University of Massachusets Boston
From the SelectedWorks of Jefrey Keisler
2011
Portfolio decision quality
Jefrey Keisler, University of Massachusets Boston
Available at: htp://works.bepress.com/jefrey_keisler/38/
Portfolio Decision Quality
Jeffrey Keisler1
Abstract. The decision quality framework has been useful for integrating decision analytic techniques into decision processes in a way that adds value. This
framework extends to the specific context of portfolio decisions, where decision
quality is determined at both the project level and the portfolio level, as well as in
the interaction between these two levels. A common heuristic says that the perfect
amount of decision quality is the level at the additional cost of improving an aspect of the decision is equal to the additional value of that improvement. A review
of several models that simulate portfolio decision making approaches to illustrates
how this value added depends on characteristics of the portfolio decisions, as does
the cost of the approaches.
2.1 Introduction
The nature of portfolio decisions suggests particular useful interpretations for
some of the elements of decision quality (DQ). Because of the complexity of these
problems, portfolio decision makers stand to benefit greatly from applying DQ.
This chapter aims to facilitate such an application by: characterizing the role of
DA in portfolios; describing elements of portfolio decision quality; defining levels
of achievement on different dimensions of DQ; relating such achievement to value
added (using a value-of-information analogy); and considering the drivers of cost
in conducting portfolio decision analysis (PDA).
It is helpful to start by characterizing the role of DA in portfolio problems,
particularly in contrast to the role of optimization algorithms. Portfolio optimization algorithms range from simple to quite complex, and may require extensive
data inputs. DA methods largely serve to elicit and structure these often subjective
inputs, thereby improving the corresponding aspects of DQ:
A portfolio decision process should frame the decision problem by defining
what is in the portfolio under consideration and what can be considered separately,
who is to decide, and what resources are available for allocation. At their simplest,
Jeffrey Keisler
Management Science and Information Systems Department, College of Management, University
of Massachusetts Boston, Boston, MA, USA, e-mail: jeff.keisler@umb.edu
1
portfolio alternatives are choices about which proposed activities are to be supported, e.g., through funding. But there may also be richer alternatives at the
project level, or different possible funding levels, as well as portfolio level choices
that affect multiple entities. For each project, information may be needed about the
likelihood of outcomes and costs associated with investments – and for portfolio
decisions especially, the resulting estimates should be consistent and transparent
across projects. The appropriate measure of the value of the portfolio may be as
simple as the sum of the project expected monetary values, or as complex as a
multi-attribute utility function of individual project and aggregate portfolio performance; this involves balancing tradeoffs among different attributes as well as
between risk and return, short term and long term, small and large, etc. Decisions
that logically synthesize information, alternatives and values across the portfolio
can be especially complex, as they must comprehend many possible interactions
between projects. Implementation of portfolio decisions requires careful scheduling and balancing to assure that sufficient resources and results will be available
when projects need them.
In practice, it has been common to calculate the value added by PDA as the
difference between the value of the “momentum” portfolio that would have been
funded without the analysis and the value of the (optimal) portfolio ultimately
funded. This idea can be refined to understand the value added by specific analysis
that focuses on any of the DQ elements. This is similar to an older idea of calculating the value of analysis by calculating the value of information “revealed” to
the decision maker by the analysis, and it suggests specific, conceptually illuminating, structural models for the value of different improvements to portfolio decision quality (PDQ).
It is productive to think in terms four steps in the different dimensions of DQ:
No information, information about the characteristics of the portfolio in general,
partial specific information about some aspects of the portfolio in a particular situation, or complete information about those aspects. These steps often correspond
(naturally, as it were) to discrete choices about formal steps to be used in the portfolio decision process. Thus, it’s possible to discuss clearly rather detailed questions about the value added by PDA efforts.
This chapter synthesizes some of my past and current research (some mathematical, some simulation, some empirical) where this common theme has
emerged. Without going to the level of detail of the primary research reports, this
paper will describe how various PDQ elements can be structured for viewing
through this lens. A survey of results shows that no one step is clearly most valuable. Rather, for each step, there are conditions (quantitative characteristics of the
portfolio) that make quality relatively more or less valuable (perhaps justifying a
low-cost pre-analysis or an organizational diagnosis step assessing those conditions).
Several related queries help to clarify how PDQ could apply in practical settings. We consider (briefly) how choices about analysis affect the cost of analysis,
e.g., number of variables, number of assessments, number of meetings, etc. Be-
cause these choices go hand-in-hand with DQ levels that can be valued, this provides a basis for planning to achieve DQ. We review (briefly) case data from several organizations to understand where things stand in current practice and which
elements of DQ might need reinforcement. Finally, in order to illustrate how the
PDQ framework facilitates discussion of decision processes, we review several
applications that describe approaches taken.
The chapter concludes with a PDQ driven agenda to motivate future research. A richer set of decision process elements could be modeled in order to
deepen understanding of what drives PDQ. Efforts to find more effective analytic
techniques can be focused on aspects of portfolio decisions that have the highest
potential value from increased quality. Alternatively, in areas where lower quality
may suffice, research can focus on finding techniques that are simpler to apply.
The relative value of PDQ depends on the situation, and it may be that simple and
efficient approaches ought to be refined for one area in one application setting,
while more comprehensive approaches could be developed for another setting.
2.2 Decision portfolios
A physical portfolio is essentially a binder or folder in which some related documents are carried together, a meaning which arises from the Latin roots port (carry) and folio (leaf or sheet). Likewise, an investment portfolio is a set of individual
investments which a person or a firm considers as a group, while a project portfolio is a set of projects considered as a group. Portfolio decision analysis (PDA)
applies decision analysis (DA) to make decisions about portfolios of projects, assets, opportunities, or other objects. In this context, we can speak more generally
of (a) portfolio (of) decisions. We define a portfolio decision as a set of decisions
that we choose to consider together as a group. I emphasize the word choose because the portfolio is an artificial construct – an element is a member of the portfolio only because the person considering the portfolio deems it so. I emphasize
the word decisions because portfolio decision analysis methods are applied to decisions not to projects or to anything else. A portfolio of project decisions starts
with a portfolio of projects and (often) maps each project simply to the decision of
whether or not to fund it. Likewise, other portfolios of concern may be mapped to
portfolios of decisions.
