Available online at www.sciencedirect.com
International Journal of Project Management 29 (2011) 808 – 816
www.elsevier.com/locate/ijproman
Socio-organo complexity and project performance
Dimitris N. Antoniadis a,⁎, Francis T. Edum-Fotwe b , Anthony Thorpe b
a
b
Carillion Ltd., London, UK
Department of Building and Civil Engineering, Loughborough University, UK
Received 31 January 2011; accepted 15 February 2011
Abstract
Technical complexity has always been considered a factor which affects project performance. Scheduling and other mechanisms have been
proposed which allow for the management of these effects. However, the effect of the complexity of interconnections, and in particular those
caused by social interfaces and boundaries between the various teams, have not been investigated. Socio-organo complexity is caused by
interconnections which if not managed could lead to a reduction in performance. Understanding the characteristics of complexity of
interconnections, how these affect project schedule performance and what deductions can be extracted, will enable the development and
implementation of innovative actions and tools that will support the management of the effects of complexity through the respective processes.
The authors present results of five case studies, with UK construction organisations, which demonstrate that the effects of socio-organo
complexity of interconnections have similarities with the behaviour of underdamped control systems. The results from the study have significant
implications for the way socio-organisational issues are managed but will also enable parallels to be drawn between the fields of project
management and control systems.
© 2011 Elsevier Ltd. and IPMA. All rights reserved.
Keywords: Complexity; Interconnections; Projects; Performance; Control systems
1. Introduction
Construction projects, and in particular mega projects, often
involve a large number of parties and subsequently interconnections. These interconnections can generate complexity
which, however, has defined characteristics (Lucas, 2000b).
Complexity on projects has been researched extensively in the
last decade and a number of proposals have been made in terms
of managing its effects (Gidado, 1996; Williams, 2002;
Lillieskold and Ekstedt, 2003; Geraldi, 2008; Girmscheid and
Brockmann, 2008). In terms of the relationship between
complexity and project schedule performance and although
heuristic considerations exist, which suggest an exponentially
decaying/inverse correlation, very little has been done in
identifying the exact relationship. Furthermore, most of the
⁎ Corresponding author. Tel.: +44(0) 7754522049.
E-mail address: dnanton00@googlemail.com (D.N. Antoniadis).
studies have been carried out on the technical side and very
little has been investigated in terms of the socio-organisational
aspects of complexity of interconnections and its effects,
especially when implementing processes such as selecting team
members, structuring the project team, or the management style
adopted. Within this paper the authors present the results from
five case studies investigating the effect of socio-organo
complexity on project schedule performance. The case studies,
part of a wider study into socio-organo complexity, were
carried out in the UK construction industry with some major
organisations. The results indicate that the relationship,
although one of an inverse correlation, does not resemble a
straightforward exponential decay curve but rather one of an
underdamped transient motion. The verification of this
relationship not only confirms the non-linearity of project
management, especially regarding socio-organisational issues,
but it can also be proven very powerful considering the
potential extrapolation and implementation of techniques
already proven in the field of systems control.
0263-7863/$ - see front matter © 2011 Elsevier Ltd. and IPMA. All rights reserved.
doi:10.1016/j.ijproman.2011.02.006
D.N. Antoniadis et al. / International Journal of Project Management 29 (2011) 808–816
809
2. Background
The management of projects transpires in a complex
environment (Bertelsen, 2004). The application of complexity
theory to the management of projects can, therefore, enable the
systematic consideration of the conditions that give rise to such
complexity. A number of authors have indicated that interfaces
generate complexity (Baccarini, 1996; Gidado, 1996; Williams,
2002), however complexity can be associated more with the
interconnection structures that link various objects and not the
objects themselves (Lucas, 2000a). As a result, considering the
prevailing conditions in projects the argument can be easily
juxtaposed to the project environment. In one sense, project
management can be considered as optimisation of the
structuring of the interconnections that link up the delivery
systems and subsystems. Understanding the characteristics of
these interconnections, especially from a socio-organisational
standpoint and how these affect the project performance, can
contribute to the design of more efficient project delivery
systems. In particular, it should enable project managers to
respond with the necessary actions and improve the setting up
of projects, the management style adopted and the decisionmaking process. Lucas (2000b) has suggested that complexity
arising from interconnections reflects distinct characteristics.
