
there were complex claims which were the
subject of separate proceedings. However the
main contractor fully participated in the
adjudication. The adjudicator found in the
favour of the claimant for just over £100,000
including fees and interest. The claimant then
claimed summary judgment, which was
opposed by the defendant on the grounds that:
“The sub-contract was not a construction
contract for the purposes of the Act, the
sub-contract had come to an end on 19
November 1998, and therefore it was too
late to issue a notice to refer to
adjudication; and, the existence of the
substantial claims made by the defendant
against the claimant in the other
proceedings amounted to sufficient
grounds under CPR Part 24.2(b) to require
that the case be disposed of at a trial.”
Judge Wilcox held that the sub-contract was
Construction & Engineering Law January / February 2000
the scope and level of the fees remained to be
agreed. Following a dispute over fees the
claimant served a Notice of Adjudication in
early 1999. The defendants alleged that the
contract was being made before the
implementation of the Act and was not subject
to the adjudication provisions. They
nevertheless took part in the adjudication but
at all times reserved their position on the
jurisdiction issue. The adjudicator duly decided
that a contract had been made which post
dated the implementation of the Act. The
defendants refused to pay; alleging that the
decision was made without jurisdiction and, as
an alternative ground, that they had never
entered into a binding contract. The claimant
brought proceedings for summary judgment,
relying on the decision in Macob Civil
Engineering v Morrison Construction Limited
(1999) TLR, 11 March 1999, and the later
decision in Outwing Construction v H Randell
& Son Limited (1999) 64 Con LR 59.
Judge
Wilcox
emphasised
that
the
adjudicator’s powers were very wide and that
the matters complained of by the defendant
were clearly within his competence. He ruled
that the claimant had discharged the burden of
showing that the defendant had no real
prospect of defending the claim in accordance
with the new test under Rule 24 (rather than
the old test of whether there was an arguable
defence).
Giving judgment, Judge Dyson said that in
enforcement proceedings the defendants could
challenge the decision of the adjudicator on
grounds of deficient jurisdiction. He concluded
that on the facts, the defendants had never
submitted to the jurisdiction of the adjudicator
and were not bound to accept his decision. He
found that there was no contract, nor clear
evidence that one had been concluded. If there
was no contract there could be no adjudication
and consequently no summary judgement.
Judge Wilcox also ruled that had the defendant
immediately challenged the adjudication as
threatened, or sought an immediate ruling by
the adjudicator as to his jurisdiction then the
outcome may have been very different. He
went on to indicate the circumstances when a
court might refuse enforcement of an
adjudicator’s decision where there are
irregularities in the adjudicator’s appointment.
In The Project Consultancy Group v the
Trustees of Gray Trust 6 the issue also centred
on jurisdiction following an application for
summary judgment under Part 24. The
claimant was engaged by the defendants to
provide consultancy services to planning
permission stage for the conversion of a
nursing home. After planning permission was
granted and the claimant paid, the parties
discussed a further contract to provide services
during construction, but nothing was
specifically agreed. In June 1998 the claimant
sent draft fee proposals to the defendants
which resulted in a further meeting.
In a subsequent letter the defendants in
principle agreed the claimant’s proposals but
Hence, any jurisdictional challenge ought to be
made at the outset and that position reserved
during any participation in the adjudication.
The third case germane to the issue of
jurisdiction is Palmers Limited v ABB Power
Construction Limited.7
The claimant was the sub-sub-sub-contractor
on a scaffolding contract but contracted
directly with the defendant for specific works.
The defendant blamed the claimant for delays
and served notice under s 111 of the Act of its
intention to withhold payment.