Considering these decisions in concert is harder than considering them separately. There are simply more facts to integrate and there are coordination costs.
Therefore, decisions are (or ought to be) considered as a portfolio only when there
is some benefit to doing so. That benefit is typically that the best choice in one decision depends on the status of the other decisions.
This chapter will discuss portfolio decision quality (PDQ). This concept
builds on the decision quality (DQ) framework, but considers how characteristics
specific to portfolio decisions may change how DQ is applied so that portfolio
managers can better understand how to design their decision processes.
2.3 Decision quality
Decision quality (Matheson and Matheson, 1998, Howard, 1988, McNamee and
Celona, 1990) is a framework developed by practitioners associated with Stanford
University and Strategic Decisions Group. Their basic story is as follows: At the
time a decision is made, its quality cannot be judged by its outcome. Rather, the
quality of a decision is judged by the process used to make it. There are six dimensions of decision quality: The six elements are: Framing, Alternatives, Information, Values, Logic, and Implementation. The quality of the decision is only as
high as its quality in its weakest dimension. In each dimension, a quality level of
100% is defined to be the point at which marginal effort would not be justified by
the benefit it would produce.
We now aim to extend this idea to portfolio decisions. In this context, we must
consider how DQ manifests at the project (or individual decision) level, at the
portfolio level, and in the interchange between these two levels. That is, in order
for the portfolio decision to be of high quality, the preparation and consideration
of the individual decisions in the portfolio must be of high quality in their own
right. They must also be considered well as a portfolio, and they must be considered at the individual level in a way that facilitates high quality consideration at
the portfolio level and vice versa.
Portfolio
level
Frame
Interchange
Alternatives
Project
level
Information
Logic
Values
Commitments
Fig. 2.1 Decision quality is created the project and the portfolio level
A 100% decision quality level is surely a worthwhile target. But the benefit of
additional analysis is usually hard to quantify. There have been efforts to quantify
the value of additional analysis as if it were additional information (Watson and
Brown, 1978). This approach is hard to apply in general. With portfolio decisions,
there are reasons why it’s not so hopeless. The ultimate value resulting from the
decisions about a portfolio decision is a function of the analytic strategy used
(steps taken to improve decision quality in different dimensions) and certain portfolio characteristics. I have used an approach that has been dubbed optimization
simulation (Nissinen, 2008) to model the value added by the process. This approach works if there is an appropriate way to specify the steps taken and to quantify the portfolio characteristics. I am not sure if it is applicable as a precise tool to
plan efforts for a specific portfolio decision, but it is able to generate results for
simulated portfolios and these give insight that may guide practice.
2.4 Portfolio decision quality
We now discuss how the decision quality framework applies in the context of
portfolio decisions. Note, this is a perspective piece, and so the classifications that
follow are somewhat arbitrary (as may be the classifications of the original decision quality framework), but are intended as a starting point for focusing discussion on the portfolio decision process itself.
2.4.1 Framing
In DA practice, “framing” (drawing rather loosely on Tversky and Kahneman’s
(1981) work on framing effects) typically refers to understanding what is to be decided and why.
In many decisions (single or portfolio), before even discussing facts, it is necessary to have in mind the right set of stakeholders, as it is their views that drive
the rest of the process. There are various methods for doing so (e.g., McDaniels et
al, 1999) and because portfolios involve multiple decisions, it is typical for there
to be multiple stakeholders associated with them.
In portfolio settings, a first step in framing is to determine what the portfolio of
decisions is. Sometimes the decisions are simple fund/don’t fund decisions for a
set of candidate projects. In other situations, it is not as clear. For example, there
might be a set of physical assets the disposition of each of which has several dimensions that can be influenced by a range of levers. Then the portfolio might be
viewed in terms of the levers (what mix of labor investment, capital improvements, new construction, outsourcing, and closure should be applied), the dimensions of disposition (how much should efforts be directed toward achieving efficiency, effectiveness, quality, profitability, growth, and societal benefit), the assets
themselves (how much effort should be applied to each site), or richer combinations of these.
Once the presenting portfolio problem has been mapped to a family of decisions, a key issue in framing is to determine what is in and out of the portfolio of
decisions. The portfolio is an artificial construct, and decisions are considered together in a portfolio when the decision maker deems it so. There is extra cost to
considering decisions as a portfolio rather than as a series of decentralized and
one-off decisions. Thus, the decisions that should be joined in a portfolio are the
ones where there is enough benefit from considering them together to offset the
additional cost. (Note, Cooper et al, 2001, discuss the related idea of strategic
buckets, elements of which are considered together). Such benefit arises when the
optimal choice on one decision depends on the status of other decisions or their
outcomes.
A common tool for framing decisions is to use the decision hierarchy (Howard,
2007), to characterize decisions as already decided policy, downstream tactics
(which can be anticipated without being decided now), out of scope (and not
linked to each other in an important way at this level), or as the strategic decisions
in the current context. Portfolios themselves may also form a hierarchy, e.g., a
company has a portfolio of business units each of which has a portfolio of projects
(e.g., Manganelli and Hagen, 2003). The decision frame, like a window frame, determines what is in view and what is not – what alternatives could reasonably be
considered, what information is relevant, what values are fundamental for the context, etc.
In the standard project selection problem, the most basic interaction between
decisions arises from their drawing on the same set of constrained resources. Thus,
with a set of decision variables x1, …, xn (e.g., the amount of funding for projects
1 to n, or simply whether indicator variable of whether or not to fund the projects)
the decision problem is Max X V(X) s.t. C(X) <= B. The first part of the framing
problem is to determine the elements of X, and the related question of identifying
the constraints B.