The 16 characteristics directly relevant have been mapped onto
project conditions and detailed description has been presented
in Antoniadis et al. (2006).
Construction projects are typically characterised by complexity; under time and/or cost pressure and requiring both
creativity and cooperation and which, for most projects, reflects
a dynamic process involving non-linear procedures (Bertelsen,
2004). Previous analyses of complexity in construction projects
have been conducted mainly from a technical perspective
(Gidado, 1996; Lillieskold and Ekstedt, 2003) and not directly
addressing the effects of complexity on project schedule
performance. Only recently has the subject of complexity
been linked to non-technical project aspects such as communication, behavioural and social issues (Geraldi, 2008; Girmscheid and Brockmann, 2008), again though not directly linked to
the effects of socio-organo complexity of interconnections on
project schedule performance.
Empirically/heuristically it is presumed that as complexity increases performance drops (inverse correlation)
and the expected graphical output resembles that of an
exponentially decaying curve (e.g. e−x ) or a curve similar
to an overdamped system such as that presented in Fig. 1
below. Fig. 1, depicts the theoretical harmonic oscillations
of systems as these come under the influence of various
damping devices.
The overall concept of motion represented in Fig. 1 can be
described by the equation:
d2 xð t Þ
dxðtÞ
+ 2ζωn
+ ω2n xðtÞ = 0
d2 t
dt
ð1Þ
Fig. 1. Harmonic oscillator with damping. Various cases are depicted, from
underdamped to overdamped. As presented in http://www.scar.utoronto.ca/~pat/
fun/NEWT1D/PDF/OSCDAMP.PDF.
1981) which are expressed by the general mathematical
function:
h
i
ð2Þ
x = Aeð−ζωtÞ sin ω √ 1−ζ2 t + a
where:
•
•
The first part of Eq. (2), [Ae(−ζωt)], expresses the exponential
decay element and the second part, [sin(ω(√(1 − ζ2t)) + a)],
expresses the circular frequency element (Beards, 1981).
Therefore, depending on the outcome of the investigation
there could be some correlation between the effect of socioorgano complexity of interconnections onto project schedule
performance and the effect of damping on transient motion.
Also, since much of the socio-organisational complexity is
associated with the organising and the management of projects
these areas form the focus of investigation in this paper.
3. The investigation
The review established the need for further investigation of
the relationship between socio-organo complexity of interconnections, in particular the processes of selecting team
members, structuring project teams and the management style
adopted, and project schedule performance. Therefore the
following Study Question (SQ) was formulated:
SQ 1: Socio-organo complexity of interconnections is inversely
correlated to project schedule performance.
In order to investigate the above question it was decided to
conduct a carefully developed, closed design (Yin, 2003), multiple
case study approach, for 9 weeks or two project reporting periods,
with an adaptive and flexible feedback mechanism. The importance
of implementing multiple case studies was based on the fact that:
Fears of uniqueness and artificial conditions surrounding the
case(s) are minimised; and
• To enable literal replication logic (Yin, 2003).
•
Using the equation of motion (Eq. 1) the graphs depicted
above (Fig. 1) are a combination of two motions (Beards,
ω = undamped natural frequency
ζ = damping ratio
810
D.N. Antoniadis et al. / International Journal of Project Management 29 (2011) 808–816
In considering all the above, it was decided that the most
appropriate method to investigate the study question would be
to monitor and record the reasons for delay of the activities to be
performed in the predefined time and the tool to be used would
be the project programme. Progress would be monitored weekly
by the PM and/or the appropriate Team Leader and reasons for
delay would be selected from a pick list. Working programmes
would have to be at the appropriate level of detail so that the
length of delay could be reasonably recorded and reported
weekly. Pre-arranged meetings with the researcher would
enable clarification of any queries, checking clarity of data
recorded in the performance log supplied and confirming
correctness of process followed. An extensive pick list of
‘reasons for delay’ was developed, focusing essentially on the
three areas under investigation (Table 1 presents an extract from
this list). Each reason was coded and linked to one or more of
the 16 complexity characteristics for ease of use by the case
study PMs. Reasons for delay(s) due to issues/causes raised in
the past were also available from the pick list and when/if used
Table 1
Extract from list for ‘Reasons of activity delay’ given to case study project
managers.