The claimant contended that it was entitled to
suspend operations under s 112 and that the s
111 notices were invalid and commenced
adjudication over outstanding interim
payments. The defendant alleged that there
was neither a “construction operation” nor a
construction contract as defined under s 105 of
the Act. Thus, there was no right to
adjudication and any adjudicator purportedly
appointed would have no jurisdiction. In his
judgment, Judge Thornton confirmed that it
Construction & Engineering Law January / February 2000
Construction Adjudication
evidenced in writing by a sub-contract order
and written submissions, which had been
exchanged in the separate proceedings, and
therefore constituted a construction contract
within the meaning of s 104 of the Act. As the
sub-contract did not provide any express
provision for adjudication, the Scheme was
held to apply. Thus the reference to
adjudication was valid and effective. The fact
that the sub-contract was determined did not
prevent the dispute being one which arose
under the contract and did not affect the right
of the claimant to issue notice of adjudication.
Judge Wilcox said that had parliament
intended to impose a time limit on the exercise
of rights to refer to adjudication, it would have
to have been clear. A better view seems to be
that one can pursue an adjudication at any
time subject to any evidential bars that might
be contained within a contract. Thus the
decision of the adjudicator was valid and
effective.
.17
Book Reviews
was appropriate for the court to declare
whether the adjudicator had jurisdiction where
the adjudicator had no inherent powers to
resolve disputes about his own jurisdiction. In
interpreting the Act Judge Thornton followed
judicial approval 8 of the admissibility of
parliamentary material, holding that the
scaffolding operations in question did
constitute construction operations. He further
stated that it was not appropriate to determine
the validity of a s 112 notice to suspend where
the serving party also sought adjudication.
Finally he held that the s 111 notice was
invalid if it did not specify the amount to be
withheld. Accordingly the claimant obtained a
declaration that its interim payments were due
and payable, but in the absence of a monetary
claim, no money.
Simon J A Tolson
Partner, Fenwick Elliott
1. Fillite (Runcorn) Limited v Aqua Lift
Limited (1989) 47 BLR 27.
2. Now version 1.3.
3. Scheme for Construction Contracts
(England and Wales) Regulations 1998.
4. Aughton Ltd v M F Kent Ltd (1992) 57
BLR et al. See s 5 Arbitration Act l996.
In conclusion, whilst earlier decisions such as
Macob, Outwing and the Rentokil decision in
Scotland have confirmed the courts’ support
for adjudication, it now seems that the courts
will be prepared to consider the substantive
merits of adjudicators’ decisions on
jurisdictional grounds and refuse enforcement
if appropriate.
5. A decision of His Honour Judge David
Wilcox delivered on 23 June 1999.
These three cases are likely to encourage
further litigation. Adjudicators will also need
8. Pepper (HMIT) v Hart (1992) 3 WLR
1032.
Book
Reviews
made, how rights may be determined and
terms interpreted. I particularly liked the way
the authors dealt with the parties to a
construction contract and their particular
status and the various standard forms. Part B
of the text illustrates this in dealing with the
employer, contractor, sub-contractor, engineer
and architect under contract title headings: ICE
6th, JCT 98, CECA Blue Form, DOM/1, and
DOM/2. Part C deals with non-performance
and breach of obligation by employer, contract
administrator, contractor. This part needs to be
revised to include more comprehensive
coverage of an important area. In particular it
fails to deal with the role of the architect and
the engineer. No doubt this, as with other parts
of the text, will be gradually expanded. Part E
contains a general guide to dispute resolution
and the new CPR. I was not sure what the
authors really intended by the inclusion of such
general descriptions of the various alternative
procedures now open to disputants. If it is
simply to inform the reader of the differences
between the various processes then it would be
useful if it could contain all the relevant rules
of adjudication, arbitration and litigation,
Guide to Construction Contracts
by Delves, Lewis, Fleet and
Tadiello; Butterworth/Tolley,
1999
This loose-leaf guide is broken down into five
key sections: Formation and Construction,
Parties’ Rights and Obligations, Nonperformance, Planning for Contingencies and
Dispute Resolution. The text is readable and
easy to follow. There are no disjointed
references to numerous authorities that can
confuse, but instead reference to the leading
case on that particular part of the text with
citations in the appendices. The style is modern
and clearly-focused on recurring practice
problems: what the contract is and how it is
18.
to be cautious about jurisdictional issues which
go to the root of their appointment and
entitlement to payment.