The set of all project proposals can be divided into clusters in terms of timing
(e.g., should all proposals received within a given year be considered in concert,
or should proposals be considered quarterly?), department or division (should
manufacturing investments compete with funds alongside marketing investments?) geography, level, or other dimensions. Montiebeller et al (2009) give
some attention to this grouping problem. Even if there are no interactions between
projects other than competition for resources, the larger the set of projects considered within a portfolio, the less likely it is that productive projects in one group
(often a business unit or department) will go without resources while unproductive
projects elsewhere (often in another business unit or department) obtain them.
Related to bounding of decisions in the portfolio problem is defining the constraints. Of course, a portfolio consisting of all proposals received in a 3-month
period ought to involve allocating a smaller budget than a larger portfolio of proposals received over a longer time. But sometimes the budget has to be an explicit
choice. For example, Sharpe and Keelin, 1998, describe their success with the
portfolio at Smithkline Beecham, and in particular how they persuaded management to increase the budget for the portfolio when the analysis showed that there
were worthwhile projects that could not be funded. In this case, the higher budget
required the company to align its R&D strategy with its financial strategy for engaging in capital markets, essentially allowing the portfolio of possible investments to spread over a greater time span. In other cases, allowing the portfolio
budget to vary could imply that R&D projects are competing for funds with investments in other areas, so that the relevant portfolio contains a wider range of
functions.
We see here that portfolio decisions involve distinctions that are not salient in
general. Mapping from a portfolio of issues to a portfolio of decisions (what is to
be decided) frames at the level of the individual projects, although this also necessarily drives how analysis proceeds at the portfolio level. Scoping frames explicitly at the portfolio level, but it automatically affects the primary question at the
project level of whether a proposal is even under consideration. Bounding the solution space in terms of budget/resource constraints frames at the portfolio level,
and has little bearing on efforts at the project level.
2.4.2 Alternatives
In the DQ framework, the quality of alternatives influences the quality of the decision because if the best alternatives are not under consideration, they will simply
not be selected. High quality alternatives are said to be well-specified (so that they
can be evaluated correctly), feasible (so their analysis is not a waste of time), and
creative (so that surprising potential sources of value will not be overlooked). In a
portfolio, there are alternatives defined at the project level (essentially, these are
mutually exclusive choices with respect to one object in the portfolio), and at the
portfolio level (e.g., the power set of projects). At the project level, the simplest
alternatives are simply “select” or “don’t select”. A richer set of alternatives may
contain different funding levels and a specification for what the project would be
at each funding level; although these variations take time to prepare, richer variation at the project level allow for a better mix at the portfolio level. A related issue
is that the level of detail with which projects are defined determines what may be
recombined at the portfolio level. For example, if a company is developing two
closely related products, it may or may not be possible to consider portfolio alternatives including one but not the other product, depending on whether they are defined as related projects (with detail assembled for each) or as a single project.
At the portfolio level, one may consider as the set of alternatives the set of all
feasible combinations of project-level decisions. Here we get into issues of what is
computationally tractable, as well as practical for incorporating needed human
judgments. How alternatives are defined (and compared) at the portfolio level af-
fects what must be characterized at the project level. Where human input is
needed, high quality portfolio level alternatives may be organized with respect to
events (following Poland, 1999), objectives (following value-focused thinking,
Keeney, 1993), or resources (e.g., strategy tables, as in Spradlin and Kutolski,
1999), or constraints, or via interactive decision support tools (e.g., visualization
methods such as heatmaps, as in Kiesling et al, in this volume).
2.4.3 Information
The quality of information about the state of the world (especially as it pertains
to the value of alternatives) is driven by its completeness, its precision, and its accuracy. High quality information about what is likely to happen enables estimates
that closely predict actual value of alternatives. In portfolio decisions, the quality
of information at the project level largely has the same drivers. But rather than
feeding a go/no-go decision about the project in isolation, , this information feeds
choices about what is to be funded within a portfolio, and this can mean that less
detailed estimates of project value are needed. On the other hand, because projects
may be in competition for resources used, project level information about costs
may be more significant in feeding the portfolio decision. Furthermore, as has
been noted, consistency across projects is important – a consistent bias may have
less impact on the quality of the portfolio decision (and its implementation) than a
smaller bias that is less consistent. At the level of the portfolio, interactions between projects are important – synergies and dissynergies, dynamic dependencies
/sequencing, and correlations may all make the value of the portfolio differ from
the value of its components considered in isolation. When these characteristics are
present, the search for an optimal portfolio is not so simple as ranking projects in
order of productivity index to generate the efficient frontier. Therefore, it is important to not only collect this portfolio information appropriately (and perhaps iteratively), but to structure it so as to facilitate later operations.
2.4.4 Values
In decision analysis and other prescriptive approaches to decision making, decision makers seek to select the most preferred option. Much effort may go into
identifying preferences and values in order to facilitate that selection. In valuing a
portfolio of projects, since the options are different possible portfolios, it helps to
construct a value function that comprehends preferences and then represents them
in a form amenable to making the necessary comparisons, i.e., the options that
have higher values ought to be the ones the decision maker prefers. If project value is additive, then high quality on values requires mainly that the value function
include the right attributes and the right weights for each project. If the value function is additive across attributes and across projects, then the best portfolio decision arises from setting the right value function to be incorporated across the set of
projects. A more complex value function, e.g., a non-linear multi-attribute utility
function over the sum of project level contributions, requires that the projects be
characterized and measured in the right terms, but the hard judgments must be
made at the portfolio level. Finally, with portfolio decisions there are often more
stakeholders affected by the set of projects, and who therefore have values to be
integrated. This is an area within PDA where there are numerous common approaches.