Code
Complexity
characteristic
D300
D700
B300
Self-reproduction
Emergence
Undefined values
—structure
D100
Co-evolution
—team
C500, Attractors/
C300 non-equilibrium
C402
Non-linear
—structure
C420
Non-linear
—management
D400
Downward causation
—team selection
D410
Downward causation
—structure
D420
Downward causation
—management
B100
Unpredictability
D110
C210
Co-evolution
—structure
Instability
—structure
C101,
Autonomous agents
—team
C310 Non-equilibrium
—structure
C211
Instability,
D510
Mutability,
D511
D500
D520
D800
Phase changes
Reason
R01—lack of appropriate level of induction
R03—team cohesion
R04—inter-team issue (please elaborate)
R06—lack of flexibility within the team
R08—no expertise within the
team—external input requested
R09—structure of team required improvement
R10—authoritative approach caused problem
in team
R11—team selection could have been better in
terms of tackling the task
R12—definition of work structure needed
clarification
R13—line of command needed clarification
R14—problem from initial phases of project
re-surfaced and caused delay
R16—communication between team and
others
R17—clarity of communication/instruction
cause confusion to the team which took some
time to react to the misunderstanding
R18—restriction in people availability did not
allow for appropriate level of expertise
R19—unexpected activity due to:
R20—non-availability of material
R21—change in higher level programme
R22—causing an upset in the team (who
probably did it again)
R23—caused by unreasonable insistence by
others
R24—caused by not ‘listening’ to team
feedback/expertise
the PMs would be asked to elaborate during the pre-arranged
meetings. Particular interest was paid to those issues since
‘unpredictability’ (one of the 16 complexity characteristics) or
incumbent pathogens (Busby and Hughes, 2004) causes
increase in complexity. Also, various scenarios were identified
so that these can be discussed with the PMs, in order to
determine instances where complexity had a compounding
effect.
In terms of the approach taken to measure the performance
the ‘simple method’ shown below was discussed and agreed
with participants:
Activity performance = (Duration Planned ∗ % performance
reported); and
• Total performance = (Σ of duration achieved / Σ of Duration
Planned) irrespective of the time elapsed for the activity to be
completed.
•
Five major construction organisations (clients and contractors)
accepted to participate. The number of case studies was
considered appropriate because, as Yin (2003: 32) states, ‘if two
or more cases are shown to support the same theory replication
may be claimed and results will be considered more potent.’
Board Directors were briefed on the requirements and asked to put
forward projects at the three different phases of the project
lifecycle—feasibility, construction and commissioning—and the
case study PMs to have 10 or more years of experience. After
discussions with Board Directors the case study projects were
selected and the respective PMs were briefed extensively on the
purpose and the process to be followed. PMs were asked and they
provided general information about their project and a number of
weekly meetings between the researcher and case study PMs were
arranged.
To prove the relationship between project schedule performance and complexity, and in particular for the 16 complexity
characteristics, the data from the multi-case studies were
analysed following Yin's (2003) five evidence techniques and
also a number of graphs were plotted including ‘weekly % drop
in performance against reason of delay’, ‘frequency of
occurrence of coded reasons for delay’ as well as ‘frequency
of complexity characteristics causing delay’. The results from
the case studies will be deemed acceptable if replication is
established between two or more cases (Yin, 2003) but also by
carrying out validation interviews with PM practitioners from
different organisations.
4. Results
Implementation was over a period of 10 months (2007–
2008) and presentations were given to respective Board
Directors on the aims and objectives of the research and the
case studies. The details of projects put forward by the
companies are shown below in Table 2.
Representative results from two of the five case studies are
given below.
The significance of the drop in performance in case study
G2.1 can be seen in Fig. 2, which displays ‘Cumulative
811
D.N. Antoniadis et al. / International Journal of Project Management 29 (2011) 808–816
Table 2
Case study contributors by project stage.