6. The Honourable Mr Justice Dyson handed
down on 16 July 1999.
7. His Honour Judge Anthony Thornton QC
delivered 6 August 1999.
Construction & Engineering Law January / February 2000
including practice directions and pre-action
protocols, analysing such differences;
advantages and disadvantages.
The difficulty for the authors is the same
difficulty that has confronted every author of a
construction law textbook since the days of
Alfred Hudson. Namely, dealing with the
rights, obligations and remedies of the parties
at Common Law and under Statute. These
authors have succeeded in providing a simple
logical structure upon which to build their
guide. What is lacking on the Construction
lawyer’s bookshelf is a more scientific analysis
of this complex subject, which deals with each
standard form in depth as a guide to both
draftsman and advocate.
Michael P Reynolds
Solicitors Duties and Liabilities
by Roger Billins; Sweet &
Maxwell, 1999
A good book, practical and worth reading.
Michael P Reynolds
Construction Law Yearbook
1998-1999
To those unfamiliar with this series the book
contains topical articles on construction lawrelated matters, “sanitised” construction
arbitration awards which the authors, via
contributors, have found interesting to the
wider construction law fraternity, previously
hard-to-access case reports, and a construction
law case index that includes cross-references to
standard forms of contract, statutes and court
rules and judicially-considered cases.
This, the fourth volume of the yearbook,
commences with a refreshingly sardonic review
of the 1998 construction law year. It dwells
particularly on the recent developments in
statute-based adjudication and its dependent
contractually-based procedures, with other
sections commenting on the reversal of
Crouch, and the changes to and renaming of
the Official Referee’s Court as the Technology
and Construction Court.
Of particular interest to some will be the
section headed “Adjudication in Peril”, which
offers the view that application of s 26 of the
Scheme for Construction Contracts (via s
114(a) of the Housing Grants, Construction
and Regeneration Act 1996) makes
adjudicators potentially liable to third parties
who suffer loss through their decisions. Whilst
construction contracts usually expressly confer
immunity on adjudicators, and vis-à-vis the
parties s 26 of the Scheme does similarly, there
is thus, according to this editorial, a risk to
adjudicators that many will be unaware of and
which may seem controversial. The
conventional view that adjudication is a roughand-ready, interim means of dispute resolution,
albeit open to review in due course at
arbitration or via the courts, means that there
is a possibility that a wrong decision between
the parties to an adjudication could prejudice
the position of a third party. No example is
offered in the Con L Yb, but the present writer
might suggest a situation where a bondsman is
forced to pay up on insolvency triggered by an
adverse, but patently wrong decision against a
contractor at adjudication. It is to be
Construction & Engineering Law January / February 2000
Book Reviews
This is an essential guide for all practising
solicitors and complements the Law Society’s
Guide to the Professional Conduct of Solicitors
(7th Edition). The author has dealt with some
very important aspects of practice, in
particular the question of retainer by particular
persons, e.g. companies, trustees, liquidators,
agents and the duration of that retainer.
Secondly, he deals with the importance of the
solicitor’s authority to act in contentious and
non-contentious business. This is worth serious
consideration, especially in the context of the
urgency with which certain actions must be
taken, e.g. as to whether or not authority exists
to take urgent action to deal with the
unexpected service of an adjudication notice.
The text also deals with a solicitor’s fiduciary
duty, and conflicts of interest, both of which
are well worth reading about in the context of
Judge Bowsher’s recent decision Maes Finance
Ltd v Sharpe & Partners (see Construction &
Engineering Law, Vol 4, Issue 5) and the recent
cases reported in this issue from the Court of
Appeal. This book is easy to read, logically
presented and proportionate to the importance
of the subject’s various divisions. In particular
I found the references to the Civil Procedure
Rules 1998 useful and noted the wise advice
that the Rule 15 client care letter should
explain to the client in detail what will be
required of the client to ensure compliance
with the court timetable. After reading this it
sparked a few ideas as to how any new Preaction Protocol of the TCC may be linked to
the solicitor’s client-care letter. The TCC’s new
protocol with respect to pre-action matters
might well benefit by some consideration of the
client’s duty to help the court to further the
overriding objective in accordance with Rule
1.3.