Of particular note, at the portfolio level there is often a range of interacting objectives (or constraints). Rather than undertaking the sometimes prohibitive task of
formally structuring a utility function for them all, the portfolio manager may
strive for “balance” (see Cooper et al, 2001, the “SDG grid” in Owen, 1983 and
elsewhere, or Farquhar and Rao, 1976), which is commonly done through 2x2 matrices showing how much of one characteristic and how much of another each
project has. This could include balance: between risk and return, across risks (i.e.,
diversification), benefits and costs, short term and long term, internal and external
measure, one set of stakeholders and another (i.e., fairness), resources of different
types used, balance over time, or other characteristics. Balance grids are easier to
work with conceptually than are convex multi-attribute utility functions with interactive terms. With such grids, and with projects mapped to them, the decision
maker can then envision the effect of putting in or pulling out individual projects,
thus directly relating decisions about individual projects to portfolio level value.
Other interactive approaches utilizing feedback or questions based on an existing
portfolio model may also help to identify values and interactions between them,
e.g., Argyris et al, in this volume.
2.4.5 Logical synthesis
In a standard DA setting, the logic element of DQ means the assurance that information, values and alternatives will be properly combined to yield identify the
course of action most consistent with the decision maker’s preferences. Standard
DA utilizes devices such as decision trees, probability distributions and utility
functions to ensure consistency that the decision maker’s actions and beliefs conform to normative axioms. Certainly, much of this still applies at the project level
within portfolios. Detailed inputs at the project level ought to be logically synthesized to obtain value scores that are then incorporated in the portfolio level decision. For example, in the classic SDG style PDA, decision trees at the project level
identify the ENPV and cost of each project.
If there is minimal interaction between projects, the portfolio level synthesis is
simply to rank projects by productivity index and fund until the budget is ex-
hausted. However, interactions – as mentioned previously – can include synergies
and dissynergies, logical constraints where under some circumstances some combinations of activities may be impossible, while in other cases certain activities
may only be possible if other activities are also undertaken. In simpler cases, it
may be possible to still capture this primarily with simple spreadsheet-level calculations based on the DA derived inputs, but often optimization and math programming techniques are required and in their absence, it is unlikely that an unaided decision maker would be able to approach the best portfolio. When such
techniques are to be used, it is especially important to have coherence between the
algorithms to be deployed and the project level inputs. Furthermore, because optimization models often require simplifying assumptions (as do all models to some
extent), this element of quality may require a feedback loop in which managers
review the results of the model and refine it where necessary. Such feedback is
commonly prescribed in decision modeling (see Fasolo et al, in this volume).
2.4.6 Commitment and implementation.
Producing the desired results once portfolio decisions are made (which SDG calls
Value Delivery) requires effort at the border of project and portfolio management.
At the portfolio level, resources must be obtained and distributed to projects as
planned. The portfolio plan itself, with more precise timing, targets, and resource
requirements must be translated back into detailed project plans, as the initial specifications for all individual approved projects must be organized into a consistent
and coherent set of activities for the organization. Project managers monitor
progress and adapt plans when the status changes. Sets of projects may affect each
others’ execution, e.g., one project might need to precede another or it may be impossible to execute simultaneously two projects that require the same resource. In
this case, in addition to orchestrating a multi-project plan, the portfolio manager
must monitor the fleet of projects and make adjustments to keep them in concordance over time with respect to resource use and product release, etc. One important event that can occur at the project level is failure. When projects really do fail,
the portfolio is better off if they are quickly abandoned. At the project level, this
requires incentives to not hide failure and to move on (as was embodied in Johnson & Johnson’s value of “Freedom to Fail,” Bessant, 2003). All these information flows between projects and between project and portfolio managers benefit if
the portfolio decision process has organizational legitimacy – if it is transparent
and perceived as fair (Matheson and Matheson, 1998).
2.4.7 Interacting levels of analysis
Thus, portfolio decision quality is determined at the project level, the portfolio
level, and in both directions of the interface between those two levels, as shown in
this partial listing.
Table 2.1 Some determinants of portfolio decision quality
Framing
Portfolio level
Interchange between
project and portfolio
levels
Resources and
Which projects are in
Mapping issues to deciwhich portfolio (scoping) sions
budgets (bounding)
Alternatives
Subsets of candidate
projects, portfolio strategies
Information
Project level
Projects suitably decom- Well-specified plans for
posed
multiple funding levels
Specifying synergies, dy- Consistency
namic dependency, correlations between projects
Probability distribution
Values
Utility function, balance
Summary statistics
Attributes & measures
Logical
Optimization
Dealing with dependencies
Decision tree
synthesis
over outcomes
between projects
Implementation
Alignment,
monitoring
Ensuring resource availa- Project management,
bility
incentives, buy-in, etc.
and correcting
Since the required level of each element of decision quality depends on the
value added by that element as well as its costs (we can think of this terms of
bounded rationality), it would help to have a way to measure the value and cost.
Cost of efforts to create decision quality is a subject that has not been much studied, and we shall only consider it in abstract terms in this chapter, but it is not so
difficult to think about – if specific efforts are contemplated, the main cost of
those efforts is the time of the individuals involved, and there are many areas of
management in which methods are applied to quantify such costs, e.g., software
development cost estimation. Value depends on the information and decisions involved, and perhaps other context, which makes it difficult to judge intuitively.
We now explore how models of the portfolio decision process can be used to gain
insight about the way specific efforts affect portfolio value.
2.5 Valuing portfolio decision quality
2.5.1 Four discrete levels of portfolio decision quality
It can be useful in some of these cases to think about four possible levels of information being brought to bear on the decision.
Analytic
estimates
Intuitive estimates
Analog data
Ignorance or equivalent
Fig. 2.2 Four levels of quality resulting from different processes for obtaining and
using information
The first level is “ignorance” – not that decision makers have no information, but
rather that their decisions take a perspective other than that of using the parametric
information they do have. For example, in highly politicized situations, information about project value may have little to do with funding. The value of the portfolio under such a process can be used as a baseline for measuring improvement,
and the process is modeled as if it selects projects at random. The second level is
“analog” portfolio-level information but not about information specific projects.