Company—
case study
Project
stage
Description
G1.3
G1.1.2
G1.1.4
G2.1
G1.2
Feasibility
Design/early construction
Construction
Construction
Commissioning
Waste water treatment works
Terminal forecourt extension
Redevelopment of lounge
Building—28 luxury flats
Chemical removal plant
2003). The results (Figs. 3 and 4) indicate clearly the inverse
correlation between socio-organisational complexity of interconnections and project schedule performance and therefore
prove the study question raised. Also the curves in Figs. 3, 4, and 5
resemble accurately the theoretical curve of underdamped
transient motion (see Fig. 1 above). Furthermore from the results
it is evident that:
The shapes of the project schedule performance curves, in
particular for those case studies in construction (with the
exception of case study G1.1.4 which faced extenuating
circumstances and the team never had the chance to recover),
follow that of the underdamped transient motion curve.
• The results for the case studies at the earlier and latter phases
of the project lifecycles G1.3 and G1.2 do not overrule/distort
the overall outcome. Actually, the exponential decay shape
of the feasibility (Dsgn) case study and the slightly
underdamped shape of the commissioning (cmsng) case
study underpin the findings.
• As described by Moore (2002:66 and 90)—in the team
effectiveness curve—at the early phase of the project,
performance is higher as the team comes together. This can
be observed in case study G1.3 Dsgn where the percentage
drop is reduced by 9%.
• Similarly at the commissioning phase, team members
become anxious about the future, the next project, the new
team and other soft issues (Moore, 2002) and thus, as
commissioning approaches, performance drops. Eventually,
the ‘key players’ (the commissioning team—as described by
the G1.2 PM) deliver the project.
•
Planned’ and the ‘Cumulative Achieved’ durations for the case
study period. As can be seen only 43% of the planned activity
time (or 252 days of the 590) was achieved and as a result the
PM had to delay a number of fit-out tasks.
Overall results, in terms of drop in performance, as well as
the average from all five case studies, are presented below in
graphical form.
Two tables of results with all the complexity characteristics
that affected performance, by sub-process investigated, are
drawn and shown below. Table 3 indicates the frequency of
occurrence of each characteristic, which was represented by one
or more corresponding causes of delay, and Table 4 presents an
analysis of complexity characteristics causing delay by subprocess investigated.
The results were validated by conducting saturation interviews with project management practitioners from different
organisations and from the levels of Project Director to PM. All
interviewees, having reviewed the results, accepted the findings
as a true representation of the current status and the issues they
face when delivering projects (Antoniadis, 2009).
5. Analysis
In order to extract inclusive and integrated deductions as well
as establish replication, the analysis of the case study results is
conducted holistically rather than each one in isolation (Yin,
The results indicate that as the effects of the complexity
characteristics on each activity monitored increase, performance
drops and, as remedial actions are implemented, the effects are
managed and keep the project performance at a plateau. All case
study curves, irrespective of the project phase, support this
finding. Thus the results confirm replication. Results from case
Number of Complexity characteristics & % Drop in Performance
0%
0%
14
10%
13
13
13
20%
12
11
10
12
30%
10
10
43%
8
50%
52%
49%
55%
6
50%
50%
56%
58%
55%
60%
6
70%
4
Drop in Performance
Num of Complexity characteristics
2
0
40%
80%
90%
100%
0
Wk0
% Drop in Performance
Num. of characteristics
11
wk1
Wk2
wk3
wk4
wk5
wk6
wk7
wk8
wk9
Fig. 2. Case study G2.1, % drop in performance against number of complexity characteristics that affected performance.
812
D.N. Antoniadis et al. / International Journal of Project Management 29 (2011) 808–816
Number of Complexity characteristics & % Drop in Performance
10
0%
Drop in Performance
Num of Complexity characteristics
9
10%
7
7
30%
7
40%
6
5
5
5
59%
5
58%
5
58%
62%
4
67%
57%
50%
60%
61%
65%
70%
72%
% Drop in Performance
20%
8
Num. of reasons
0%
80%
2
90%
0
0
Wk0
wk1
Wk2
wk3
wk4
wk5
wk6
wk7
wk8
wk9
100%
Fig. 3. Case study G1.1.2, % drop in performance against number of complexity characteristics that affected performance.
study G1.2—commissioning phase—provide further evidence
of the point made above. Actually the case study, with the
continuous increase in performance, also presents the stage after
the plateau. As the project reaches completion and complexity is
dealt with the number of complexity characteristics causing
delay are gradually reduced in number and performance
increases.