.19
Book Reviews
conjectured whether all those who hold
themselves out as construction adjudicators, or
their professional indemnity insurers, have
identified this area of potential risk.
Of the articles included I found the Anthony
Lavers analysis of the Banque Bruxelles and
South Australia decisions (“Professionals
Beware”) of particular interest. Although it
had seemed to me that the dicta of Lord
Hoffmann in the latter needed little subsequent
judicial assistance in interpretation, Professor
Lavers points up the potential for difficulty in
analysing the interrelationship of the advice
given by the team of advisers appointed by a
developer or other client organisation and/or
its funder and the scope of the duty owed by
each member of that team.
The sanitised construction arbitration awards
included are by Messrs Pickavance, Tait and
Willis, all well-known names in the field. They
deal with, respectively, the form of notices in
respect of default and termination under the
ACA standard form of contract and the place
of “business common sense”; jurisdiction in
respect of joinder under clause 18(8) of the
FCEC sub-contract conditions; and the extent
of the arbitrator’s discretion as to costs under s
18(1) of the 1950 Act. These works, so far as
they are unlikely to be replicated by judicial
pronouncement, are useful additions to the
body of reference available to the specialist
practitioner and good examples of awardwriting that would also be of interest to wouldbe arbitrators.
The two cases included are Cadmus
Investment Company v Amec Building Ltd,
which followed the third award published in
this volume, and the well-known Wells v Army
and Navy Co-operative Society first reported
in the Casebook to the 4th Edition of Hudson
of 1914, long out of print.
The greater part of this volume, and its true
utility besides the above goodies, is devoted to
the listings of cases and statutes relevant to
construction law in name order and by subject,
with lists of judicially-considered cases, rules
and other indices. It may surprise non-lawyers
or others unfamiliar with works of this nature
to find that decisions are not given, even in
gist, but the value of this part of the book is the
cross-referencing via topic and judicial
consideration to other cases, all with full and
alternative citations to law reports and articles
in learned journals. Thus the student or
practitioner is referred to the source material
20.
and commentary elsewhere rather than given a
digest capable of misinterpretation or
incomplete understanding through missing
distinguishing factors discernible from the
report itself.
It seems obvious that a work like this would
benefit from computerisation, and indeed this
is part of the package: a CD-ROM containing
the Construction Law Case Index database is
included with the book. There are 1034 case
abstracts, 60 subject headings, 78 statutes or
rules, 40 standard forms and 2266 judicially
considered cases listed in the database.
A complete user manual appears as an
appendix to the book. The database is easy to
install and versatile in use. It is packaged as an
application based on a run-time version of
Folio Bound Views for Windows software,
which allows text-based searching and
hyperlinking. A small criticism may be levelled
at the need to double-click on hyperlinks
rather than the single click usual in other, more
widely-used, software, but this is a quirk that
is readily adjusted to for the power of the
search tool harnessed. When a search for
words is made Boolean logic is automatically
supplied for the user, where necessary, making
this one of the most user-friendly search
engines I have ever used. Upon searching for a
particular word the user is informed of the
number of items that would be retrieved,
allowing addition of other words to limit or
increase the number of entries returned. The
entries themselves appear with the sought
words highlighted to allow immediate contextchecking. The search engine retrieves
according to either text included in the abstract
or by name (or part of a name – a boon to the
nominally
aphasic
construction
law
practitioner). When a case abstract is selected it
appears with head note and cross-referencing
to subject categories, statutes/rules, standard
forms and the judicially considered cases.
Double-clicking on the hyperlink takes the user
to the item shown. Browsing is easy and
speedy.
This work would be worth buying for the CDROM alone. It could quickly become an
essential reference tool for all involved in
construction dispute resolution or any research
related to it. The book itself is a bonus; the
Review and the articles are stimulating, and the
arbitration reports are also of interest.
Chris Ennis
Construction & Engineering Law January / February 2000