In this case, a decision rule can be developed that takes into account the characteristics of the average project – or even of the distribution of projects. In the pharmaceutical industry, for example, it is common to use “portfolio-wide averages to
estimate success probabilities for individual projects where assessments have not
been conducted. The third level is information that is intuitive “estimates” that
are situation (or project) specific but non-analytic. For example, qualitative descriptions of project-level characteristics that do not allow as fine comparisons and
algorithmic manipulations as do quantitative descriptions. We can usually model
this level as a noisy version of the true state. The fourth level is “analytic”: complete quantified and vetted information. We can model processes using this level
of information as making decisions based on the true facts. That is artificial, of
course, as in many cases even the best estimate of a project’s value is itself only a
snapshot at one point in time and from one perspective.
These levels correspond to different choices made in structuring the decision
process (and the role of analysis in it). Thus, variations of these four levels can be
incorporated into optimization simulation models allowing us to understand the
value added by improved information that arises from different rules in the decision process.
We now review studies using models to value four portfolio level analytic choices.
2.5.2 Modeling the value of higher quality information.
Keisler (2004) considers the basic question: what is the value of increasing precision of value and cost estimates in PDA. This model assumes that projects are described by their value-to-cost ratios and their costs, that all projects have values
for these parameters drawn from a lognormal distribution, and that the decision
maker can receive either no information, imperfect information, or perfect information about each. The decision maker solves for the optimal funding decision
vector max Fi EV = E((FiriCi) s.t. (FiCi)<=B, where Fi = 1 if project i is funded
and 0 otherwise, B is the available budget, the ri are (in the best guess used for this
simulation study) log normal and Ci are either constants (in the base case study) or
log normal. The partial information state is interpreted as having pre-analysis information about r (and sometimes C), but being disciplined in funding projects in
order of their value-to-cost ratio. The no-information state is interpreted as not applying that discipline (with nothing really implied about what information the decision maker has), and the perfect information state is interpreted as obtaining
high quality project valuation and maintaining the discipline to fund projects in
order of productivity. Partial prioritization is defined as assigning a threshold level
for the productivity index and funding projects that exceed this threshold in random order until funds are exhausted. Thus, with reasonable assumptions based on
empirical data, a simulated portfolio showed that the added value (the increment
from the no-information case) resulting from disciplined prioritization with intuitive value estimates the baseline no-information case to well-disciplined (and being disciplined) is somewhat greater than the additional value attributable to the
obtaining high-quality value estimates, but on the same order of magnitude. As
seen below, the when the budget is sufficient to fund most projects, the value added by a disciplined process alone is almost as great as that added by full analysis.
Depending on other conditions (not shown here), the total value added by analysis
can be as low as 0 (if there is no uncertainty) but often as high as 100%+ of the
baseline portfolio value, which itself is quite substantial (and is consistent with
practitioner experience).
200
180
160
Perfect + Prioritization
140
Partial Information + Prioritization
100
No Information / No prioritization
Portfolio benefit
120
80
60
Partial Information + Partial
Prioritization
40
Perfect Information + Partial
Prioritization
20
0
0
5
10
15
20
25
30
Budget level
35
40
45
50
Fig. 2.3 Value achieved with different levels of information and prioritization in a
simple portfolio
The implication is that portfolio managers should focus first on creating a culture that supports discipline in sticking to prioritization, and only focus on more
precise estimates where there is relatively large uncertainty. Under some circumstances, reasonable shortcuts can yield most of the value added by analysis with
proportionally lower cost of analysis than with the brute-force approach in which
all projects are analyzed. Specifically, if organizational conditions allow for a
well-defined threshold productivity level to be identified before analysis, a project
can be funded or not merely based on whether its value-to-cost ratio exceeds the
threshold. A modified threshold rule works well if there is large variance among
the value-to-cost ratio of different projects: apply triage and fund projects that exceed the productivity threshold by a certain amount, don’t fund projects that fall a
certain amount below, and analyze the rest of the projects so that they can be
funded if after analysis they are shown to exceed the threshold. This model considers the general question of improving estimates. The three other models essentially take this as a starting point and consider choices about which bases of the
value estimate to improve, or, alternatively, what more complex portfolio value
measures should be based on the general value estimates.
Decision analysts who saw these results found them interesting, but also
stressed that analysts do more than obtain precise value estimates. For example,
they make the alternatives better – in particular by identifying a range of alternatives for different funding levels.
2.5.3 Modeling the value of higher quality alternatives
The next model (Keisler, 2011) compares different tactics for soliciting alternatives for various budget levels for each potential investment. In this model, C denotes cost, and each project is assumed to have an underlying value trajectory
(colloquially called a buyup curve):
Vi(Ci) = ri[1–EXP(–kiCi/Cimax)]/[1–EXP(–ki)].
Project level parameter values for the return (ri) and curvature (ki) are drawn
from random distributions. Funding decisions to maximize E(ΣiVi) s.t. Σi Ci <= B
are compared for analytic strategies that result in stronger or weaker information
states about k and r.
As before, in a baseline situation projects are selected at random, after a firstcut analysis, projects are funded based on their productivity parameter, also essentially as before. At the other extreme is the gold standard analysis in which a full
continuum of funding levels and corresponding project values is determined for
each project. In between are strategies where a small number of intermediate alternatives are defined for each project as well as “haircut” strategies that trim each
project’s funding from its requested level, with the rationale that projects tend to
have decreasing returns to scale. If returns to scale are not decreasing, the optimal
portfolio allocates projects either 0 or 100% of their requested funds. Otherwise,
the relative value added by different analytic strategies varies with the distribution
of returns to scale across projects. This study showed value added by generating
project level alternatives can be as high as 67% of the value added by getting precise value estimates for the original simple projects as in the first model, as seen in
Figure 2.4.