As time elapses and activities are not completed, various
measures are taken to overcome the performance problems. For
example, additional resources might be ‘pulled in’, or other
activities deferred, as is the case with G2.1 where the PM had to
delay groups of fit-out activities to a later stage. Therefore,
expected performance and, in particular, project monitoring
techniques such as Earned Value, the Cost Performance
Indicator (CPI) and Schedule Performance Indicator (SPI)
Table 3
Frequency of occurrence of complexity characteristics which affected
performance per case study and project stage.
Construction
Feasibility Commissioning
Case Case Case Case
study study study study
1.1.2 1.1.4 2.1
1.3
Unpredictability
Non-standard
Undefined values
Autonomous agents
Instability
Non-equilibrium
Non-linear
Attractors
Co-evolution
Self-modification
Self-reproduction
Downward causation
Mutability
Non-uniform
Emergence
Phase changes
B1 9
B2
B3
C1 9
C2 5
C3 9
C4 8
C5
D1 16
D2
D3
D4 17
D5 17
D6
D7
D8 9
9
9
6
9
13
6
4
3
9
12
6
Case
study
1.2
8
9
8
7
8
9
5
12
9
14
18
6
16
6
18
4
4
5
1
7
could be used to present a more complete picture. These,
however, are beyond the scope of this paper.
As data from the case studies were analysed, it became
apparent that, due to the corrective actions taken by the project
teams, most of the graphs resembled that of an underdamped
transient motion (as per Fig. 1), which is a combination of an
exponentially decaying curve together with a circular frequency curve (Beards, 1981). The performance curves of two case
studies, G1.1.4 in construction and G1.3 in design (see xFig. 6),
can be depicted by the exponential decay curve, whereas those
of case studies, G1.1.2 in early construction, and G2.1 in
construction, can be depicted by the function of the underdamped transient motion, which combines both elements of
Eq. (2). Thus, not only has replication been established but also
consistency, with an already proven and established theory.
The only case study that does not accurately conform to these
curves is G1.2 which was at the commissioning phase.
However this can be explained by the fact that the project
was essentially complete just after week 4 of the case study
period. Nevertheless, considering the initial deep drop and the
gradual recovery, it can still be regarded and represented by an
equation of ‘underdamped’ transient motion but in a slower
cyclic mode.
From a brief analysis regarding the impact of complexity
characteristics, using the information provided in Table 3
above and for those case studies in construction, the
complexity characteristics with the highest frequency of
occurrence are detailed below together with the relevant
explanation:
B1: Unpredictability. This represents the importance of the
initial project conditions which, if not managed appropriately, could lead to chaotic conditions occurring later on during
the projects (see also pathogens and incubation period,
Busby and Hughes, 2004);
• C3: Non-equilibrium. Represents the various ‘pulls’ (contractual, behavioural, stakeholder influences, company
•
D.N. Antoniadis et al. / International Journal of Project Management 29 (2011) 808–816
Table 4
Analysis of complexity characteristics causing delay by sub-process.
Phase
Construction
Case
study
Selecting team
members
G1.1.2 Unpredictability
(B1)
Autonomous
agents (C1)
Non-equilibrium
(C3)
Non-linear
(C4)
Co-evolution
(D1)
Phase changes
(D8)
G1.1.4 Unpredictability
(B1)
Autonomous
agents (C1)
Non-equilibrium
(C3)
Non-linear
(C4)
Attractors
(C5)
Co-evolution
(D1)
Selfmodification
(D2)
Emergence
(D7)
G2.1
Unpredictability
(B1)
Autonomous
agents (C1)
Instability
(C2)
Co-evolution
(D1)
Downward
causation (D4)
Mutability
(D5)
Design
G1.3
Undefined
values (B3)
Autonomous
agents (C1)
Instability
(C2)
Non-linear
(C4)
Co-evolution
(D1)
Downward
causation (D4)
Emergence
(D7)
Commissioning G1.2
Autonomous
agents (C1)
Non-equilibrium
(C3)
Co-evolution
(D1)
Self-modification
(D2)
Structuring
the team
Management
style
Instability
(C2)
Non-equilibrium
(C3)
Co-evolution
(D1)
Downward
causation (D4)
Mutability
(D5)
Phase changes
(D8)
Instability
(C2)
Non-equilibrium
(C3)
Co-evolution
(D1)
Downward
causation (D4)
Mutability
(D5)
Phase changes
(D8)
Downward
causation (D4)
Mutability
(D5)
Phase
changes (D8)
Instability
(C2)
Non-equilibrium
(C3)
Co-evolution
(D1)
Mutability
(D5)
Phase changes
(D8)
Mutability
(D5)
Phase
changes (D8)
Instability
(C2)
Non-equilibrium
(C3)
Co-evolution
(D1)
Mutability
(D5)
Phase
changes (D8)
politics and management pressures, to mention but a few)
that occur in projects from the multiple contributors. These,
depending on the situation, will establish semi-stable modes
with ‘players’ (attractors) who will attempt to influence the
project at the opportune moment;
• D5: Mutability. It is typical of random mutations to occur in
projects. Project Managers have to identify and manage
them.
