Basslink
Basslink | |
---|---|
Location | |
Country | Australia |
Coordinates | Lua error in package.lua at line 80: module 'strict' not found. Lua error in package.lua at line 80: module 'strict' not found. Lua error in package.lua at line 80: module 'strict' not found. Lua error in package.lua at line 80: module 'strict' not found. |
From | Loy Yang Power Station, Victoria |
Passes through | Bass Strait |
To | George Town substation, northern Tasmania |
Ownership information | |
Owner | CitySpring Infrastructure Trust |
Construction information | |
Construction started | 2003 |
Commissioned | 2005 |
Technical information | |
Type | submarine cable |
Type of current | HVDC |
Total length | Lua error in Module:Convert at line 1851: attempt to index local 'en_value' (a nil value). |
Power rating | 500 MW (670,000 hp) |
Basslink is a high-voltage direct current (HVDC) cable link crossing Bass Strait, connecting the Loy Yang Power Station, Victoria on the Australian mainland to the George Town substation in northern Tasmania. It can supply some of the peak load capacity to the mainland of Australia and take some of the excess base load capacity off the coal-fired generators on the mainland to supply Tasmania, leading to reduced pollution. Financial benefits from the Basslink investment included reduced or deferred need to invest in further base load generation facilities, and potential to profit from selling peak load power into a market in which prices are generally higher, and because the cable was also used to supply power to Tasmania in times of drought, as the majority of Tasmania's electricity generation is hydroelectricity. However, "Basslink-related costs have been around $130 million ($ nominal) greater than the actual revenue benefits".[1] This was due to drought conditions reducing hydro production
Contents
History
When the Board of Hydro Tasmania originally entered into a preliminary agreement to build Basslink in 2000, it was projected to cost $500 million.[2] Efforts to prevent corrosion of pipelines and other factors ultimately meant it cost around A$800m to build.[3]
The interconnector was constructed between 2003 and 2005 as an asset of National Grid Australia Pty Ltd, which itself was owned by UK company National Grid plc.
On 1 December 2005, electrical power flowed across Basslink for the first time, as part of the testing procedure. At midnight on the morning of Saturday, 29 April 2006, the link was officially enabled for commercial trading of energy on the National Electricity Market.[4]
On 31 August 2007, CitySpring Infrastructure Trust, a wholly owned subsidiary of Temasek, completed the acquisition of Basslink with a total enterprise value of A$1.175 billion.[5]
2015-2016 outage
See also 2016 Tasmanian energy crisis
On 21 December 2015 it was announced the Basslink was disconnected due to a faulty interconnector approximately 100 kilometres off the Tasmanian coast, Basslink originally announced the cable would be repaired and returned to service by 19 March 2016,[6] however they have since advised the date will not be met and as of 22 February 2016[update] there is no set time for completion of the task.[7]
Due to the loss making situation of the link, and general prognosis, the demise of the company and the link have been speculated upon [8]
Reconnection and repair of the link was set back to June 2016 completion date [9]
By late April 2016, the first stage of the repair of the link was accounced as successful [10]
However some reports suggest that repairs on the cable requires a window of time of 18 days of clear weather, longer than the usual weather patterns that occur in the Bass Strait in winter [11]
Technical description
Basslink is a monopolar with metallic return[12] HVDC operating at a nominal voltage of 400 kV DC. The nominal rating of the link is 500 MW (670,000 hp) although it is capable of transmitting 630 MW (840,000 hp) from George Town to Loy Yang for up to 4 hours.
It consists of:
- 290-kilometre (180 mi) long submarine power cable from McGaurans Beach near Giffard, Victoria to Four Mile Bluff above George Town in Tasmania. The cable weighs 60 kg/m.[13] It is the second longest submarine power cable in the world. (see also NorNed)
- 60.8 kilometres (37.8 mi) overhead power line to the Victorian coast
- 6.6 kilometres (4.1 mi) underground cable in Victoria
- 11 kilometres (6.8 mi) overhead line section to the Tasmanian coast
- 1.7 kilometres (1.1 mi) underground cable in Tasmania.
The pylons of Basslink are of an unusual type. They have two asymmetric crossbars with different lengths. The high voltage line is mounted on the upmost longer crossbar, while the electrode line is carried by the lower smaller crossbar, which shows in the opposite direction.[14]
Communications cable
The Basslink cable also included a run of dark fibre. This is notable as it was the first non–Telstra operated fibre cable crossing Bass Strait. The Tasmanian Government uses it, as well as the TasGovNet fibre backbone, as part of the Connect Tasmania Core infrastructure, to facilitate a more competitive telecommunications industry within the state.[15] The link was also to be used by the now defunct OPEL network.[16]
The Basslink fibre between Loy Yang and Georgetown went into operational testing in April 2009[17] and went live in July 2009.[18]
Basslink Telecoms was officially launched on Thursday 16 July 2009 by the Tasmanian Premier David Bartlett, Federal Minister for Communications Stephen Conroy and Basslink CEO Malcolm Eccles.[19]
Sites
- LoyYang Static Inverter Plant: Lua error in package.lua at line 80: module 'strict' not found.
- Victorian Cable Terminal: Lua error in package.lua at line 80: module 'strict' not found.
- Tasmanian Cable Terminal: Lua error in package.lua at line 80: module 'strict' not found.
- Georgetown Static Inverter Plant: Lua error in package.lua at line 80: module 'strict' not found.
References
- ↑ http://www.electricity.dpac.tas.gov.au/__data/assets/pdf_file/0011/155297/Basslink_-_Decision_Making,_Expectations_and_Outcomes.pdf
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Dark Days Loom For Power Supply. 06/11/2011. The Age
- ↑ Power flows through Basslink. 29/04/2006. ABC News Online
- ↑ [1]
- ↑ [2]
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ http://www.themercury.com.au/news/opinion/talking-point-cable-and-company-may-be-sunk/news-story/c27abfae07080db30a9ee97138960b53
- ↑ http://www.abc.net.au/news/2016-03-31/temporary-diesel-generators-unveilled-meadowbank-power-station/7287076
- ↑ http://www.abc.net.au/news/2016-04-22/basslink-repair-on-track-and-should-be-completed-on-schedule/7350978?section=tas
- ↑ http://www.zdnet.com/article/basslink-subsea-cable-repairs-rely-on-18-days-of-clear-weather/
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ National Grid To Sell Basslink Electricity Interconnector
- ↑ [3]
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Lua error in package.lua at line 80: module 'strict' not found.
- ↑ Basslink launch
External links
- Use Australian English from February 2016
- All Wikipedia articles written in Australian English
- Use dmy dates from February 2016
- Articles containing potentially dated statements from February 2016
- Articles with Geo
- Energy infrastructure completed in 2005
- Submarine power cables
- Electric power transmission systems in Australia
- Communications in Australia
- HVDC transmission lines
- Bass Strait
- 2005 establishments in Australia
- 2016 Tasmanian energy crisis