Contininuous project funding
levels
160000
P
o
r
t
f
o
l
i
o
140000
Funding proportional to project's
productivity index at full funding
120000
100000
Four possible funding levels per
project
80000
60000
v
a
l
u
e
Each project gets sam e portion
of request (haircuts)
40000
20000
Yes-no funding decisions
0
0
1000
2000
Budget
3000
4000
Fund projects at random
Fig. 2.4 Portfolio value when projects may be funded at intermediate levels
Most of the additional value added can be obtained by either generating an additional one or two intermediate funding level alternatives per project. In some
circumstances, similar gains are possible from applying a formula that utilizes
project-specific information about k along with a portfolio-wide estimate of r, for
a sophisticated type of haircut (layered). The results were sensitive to various parameters. For example, at high budget levels where most of the funding requested
by projects is available, there is little benefit to having additional alternatives between full and no funding.
2.5.4 Modeling the value of higher quality on values
Another PDA technique is scoring projects on multiple attributes, computing total
project value as a weighted average of these scores (e.g., Kleinmuntz and Kleinmuntz, 1999); weights themselves may be derived from views of multiple stakeholders. To understand the value added by this approach, Keisler (2008) simulates
portfolios in which for each portfolio, a set of weights (randomly generated) applies and each project has randomly generated scores on each attribute.
In this model, the portfolio value is the sum of project values, ∑i Vi. Individual
k uses attribute weights Wk, for attributes j = 1 to n. As before, there is a funding
constraint ∑i FiCi <= B. There is a “true weight” wj0 for each attribute, and wjk =
wj0bjk, where b represents an individual bias factor. wj0 are log normal, bjk are log
normal, with parameter values calibrated to available data. The baseline strategy
again funds projects at random, and the gold standard uses correct weights for
each attribute. In between are strategies that may use a subset of the attributes, and
may use equal weights or an imperfect approximation of the correct weights (such
as rank-based weights). Figure 2.5 shows results of a simulation in which one approach identified multiple attributes and estimated their weights.
50%
45%
40%
35%
30%
25%
20%
15%
10%
5%
0%
No info
One
Indiv's top Top attr
attribute
attr
All attrs,
Top attr
All attrs
All attrs,
Top attr
All attrs,
Weights
Fig. 2.5 Percent increase in portfolio value from identifying attributes and weights
Those steps added almost 50% to the baseline portfolio value – as before, a
noteworthy level of improvement. But this study also showed that merely identifying all attributes and giving them equal weighting achieves 70% of the value added from perfect weighting. It also found that using a single individual’s imperfectly assessed weights across all attributes does not add much value beyond that, and
that the frugal step of identifying the most important attribute adds substantial value to the selected portfolio regardless of how many other attributes are identified.
2.5.5 Modeling the value of considering synergies
In each of the previous models, projects interact only through competition for
resources. We now consider the importance of this assumption. In general,
projects may also interact by affecting each other’s value or cost directly. For example, two new products may share a common base technology and thus they
could share the cost of that element if both were pursued, i.e., they have cost synergy. Alternatively, projects can have value synergy, e.g., while each product has a
target market, new markets can be pursued only if multiple products are present
(e.g., peanut butter and chocolate). In these cases where portfolio cost and value is
not actually the sum of individual project cost and value PDA can add value by
identifying such synergies prior to funding decisions. A decentralized PDA will
not identify synergies, but where the process has a specific step built in to identify
synergies, it will most likely identify those that exist. This is not trivial, as the
elements from which potential synergies emerge are not labeled as such – in the
example above, it would be necessary to identify the peanut butter cup market and
this would require creative interaction involving the chocolate and peanut butter
product teams.
The model in Keisler (2005) compares analytic strategies that evaluate all synergies, cost synergies or value synergies against the simplest strategy that considers no synergies and again, a baseline in which projects are not funded or are
funded at random. (This model does not include possible dissynergies, e.g., in
weapon selection problems where if an enemy is going to be killed by one weapon, there is no added value in another weapon that is also capable of killing the
enemy). In this model, each project can require successful completion of one or
more of atomic cost elements, where Sik = 1 or 0 depending on whether or not cost
element k is required to complete project i. Similarly, Rij = 1 or 0 depending on
whether project i is required to achieve value element j. The jth value element is
worth Vj, and the kth cost element costs Ck. Portfolio value is ∑j Vj ∏i Fi Rij, and
portfolio cost is ∑k Ck Maxi FiSik. In the simulation, V and C are drawn from
known distributions, and Rij and Sik have randomly generated values of 0 or 1 with
known probability.
The relative value added by strategies that comprehend synergies compared to
myopic strategies depends on the munificence of the environment (Lawerence and
Lorsch, 1967). At low levels of actual synergy, value added is small because little
is worth funding, and above a saturation point, value added is small because many
projects are already worth funding. At a sweet spot in the middle, completely considering synergies can increase portfolio value more than 100% and in some cases
over 300%. In certain cases, comprehension of the possibility of synergies is a
substantial improvement over the case where each project is evaluated myopically.
Figure _ shows results from a less-extreme cluster of projects simulated in this
study, where cross-project cost synergies were assumed to be present of 30% of
the cost elements in the cluster, and cross-project value synergies were assumed to
be present in 10% of the value elements. In this example, the value of identifying
synergies is substantial, but far more substantial if both cost and value synergies
are both identified. Most important in determining the value added at each level
are the prevalence of synergies between value elements and cost elements of different projects, as well as the relative size of value elements to cost elements (and
thus the likelihood that projects will merit funding even in isolation).
32.8
35
30
Value
25
20
21.2
20.0
21.6
16.2
15
10
5
0
NoValue
NoCost
NoValue
PerfectCost
PerfectValue
NoCost
PartialValue
PerfectCost
PerfectValue
PerfectCost
Information on synergy
Fig. 2.6 Value added by obtaining information about cost and value synergies
among projects
2.5.6 Discussion of model results
In each of the above models, typical analytic strategies observed in practice were
characterized as attempts to obtain and structure a specific set of parameters, the
same set for each project. Each of the models also considered certain frugal strategies that were not necessarily observed in practice, but which could be characterized in terms of the same type of structuring method. The frugal strategies typically involved making optimal use of pre-existing analog-level knowledge about
the portfolio in some areas, while actively acquiring it either through estimates or
analysis in other areas. e.g., project cost, project value, returns to scale, strength of
synergies.