Further detailed results are presented in Antoniadis (2009).
An immediate observation of the results extracted in
Table 4 is the lack of complexity characteristics affecting
the sub-process of management style adopted for the case
studies in design and commissioning. Also of interest, is the
commonality of two complexity characteristics, mutability
and phase changes, which affected all three case studies in
construction. A comment that could be made regarding the
former observation is the relevance of the findings to the
Traveller's Dilemma, people choose or reflect on the events
for their own benefit or exposure, as opposed to the benefit
of the company/organisation for which they work (Basu,
2007).
Further analysis and discussion on the effect complexity
characteristics have on project schedule performance will not
be conducted here as the purpose of this paper is to
demonstrate the relationship and discuss the significant
implications that emanate from the relation between socioorganisational complexity of interconnections and project
schedule performance. The latter is covered in the next
section.
6. Discussion
The detailed case study results and analysis presented
undoubtedly confirm replication. Another observation is
that as the effect of complexity of interconnections
increases, or is not managed, project performance
decreases. The results indicate a significant percentage
drop in project performance for the case studies in
construction, 57% drop, (see Fig. 6) as well as all case
studies, 39% drop, (see Fig. 5). This raises a number of
points regarding project managers' performance and how
this can be improved, the levels of training and the tools
available to them which will enable them to successfully
and satisfactorily manage the project.
Other more generic questions that are raised from the case
study results are:
What has happened in the last 15 years in UK, since the
Latham report, in terms of improving performance of
construction projects?
• Has complexity of interconnections increased considerably
in the construction industry in the last 15 years?
• If project management has remained stuck in a time warp in
the 60s (Morris, 1994) due to the influence of the machine
metaphor (Morgan, 1997), how would new initiatives such as
PRINCE 2 and certification improve performance?
•
Non-equilibrium
(C3)
Attractors
(C5)
Co-evolution
(D1)
813
814
D.N. Antoniadis et al. / International Journal of Project Management 29 (2011) 808–816
Modelling Performance
Wk0
wk1
Wk2
wk3
wk4
wk5
wk6
wk7
wk8
wk9
Cum. Planned Du
Cum Achieved Du
700
600
590
400
300
252
Total Dus
500
200
100
0
Fig. 4. Case study G2.1. Modelling of performance based on Total Duration achieved against time taken.
As the case study data were extracted and analysed, it
became apparent that, due to corrective actions taken by
project managers, the curve resembled that of an underdamped
transient motion. Thus the results confirm, through the well
established theory of vibration analysis and control systems,
the higher order and non-linearity of project management.
This correlation should enable collaboration between the two
disciplines and facilitate a number of activities such as
establishment of variables and how these could be ‘translated’/
used by project management. With the above in mind, some
simple thoughts for further discussion are presented below.
Using the correlation between project performance and
control systems a model can be generated where, by using the
appropriate levels of natural frequency, the complexity
characteristics could be used as damping devices (‘dampers’).
The value allocated to each characteristic/damping device, and
for the corresponding project management sub-process, could
be generated from tools designed to manage each complexity
characteristic. The whole approach could resemble the
treatment prescribed by psychiatrists who use a range of
The results indicate a direct link between project performance and induced socio-organisational complexity of
interconnections and the investigation examined the causes
of delay due to each individual characteristic for the areas
investigated. However, the characteristics of complexity of
interconnections are/should be common to all other project
management sub-processes, e.g. monitoring and control,
efficient use of resources, etc. Thus, more than one complexity
characteristic can have the same cause of delay and similarly,
the same cause of delay could belong to more than one subprocess. Therefore, it is feasible that other sub-processes
contribute to the drop of performance recorded. The overall
drop recorded does not change, but the contributory factors
could simply be wider than those presented in this
investigation.