It would not be realistic to work toward a comprehensive model to calculate value
of all sorts of possible analyses in real situations. But a portfolio manager could
make judgments about the salient characteristics of the portfolio. Pre-analysis, we
might ask whether the mean values, the spread of values, or the uncertainty of values for some aspect of the portfolio (levels of synergy, project costs, etc.) are especially large or small. We would then note the implications this has for the value
of different analytic thrusts. Organizations that regularly make decisions about
their portfolios might explore their archival data to help characterize the portfolio
(see Stonebraker and Keisler, in this volume).
2.6 Cost of analysis and organizational requirements
A final set of considerations in choosing a direction for PDA is its cost to the organization (especially if we go by the guideline that 100% decision quality is
where the marginal value of improved quality no longer exceeds its marginal
cost). This section does not present research results, but does provide guidelines
for understanding what drives the cost of a process. Assessment costs ought to
vary systematically with the number of assessments that must be done of each
type. This way of thinking about decision process costs is similar to the way that
computation times for algorithms are estimated – considering how often various
steps are deployed as a function of the dimensions of the problem and then accounting for the cost of each step (and in simpler decision contexts, psychologists
(Payne et al, 2003) have similarly modeled the cost of computation. Beyond assessments, there are organizational hurdles to successfully implementing some approaches. The treatment of both issues below is speculative, but in practice, consultants use similar methods to define the budget and scope for their engagements.
Estimating assessment costs
A: number of projects analyzed,
B: cost of analysis per project
C: number of alternatives generated per project
D: cost per alternative generated/evaluated
E: number of attributes in value function
F: cost of assessing an attribute’s weight
G: cost of scoring a project on an attribute
H: projects per cluster
I: number of value elements
J: number of cost elements
K: cost per synergy possibility checked
Analysis for estimation of project productivity:
AxB
For example, with a portfolio with 30 (=A) projects for which productivity
must be estimated at a cost of $5000 (B) of analysis per project, the cost of analysis would be $150,000.
Analysis for estimation of intermediate alternatives:
AxCxD
For example, with a portfolio with 30 (=A) projects, each having a total of 3
(=C) non-zero funding levels whose cases must be detailed at a cost of $10,000
(=D) per case, the cost of analysis would be $900,000.
Analysis involving use of multiple criteria:
ExF+ExAxG
For example, with a portfolio with 30 (=A) projects being evaluated on 8 (=E)
attributes with a cost of $5000 (=F) per attribute to judge its importance (e.g.,
translate to a dollar scale), and $1000 (= G, e.g., the cost 1 hour of a facilitated
group meeting with 5 managers) to score a single attribute on a single project, the
cost of analysis would be $40,000 + $240,000 = $280,000.
Analysis to identify synergy:
(A / H) x H! x (I +J) K
For example, with a portfolio of 30 (=A) projects divided into clusters of size 5
(=H), searching for potential synergies among 7 (I) value elements and 8 (J) potential value elements at an average cost of $50 per synergy checked (=K, some
short interviews and checked with some brief spreadsheet analysis), the cost of
analysis would be 6 * 5! * (7+8) * $50 = $540,000.
These costs apply only to the parts of analysis that are at the most complete
level. Frugal strategies replace some of the multiplicative cost factors here with
one-time characterizations, and it is also possible to omit some of the analysis entirely. Excluded are certain fixed costs of analysis.
2.7 Observations from practice and from other research
Both the PDQ framework and the associated value-of-analysis as value-ofinformation approach have, in my experience, been useful lenses for examining
organizations’ portfolio decision processes.
At one company (Stonebraker and Keisler, in this volume) this framework facilitated analysis of the process used at a major pharmaceutical corporation. In general, the data showed (at a coarse level) that the organization was putting more effort in where the value added was higher. We were able to identify specific areas
in which it may have spent too much or too little effort developing analytic detail.
This led to discussion about the reasons for such inconsistencies – which were intentional in some cases but not in others –and whether the organization could improve its effectiveness in managing those sub-portfolios.
At another major company (Keisler and Townson, 2006), analysis of the data
from a recent round of portfolio planning revealed that adding more alternatives at
the project level would add substantial value to some of the portfolio by allowing
important tasks on relatively low-priority projects to go ahead, and that this would
be an important consideration for management of certain specific portions of the
portfolio. We were able to identify some simple steps to gain some of this potential value with minimal disruption.
At this same company, we also considered the measures used for project evaluation and were able to find a simpler set of criteria that could lead to the same value as the existing approach – or better if some of the measures were better specified. In another application (described at the end of Keisler, 2008), a quick look at
the portfolio characteristics showed the way to a satisfactory approach involving a
modest amount detail on criteria and weights, to successfully recover from an unwieldy design for a portfolio decision support tool.
Finally, on another PDA effort that covered multiple business units at a major
pharmaceutical company, involved many projects and products with a substantial
amount of interaction in terms of value and cost, and it looked like it would be
very challenging to handle such a volume of high-quality analysis. At the outset of
the project, the engagement manager and I discussed the value of identifying potential synergies in PDA. In setting up the effort, the analysis team divided up to
consider sub-portfolios within which synergies were considered most likely. The
resulting engagement went efficiently and was considered a strong success.
2.8 Research agenda
Within this framework, we can discuss certain broad directions for research. Only
a few pieces of the longer list of decision quality elements were modeled. More
such optimization simulation models could enrich our understanding of what
drives the value of portfolio decision quality. Additionally, the description here of
the elements of PDQ can be fleshed out and used to organize lessons about prac-
tices that have been successful in various situations. As we consider where to develop more effective analytic techniques, we can focus on aspects of portfolio decisions where the value from increased quality would be highest – that is, as it becomes easier to make a decision process perform at a high level, the “100%
quality level” will be higher as will the total value added by the decision process.
Alternatively, in areas where the value added by greater precision etc. is minimal,
research can focus on finding techniques – shortcuts – that are simpler to apply.
The relative value of PDQ depends on the situation, and it may be that simple and
efficient approaches ought to be refined for one area in one application setting,
while more comprehensive approaches could be developed for another setting.
2.9 Conclusions
Interpreting DQ in the context of portfolios allows us to use it for the same purposes as in other decision contexts. We aim to improve decisions as much as is
practical by ensuring that all the different aspects of the decision are adequately
considered. But we also recognize – especially with portfolio decisions – that
many parts of the decision process are themselves costly due to the number of
elements involved, e.g., eliciting probability judgments. Resources for decision
making (as opposed to resources allocated as a result of the decision) are generally
quite limited, and time may be limited as well. Therefore, we can use the DQ
checklist to test whether the resources applied to the decision process match the
requirements of the situation. To the extent we can think in concrete terms of the
drivers of the value added by a decision process, we can use the DQ framework
more skillfully. To the extent that portfolio decisions have common characteristics
that are not shared by other classes of decisions, more detailed descriptions of
their DQ elements help ensure that attention goes to the right parts of the process.
As organizations formally integrate PDA into their planning processes, choices
about what is centralized or decentralized, what is done in parallel, etc. translate in
a clear way to the overhead cost of the process and to the levels of quality and
hence the value added by the process.
References
Argyris N, Figueira JR, Morton A (2011) Interactive Multicriteria Methods in Portfolio Decision
Analysis. In: Advances in Portfolio Decision Analysis, Salo, A, Keisler, J, Morton, A
(eds.) Springer, New York
Bessant J (2003) Challenges in Innovation Management. In: The international handbook on innovation (761-774), LV Shavinina, ed. Elsevier
Cooper RJ, Edgett S, Kleinschmidt E (2001) Portfolio Management for New Products, 2nd edition, Perseus, Cambridge, MA
Farquhar PH, RaoVR (1976) A Balance Model for Evaluating Subsets of Multiattributed Items.
Management Science 22(5):528-539
Fasolo B, Morton A, von Winterfeldt D (2011) Behavioural issues in Portfolio Decision Analysis. In: Advances in Portfolio Decision Analysis, Salo A, Keisler J, Morton A (eds.) Springer, New York
Howard RA (1988) Decision Analysis: Practice and Promise. Management Science 34(6): 679695
Howard RA (2007) The Foundations of Decision Analysis Revisited. In: Advances in Decision
Analysis From Foundations to Applications (32-56), Edwards W, Miles RF, von Winterfeldt D (eds.) Cambridge University Press, Cambridge UK
Keeney RL (1996) Value Focused Thinking. Harvard University Press, Boston, MA
Keisler J, Townson D (2006) Granular portfolio analysis at Pfizer. Presented at POMS Conference. Boston, MA
Keisler J (2008) The value of assessing weights in multi-criteria portfolio decision analysis.
Journal of Multi-Criteria Decision Analysis 15(5-6): 111-123
Keisler, J (2011) The value of refining buyup alternatives in portfolio decision analysis. UMass
Boston College of Management Working Paper UMBCMWP 1048
Keisler J (2004) Value of information in portfolio decision analysis. Decision Analysis 1(3):
177-189
Keisler J (2005) When to consider synergies in project portfolio decision analysis, UMass Boston College of Management Working Paper
Kiesling E, Gettinger J, Stummer C, Vetschera V (2011) An Experimental Comparison of Two
Interactive Visualization Methods for Multi-Criteria Portfolio Selection. In: Advances in
Portfolio Decision Analysis, Salo A, Keisler J, MortonA (eds.) Springer, New York
Kleinmuntz CE, Kleinmuntz DN (1999) A strategic approach to allocating capital in healthcare
organizations. Healthcare Financial Management 53(4):52-58
Lawerence P, Lorsch D (1967) Organization and Environment. Harvard Business School Press,
Boston, MA
Manganelli R, Hagen BW (2003) Solving the Corporate Value Enigma. American Management
Association, New York
Matheson D, Matheson JE (1998) The Smart Organization. Harvard Business School Press.
Boston, MA
McDaniels TL, Gregory RS, Fields D (1999) Democratizing Risk Management: Successful Public Involvement in Local Water Management Decisions. Risk Analysis 19(3): 497-510
McNamee J, Celona P (2001) Decision Analysis for the Practitioner 4th Ed. SmartOrg, Inc.,
Menlo Park, CA
Montibeller G, Franco LA, Lord E, Iglesias A (2009) Structuring resource allocation decisions:
A framework for building multi-criteria portfolio models with area-grouped options. European Journal of Operational Research 199(3):846-856
Nissinen J (2007) The Impact of Evaluation Information in Project Portfolio Selection. Masters
Thesis Helsinki University of Technology
Owen DL (1984) Selecting Projects to Obtain a Balanced Research Portfolio. In: Readings on
the Principles and Applications of Decision Analysis, Howard RA, Matheson, JE (eds.)
Strategic Decisions Group, Menlo Park, CA
Payne JW, BettmanJR, Johnson JR (2003) The Adaptive Decision Maker. Cambridge University
Press, Cambridge, UK
Poland WB (1999) Simple probabilistic evaluation of portfolio strategies. Interfaces29: 75–83
Sharpe PT, Keelin T (1998) How SmithKline Beecham makes better re-source-allocation decisions. Harvard Business Review 76(2): 45-57
Spradlin CT, Kutoloski DM (1999). Action Oriented Portfolio Management. Research Technology Management 42(2): 26-32
Stonebraker J, Keisler J (2011) Characterizing the analytical process used in evaluating the
commercial potential of drug development projects in the portfolio for a large pharmaceutical company. In: Advances in Portfolio Decision Analysis, Salo A, Keisler J, Morton A
(eds.) Springer, New York
Tversky A, Kahneman D (1981) The framing of decisions and the psychology of choice. Science
30 211 (4481): 453-458
Watson SR, Brown RV (1978) The Valuation of Decision Analysis. Journal of the Royal Statistical Society A-141: 69-78