Understanding how each complexity characteristic affects
each sub-process and identifying actions so that it can be
managed, as described in other parts of the research
(Antoniadis, 2009), enables PM practitioners to take precautionary steps at the appropriate time.
Case Study Performance comparison
0%
CS G1.2 - Cmsng
CS G1.3 - Dsgn
CS G1.1.4 - Cnstr
40%
CS G1.1.2 - Cnstr
CS G2.1 - Cnstr
60%
% Drop in Performance
20%
80%
100%
wk0
wk1
wk2
wk3
wk4
wk5
wk6
wk7
wk8
wk9
Fig. 5. Case studies summary results. Drop in performance due to the effects of complexity.
815
D.N. Antoniadis et al. / International Journal of Project Management 29 (2011) 808–816
% Drop in Performance - Average of all Case Studies
0%
0%
40%
37%
40%
40%
39%
40%
37%
39%
40%
39%
60%
% Drop in Performace
20%
80%
100%
wk0
wk1
wk2
wk3
wk4
wk5
wk6
wk7
wk8
wk9
Fig. 6. Average % performance drop for all case studies.
different medicines to counteract each other in order to achieve
the required outcome.
Therefore, and using the vibration control formula as a guide,
a solution would be to:
a) Minimise the circular frequency element [sin(ω(√(1 − ζ2t)) +
a)],
b) Identify the values of the damping ratio (ζ) and natural
frequency (ω), which then
c) Make the exponential decay function to equal A (see
formula 2 above).
Thus: Ae(− ζωt) = A
In project management this idealistically is interpreted as
performance at 100%, or otherwise 0% drop in performance.
From the above it can be deduced that:
eð−ζωtÞ = 1
which therefore meansð−ζωtÞ = 0
However, the variables t and ω cannot be equal to
zero, as every system has a natural frequency and the
element of time is one of the basic factors in the project
life cycle.
Therefore: ζ = 0
This indicates that those stages that are, in their majority,
governed by the exponential decay function should have the
damping ratio equal to zero.
In terms of the circular frequency function, this will also
have to be equal to zero (0), which means that the lag
between the displacement vector and the force vector is zero
(0).
So:
sin ω √ 1−ζ2 t + a = 0
If from the above ω ≠ 0 and ζ = 0
⇒ω √ 1−ζ2 t + a = ωð√ð1–0ÞÞ + a = ω + a
So sin(± ω + a) = 0, and
∴ðω + aÞ = 0⇒a = −ω;
ð3Þ
or
ð−ω + aÞ = 0⇒a = ω
ð4Þ
From Eq. (3) above, theory indicates that we have a critically
damped system towards which most of the systems are aiming.
In project management terms the above can be graphically
depicted as shown in Fig. 7.
Therefore, with some elemental thinking a number of simple
actions can be taken to define different variables for
understanding non-linearity for which the means can be
developed that will help practitioners reduce the effect of any
type of influence on the project management performance. It is
also possible to utilise and combine concepts developed by
system dynamics to enable the management of the effects of
complexity in projects.
Δt
A
Minimise drop in performance and reduce the spread of
response ∴minimise Δt by adjusting behaviours, fast
enough response, reducing wasted effort, faster
implementation and acceptance of change.
t
Fig. 7. Graphical depiction of underdamped control systems curve applied to
project performance.
816
D.N. Antoniadis et al. / International Journal of Project Management 29 (2011) 808–816
7. Conclusions
Five case studies were conducted in construction projects,
which covered all phases of the project life cycle. Causes of
delay, based on the three sub-processes investigated, were
considered and the results proved the inverse correlation
between complexity of interconnections and project performance. Thus the empirical deduction that project performance
declines as complexity increases is proven. Replication was
established between all five case studies with some minor
variations for the projects in early design and commissioning.
The results indicated a considerable overall average drop in
performance as complexity of interconnections increased
significantly. Analysis of the causes of delay indicated the
dependence of project schedule performance on the subprocesses investigated and the 16 complexity characteristics.
However, the interlinked properties of the characteristics and
those of the reasons for delay did not allow for establishing
singularity of results, or otherwise overcoming the difficulty of
identifying singular characteristics as causes of the drop in
performance. Furthermore the detection of the significant drop
in performance is attributed to the fact that the case studies
sought and extracted details that are not reported frequently, or
seen as small issues that will be overcome, otherwise known as
‘the devil is in the detail’.
The level of training and implementation of appropriate
actions, when selecting project team members, structuring the
project team and when considering the management style to be
adopted, is also questioned by the results obtained. Therefore
the industry will need to consider improving the timing and the
approach taken to implement appropriate techniques. Construction organisations will also need to consider how to improve
adjusting of behaviours and speed of response, reduction of
wasted effort and improving acceptance of change in order to
minimise the effect of complexity of interconnections.
In considering the current approach to the three areas
investigated, which are linked directly to socio-organisational
issues, it can be argued that the effect of not implementing these
has a considerable impact and is interrelated throughout the
complexity characteristics. The non-linearity of project management is also reflected through the effect of the complexity
characteristics. Therefore, a requirement is identified for
developing a framework that will enable the management of
the effects of complexity by means of its characteristics.
Deciphering and mapping the complexity characteristics to the
project management processes enables the consideration and
development of the means, as well as the approach, for
managing its effects on projects.
In addition to establishing the correlation between complexity and project performance, the relationship resembled the
behaviour of vibration control systems (non-linear systems)
and particularly that of underdamped systems. This provides
the basis for further research on the non-linearity of project
management processes by examining possible solutions based
on systems control theory. Further research could be conducted
in:
Establishing an approach that will identify variables which
can be used in known systems formulae, thus enabling PMs
to manage and improve project performance.
• Supporting the establishment of project management axioms
based on the systems dynamics theory, thus providing a
further theoretical basis for supporting project management
as a profession.
•
References
Antoniadis, D.N., 2009. Managing complexity in project teams, PhD Thesis,
Loughborough University, UK.
Antoniadis, D.N., Edum-Fotwe, F.T., Thorpe, A., 2006. Project reporting and
complexity. In: Boyd, D. (Ed.), Proceedings of 22nd Annual Conference
ARCOM, UCE Birmingham. September.
Baccarini, D., 1996. The concept of project complexity—a review. International
Journal of Management Reviews 14 (4), 201–204.
Basu, K., 2007. The traveller's dilemma. Scientific American 296 (6), 68–73
June.
Beards, C.F., 1981. Vibration Analysis and Control System Dynamics. Ellis
Horwood, Chichester.
Bertelsen, S., 2004. Construction management in a complexity perspective. 1st
International SCRI Symposium, 30–31 March 2005, University of Salford,
UK.
Busby, J.S., Hughes, E.J., 2004. Projects, pathogens and incubation periods.
International Journal of Project Management 22 (5), 425–434.
Geraldi, J., 2008. The balance between order and chaos in multi-project firms: a
conceptual model. International Journal of Project Management 26 (4),
348–356.
Gidado, K.I., 1996. Project complexity: the focal point of construction
production planning. Construction Management and Economics 14 (3),
213–225.
Girmscheid, G., Brockmann, C., 2008. Complexity of megaprojects. The
inherent complexity of large scale engineering projects. Project Perspectives
XXIX, 22–26.
Lillieskold, J., Ekstedt, M., 2003. Managing complex IT-projects—a need for a
tool addressing technical and organisational complexity. The Royal Institute
of Technology, Industrial Information and Control Systems, Stockholm,
Sweden.
Lucas, C., 2000a. Setting the scene—science, humanity and interaction. www.
calersco.org Downloaded in August 2005.
Lucas, C., 2000b. The philosophy of complexity. www.calersco.org Downloaded in August 2005.
Moore, D.R., 2002. Project Management: Designing Effective Organisational
Structures in Construction. Blackwell Science, Malden MA.
Morgan, G., 1997. Images of Organisation. Sage, London.
Morris, P.W.G., 1994. The Management of Projects. Thomas Telford, London.
Williams, T.M., 2002. Modelling Complex Projects. John Willey and Son,
Sussex.
Yin, R.K., 2003. Case Studies Research Design Methods. 3rd Edn, Sage.
Thousand Oaks, London.